Question
Chapter 15, Problem 1CS
Summary Introduction
Case summary:
The case deals about the store that manufactures old Oregon tables. There are four employees (Person T, Person G, Person L, and Person C), who deal with the operations such as preparation, assembly, finishing, and packaging. Each one would deal with a specific operation. However, all the four are able to do all the four operations. Person R is hired to perform major duties and help when the employees are absent. The time taken by each employee to perform every task is as follows:
Preparation | Assembly | Finishing | Packaging | |
Person T | 100 | 60 | 90 | 25 |
Person G | 80 | 80 | 60 | 10 |
Person L | 110 | 90 | 80 | 10 |
Person C | 120 | 70 | 100 | 25 |
Person R | 110 | 80 | 100 | 10 |
To determine: The fastest way to manufacture the tables using original crew of four employees.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
QUESTIONS:
1. A production department of a textile firm received six different orders this week. They have
calculated the processing time presented as a table (below). They have also put the due dates for
each job.
Job
с
E
B
D
F
Process.
Time
2
4
5
8
10
12
Due
Date
7
4
15
16
17
18
Based on the table please provide four sequences to complete the jobs:
a) Using first come first served (FCFS) assuming the letters represent the order they arrive (A first, B
next, then C, etc..)
b) Using shortest processing time
c) Using longest processing time
d) Using due dates
Calculate "average completion time", "average number of jobs in the system" and "average job lateness"
for all the sequences you have generated above.
How can a work breakdown structure contribute to scope creep prevention?
2
Chapter 15 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
Ch. 15 - Prob. 1EDCh. 15 - Prob. 1DQCh. 15 - Prob. 2DQCh. 15 - Prob. 3DQCh. 15 - Prob. 4DQCh. 15 - Prob. 5DQCh. 15 - Prob. 6DQCh. 15 - Prob. 7DQCh. 15 - Prob. 8DQCh. 15 - Prob. 9DQ
Ch. 15 - Prob. 10DQCh. 15 - Prob. 11DQCh. 15 - Prob. 12DQCh. 15 - Prob. 13DQCh. 15 - Prob. 1PCh. 15 - Prob. 2PCh. 15 - Prob. 3PCh. 15 - Prob. 4PCh. 15 - Prob. 5PCh. 15 - Prob. 6PCh. 15 - Prob. 7PCh. 15 - Prob. 8PCh. 15 - Prob. 9PCh. 15 - Prob. 10PCh. 15 - Prob. 15PCh. 15 - Prob. 16PCh. 15 - Prob. 17PCh. 15 - Prob. 18PCh. 15 - Prob. 19PCh. 15 - Prob. 20PCh. 15 - Prob. 21PCh. 15 - Prob. 22PCh. 15 - Prob. 23PCh. 15 - Daniels Barber Shop at Newark Airport is open 7...Ch. 15 - Given the following demand for waiters and...Ch. 15 - Prob. 1CSCh. 15 - Prob. 2CSCh. 15 - Prob. 3CSCh. 15 - Prob. 4CSCh. 15 - Prob. 1.1VCCh. 15 - Prob. 1.2VCCh. 15 - Prob. 1.3VCCh. 15 - Prob. 2.1VCCh. 15 - Prob. 2.2VCCh. 15 - Why is seniority important in scheduling servers?Ch. 15 - Prob. 2.4VC
Knowledge Booster
Similar questions
- time (hours) pH 7.00 7.30 6.99 7.00 Assignment 1 2 7.12 7.25 7.12 7.20 3 720 7.16 720 7.16 4 6.98 7.00 6.94 7.00 5 6.99 6.99 6.99 6.98 6 7.00 6.93 7.02 6.93 7 6.92 7.00 6.92 7.02 Construct the X-Bar charts and R- charts 6.88 6.82 6.94 6.99 7.10 7.00 7.00 7.00 for reporting your results 10 721 7.02 721 7.04 11 7.01 6.86 7.01 6.90 12 6.86 6.98 6.90 6.98 13 6.90 7.00 6.87 7.00 14 7.01 7.04 7.01 7.05 15 7.00 6.95 7.00 6.99 16 7.09 7.20 7.03 7.20 17 6.89 7.14 6.87 7.15 18 6.98 6.80 6.98 6.89 19 7.00 6.90 7.00 6.90 20 7.20 7.00 723 7.00 21 7.04 7.03 7.08 7.00 22 6.90 6.92 6.98 6.92 23 7.00 7.00 7.00 7.00 24 7.00 6.97 7.01 6.98arrow_forwardRequired: Develop a schedule for hiring new employees. What is thetotal cost of this schedule?arrow_forwardWhat is Workload method?arrow_forward
- Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes. Question: Balance this line using the longest task time heuristic. Work Task Task Time (seconds) Task Predecessor(s) A 70 - B 60 A C 120 B D 60 - E 240 C, D F 100 A G 190 E, Farrow_forwardplease give me a brief solutionarrow_forwardHow can I Describe and explain the intended staff traffic flow/ workflow? in Charleston SC Downtown area?arrow_forward
- Mangement question Alpha Enterprises is a company manufacturing water geysers. The company has a functional structure with four main functions-Production, Marketing, Finance and Human Resource. As the demand for the product grew, the company decided to hire more employees. Identify the concept which will help the Human Resource Manager in deciding the actual number of persons required in each department.arrow_forwardQuestion 3 of 19 The following table contains information concerning four jobs that are awaiting processing at a work center. Job Time Due date (days) (days) 14 10 7 6 Job A B C D Determine the average flow time using the EDD rule. Select the correct response: 20 20.5 19.75 21 20 16 15 17 ProviQUSarrow_forwardJobs Work Centre 1 Work Centre 2 A 10 8 B 5 7 C 12 6 D 9 9 E 7 10 F 13 9 G 12 12 H 5 15 Questions: Based on the above table Find the sequence of jobs that minimizes the total elapsed time to complete them Determine the total flow time for each work centrearrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.