
Concept explainers
a)
To determine: Sequence of jobs based on decision rule First Come First Served (FCFS).
Introduction: First Come First Served is the
a)

Answer to Problem 19P
The sequence is A-B-C-D-E.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Due date |
A | 110 | 20 | 180 |
B | 120 | 30 | 200 |
C | 122 | 10 | 175 |
D | 125 | 16 | 230 |
E | 130 | 18 | 210 |
All the jobs are arrived on day 130.
Determine the sequence of the job using FCFS:
Job sequence | Processing time | Flow time | Due date | Start day | End day | Lateness |
A | 20 | 20 | 180 | 130 | 149 | |
B | 30 | 50 | 200 | 150 | 179 | |
C | 10 | 60 | 175 | 180 | 189 | 14 |
D | 16 | 76 | 230 | 190 | 205 | |
E | 18 | 94 | 210 | 206 | 223 | 13 |
Total | 94 | 300 | 27 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 130.
End day of Job A:
Jobs arrival rate is given as 130. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 149.
End day of Job B:
Start day of Job B is the next day of the end day of Job A. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 179.
End day of Job C:
Start day of Job C is the next day of the end day of Job B. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 189.
End day of Job D:
Start day of Job D is the next day of the end day of Job C. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 205.
End day of Job E:
Start day of Job E is the next day of the end day of Job D. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job E is 223.
Lateness of Job A, Job B, and Job D:
End day of Job A, Job B, and Job D is less than its respective due date. Hence, there would be no lateness.
Lateness of Job C:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job C is 14.
Lateness of Job E:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job E is 13.
b)
To determine: Sequence of jobs based on decision rule Earliest Due Date (EDD).
Introduction: Earliest Due Date is the scheduling rule, which helps to arrange the sequence in the order. Here, the job with the earliest due date would be served first. Then, the process would be going on from the earliest due date to the latest due date.
b)

Answer to Problem 19P
The sequence is C-A-B-E-D.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Due date |
A | 110 | 20 | 180 |
B | 120 | 30 | 200 |
C | 122 | 10 | 175 |
D | 125 | 16 | 230 |
E | 130 | 18 | 210 |
All the jobs are arrived on day 130.
Determine the sequence of the job using EDD:
Job sequence | Processing time | Flow time | Due date | Start day | End day | Lateness |
C | 10 | 10 | 175 | 130 | 139 | |
A | 20 | 30 | 180 | 140 | 159 | |
B | 30 | 60 | 200 | 160 | 189 | |
E | 18 | 78 | 210 | 190 | 207 | |
D | 16 | 94 | 230 | 208 | 223 | |
Total | 94 | 272 |
Working note:
Duration and due date for the jobs have been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 130. The job should be arranged based on due date. Due date should be assembled in the ascending order.
End day of Job C:
Jobs arrival rate is given as 130. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 139.
End day of Job A:
Start day of Job A is the next day of the end day of Job C. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 159.
End day of Job B:
Start day of Job B is the next day of the end day of Job A. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 189.
End day of Job E:
Start day of Job E is the next day of the end day of Job B. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job E is 207.
End day of Job D:
Start day of Job D is the next day of the end day of Job E. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 223.
Lateness of Job A, Job B, Job C, Job D, and Job E:
End day of all the jobs is less than its respective due date. Hence, there would be no lateness.
c)
To determine: Sequence of jobs based on decision rule Shortest Processing Time (SPT).
Introduction: Shortest Processing Tine is the scheduling rule which helps to arrange the sequence in the order. Here, the job with the shortest duration would be served first. Then, the process would be going on from shortest to largest duration.
c)

Answer to Problem 19P
The sequence is C-D-E-A-B.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Due date |
A | 110 | 20 | 180 |
B | 120 | 30 | 200 |
C | 122 | 10 | 175 |
D | 125 | 16 | 230 |
E | 130 | 18 | 210 |
All the jobs are arrived on day 130.
Determine the sequence of the job using SPT:
Job sequence | Processing time | Flow time | Due date | Start day | End day | Lateness |
C | 10 | 10 | 175 | 130 | 139 | |
D | 16 | 26 | 230 | 140 | 155 | |
E | 18 | 44 | 210 | 156 | 173 | |
A | 20 | 64 | 180 | 174 | 193 | 13 |
B | 30 | 94 | 200 | 194 | 223 | 23 |
Total | 94 | 238 | 36 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 130. The job should be arranged based on the duration (processing time). The duration should be assembled in the ascending order.
End day of Job C:
Jobs arrival rate is given as 130. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 139.
End day of Job D:
Start day of Job D is the next day of the end day of Job C. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 155.
End day of Job E:
Start day of Job E is the next day of the end day of Job D. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job E is 173.
End day of Job A:
Start day of Job A is the next day of the end day of Job E. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 193.
End day of Job B:
Start day of Job B is the next day of the end day of Job A. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 223.
Lateness of Job C, Job D, and Job E:
End day of Job C, Job D, and Job E are less than its respective due date. Hence, there would be no lateness.
Lateness of Job A:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job A is 13.
Lateness of Job B:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job B is 23.
d)
To determine: Sequence of jobs based on decision rule Longest Processing Time (LPT).
Introduction: Largest Processing Tine is the scheduling rule, which helps to arrange the sequence in the order. Here, the job with the largest duration would be served first. Then, the process would be going on from largest to shortest duration.
d)

Answer to Problem 19P
The sequence is B-A-E-D-C.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Due date |
A | 110 | 20 | 180 |
B | 120 | 30 | 200 |
C | 122 | 10 | 175 |
D | 125 | 16 | 230 |
E | 130 | 18 | 210 |
All the jobs are arrived on day 130.
Determine the sequence of the job using LPT:
Job sequence | Processing time | Flow time | Due date | Start day | End day | Lateness |
B | 30 | 30 | 200 | 130 | 159 | |
A | 20 | 50 | 180 | 160 | 179 | |
E | 18 | 68 | 210 | 180 | 197 | |
D | 16 | 84 | 230 | 198 | 213 | |
C | 10 | 94 | 175 | 214 | 223 | 48 |
Total | 94 | 326 | 48 |
Working note:
Duration and due date for the jobs have been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 130. The job should be arranged based on the duration (processing time). The duration should be assembled in the descending order
End day of Job B:
Jobs arrival rate is given as 130. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 159.
End day of Job A:
Start day of Job A is the next day of the end day of Job B. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 179.
End day of Job E:
Start day of Job E is the next day of the end day of Job A. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job E is 197.
End day of Job D:
Start day of Job D is the next day of the end day of Job E. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 213.
End day of Job C:
Start day of Job C is the next day of the end day of Job D. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 223.
Lateness of Job B, Job A, Job E, and Job D:
End day of Job B, Job A, Job E, and Job D are less than its respective due date. Hence, there would be no lateness.
Lateness of Job C:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job C is 48.
Summary:
Scheduling rule | Average lateness | Average flow time | Average number of jobs in system |
FCFS | 5.4 | 60.0 | 3.2 |
EDD | 0.0 | 54.4 | 2.9 |
SPT | 7.2 | 47.6 | 2.5 |
LPT | 9.6 | 65.2 | 3.5 |
First Come First Served (FCFS):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 5.4.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 60.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 3.2.
Earliest Due Date (EDD):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 0.0.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 54.4.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.9.
Shortest Processing Time (SPT):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 7.2.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 47.6.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.5.
Longest Processing Time (LPT):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 9.6.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 65.2.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 3.55.
Hence, Earliest Due Date is the best method for the average lateness. Shortest processing time has the minimum average flow time and average number of jobs in systems.
Want to see more full solutions like this?
Chapter 15 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
- How does wellness reflect and impact the past and the future of our health as a workout routine? What are the obstacles during the workout routine, and how do you overcome the obstacles? What are the best solutions to plan and accomplish the wellness?arrow_forwardMy last question! Thank you all for helping me better understand how OM works. If you can assist me for this one I'd be very thankful. Can you explain it step by step?I know now that LS is late start, and ES is early start. - •Activities on the critical path are? •The total project completion time for Rafay Ishfaq's software firm is how many weeks?•Determine the slack time for each of the activities for A-F •What is the total slack for the non critical paths in Rafays project?arrow_forwardThank you so much! I was able to answer C without help! Can you assist me with slack time for A-F? I believe A=0arrow_forward
- There's 8 parts, but I need some help with them. I always get confused on which is most critical of a patharrow_forwardMenu Item Sales and Cost Data Taco Salad: Number Sold: 127; Item Cost: $0.71; Selling Price: $3.25 Lasagna: Number Sold: 48; Item Cost: $0.92; Selling Price: $4.67 Chicken: Number Sold: 31; Item Cost: $1.20; Selling Price: $3.00 Green Beans: Number Sold: 14; Item Cost: $0.20; Selling Price: $1.00 Corn: Number Sold: 13; Item Cost: $0.24; Selling Price: $1.00 Rice: Number Sold: 9;Item Cost: $0.13; Selling Price: $1.00 Menu Item Classification: Low contribution margin, low menu mix % DOG High contribution margin, low menu mix % PUZZLE Low contribution margin, high menu mix % PLOWHORSE High contribution margin, high menu mix o/o STAR QUESTION 1 Complete the menu analyses worksheet below. Calculations will be done using the information above. Restaurant: Date: MealPeriod: (A) ☐ (B) (C) (D) (E) (F) (G) (H) (1) (J) Menu Mix Popularity % Item Item Sold/(Menu Mix Menu Menu Item Food Menu Contribution Contribution Contribution Category Item Mix %): (B/K) Cost Selling Margin Price Margin (E-D)…arrow_forward1) Around the Clock Production of Fire Nozzles View the videos Around the Clock Production of Fire Nozzles 1 https://media.gaspar.mheducation.com/GASPARPlayer/play.html?id=132KoZwS0yMEgsToDUsZjJe (9.44 minutes, Ctrl+Click on the link) and Around the Clock Production of Fire Nozzles 2 https://media.gaspar.mheducation.com/GASPARPlayer/play.html?id=44JM0cKtFLqHP5bad6KOHAm (7.43 minutes, Ctrl+Click on the link); what are your key takeaways (tie to one or more of the topics discussed in Chapters 12 and/or 13) after watching these videos. Note: As a rough guideline, please try to keep the written submission to one or two paragraphs. 2) Cyberdyne Systems stocks and sells Cyberdyne glucose meters. The firm gathered the following information from its South Pasadena office: Demand = 19,500 units per year Ordering cost = $25 per order Holding cost = $4 per unit per year The firm’s operations manager wants to calculate the: a) EOQ for the glucose meters. b) Annual holding costs for the…arrow_forward
- In the following problems assume, unless otherwise stated, that S = $40, σ = 30%, r =8%,and δ =0. 13.1 Suppose you sell a 45-strike call with 91 days to expiration. What is delta? If the option is on 100 shares, what investment is required for a delta-hedged portfolio? What is your overnight profit if the stock tomorrow is $39? What if the stock price is $40.50?arrow_forwardQuestion 1 M&H company ltd. sells television sets and has collected monthly sales data (in units) for the past 12 months as shown in table 1below: TABLE 1 Month Sales (Units) 1 120 2 135 3 150 4 165 5 180 6 200 7 195 8 210 9 225 10 240 11 255 12 270 Using the data provided, answer the following questions: a. Using a 3-month weighted moving average with weights 0.5, 0.3, and 0.2 (most recent month having the highest weight), calculate the forecast for month 13. [2 marks] b. If the company applies an exponential smoothing method with a smoothing constant (a) = 02, and assumes an initial forecast of 120 units for Month 1, calculate the forecast for month 13. [6 marks] c. Calculate the Mean Absolute Deviation (MAD) for the exponential smoothing method and weighted moving average method using the actual sales data for Months 4 to 12 and determine which method is more accurate. [8 marks] d. Compute the values of a (intercept) and b (slope) using the least squares method. [7 marks] e. Use the…arrow_forwardQuestion 4 MGM12026 Production and Operations Management semester il 2024 A company operates a manufacturing plant that produces two products, A and B. The plant has the following capacity data: . . Design Capacity: 15,000 machine hours per month Effective Capacity: 12,000 machine hours per month Actual Output (Utilized Capacity): 10,000 machine hours per month Additionally, the plant produces Product A and Product B, with the following production data: Product Demand (Units) Processing Time Contribution Margin ($ (hours per unit) per unit) A 3,000 2.5 40 B 4,000 1.5 30 a. Calculate the plant's i. Capacity Utilization [3 marks] ii. Effective Capacity Utilization [3 marks] iii. Efficiency. Interpret the results. [3 marks] b. Compute the total machine hours required to meet full demand for both products. [5 marks] c. Determine whether the plant has sufficient capacity to meet full demand. If not, calculate the shortfall in machine hours. [3 marks] d. Using the contribution margin per…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Foundations of Business (MindTap Course List)MarketingISBN:9781337386920Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage LearningFoundations of Business - Standalone book (MindTa...MarketingISBN:9781285193946Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage Learning


