To determine: Thejob sequence, flow time, utilization metric, average number of jobs, and average lateness for EDD, SPT, LPT, and FCFS.
Introduction:
a)

Answer to Problem 18P
The values in the given table have been computed.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Date order due |
BR-02 | 228 | 15 | 300 |
CX-01 | 225 | 25 | 270 |
DE-06 | 230 | 35 | 320 |
RG-05 | 235 | 40 | 360 |
SY-11 | 231 | 30 | 310 |
All the jobs are arrived on day 241.
Table to compute:
Dispatching rule | Job sequence | Flow time | Utilization rating | Average number of jobs | Average lateness |
EDD | |||||
SPT | |||||
LPT | |||||
FCFS |
Computed table:
Dispatching rule | Job sequence | Flow time | Utilization rating | Average number of jobs | Average lateness |
EDD | CX-BR-SY-DE-RG | 385 | 37.60% | 2.66 | 10 |
SPT | BR-CX-SY-DE-RG | 375 | 38.60% | 2.59 | 12 |
LPT | RG-DE-SY-CX-BR | 495 | 29.30% | 3.41 | 44 |
FCFS | CX-BR-DE-SY-RG | 390 | 37.20% | 2.69 | 12 |
Supporting calculation:
Determine the sequence of the job using FCFS:
Processing time | Due date | Flow time | Completion time | Late | |
BR-02 | 15 | 300 | 15 | 265 | 0 |
CX-01 | 25 | 270 | 40 | 280 | 0 |
DE-06 | 35 | 320 | 75 | 315 | 0 |
RG-05 | 40 | 360 | 115 | 345 | 35 |
SY-11 | 30 | 310 | 145 | 385 | 25 |
Total | 390 | 60 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 241.
First Come First Served (FCFS):
Completion day of CX-01:
Jobs arrival rate is given as 241. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 265.
Completion day of BR-02:
Start day of BR-02 is the next day of the completion day of CX-01. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 280.
Completion day of DE-06:
Start day of DE-06 is the next day of the completion day of BR-02. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day of DE-06 is 315.
Completion day of SY-11:
Start day of SY-11 is the next day of the completion day of DE-06. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day of SY-11 is 345.
Completion day of RG-05:
Start day of RG-05 is the next day of the completion day of SY-11. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day of RG-05 is 385.
Lateness of CX-01, BR-02, and DE-06:
Completion day of CX-01, BR-02, and DE-06 is less than its respective due date. Hence, there would be no lateness.
Lateness of SY-11:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 35.
Lateness of RG-05:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 25.
Determine the sequence of the job using SPT:
Processing time | Due date | Flow time | Completion time | Late | |
BR-02 | 15 | 300 | 15 | 255 | 0 |
CX-01 | 25 | 270 | 40 | 280 | 10 |
SY-11 | 30 | 310 | 70 | 310 | 0 |
DE-06 | 35 | 320 | 105 | 345 | 25 |
RG-05 | 40 | 360 | 145 | 385 | 25 |
Total | 375 | 60 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 241.
Shortest Processing Time (SPT):
Completion day of BR-02:
Jobs arrival rate is given as 241. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 255.
Completion day of CX-01:
Start day of CX-01 is the next day of the completion day of BR-02. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 280.
Completion day of SY-11:
Start day of SY-11 is the next day of the completion day of CX-01. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 310.
Completion day of DE-06:
Start day of DE-06 is the next day of the completion day of SY-11. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 345.
Completion day of RG-05:
Start day of RG-05 is the next day of the completion day of DE-06. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 385.
Lateness of BR-02 and SY-11:
Completion day of BR-02 and SY-11 is less than its respective due date. Hence, there would be no lateness.
Lateness of CX-01:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 10.
Lateness of DE-06:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 25.
Lateness of RG-05:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 25.
Determine the sequence of the job using LPT:
Processing time | Due date | Flow time | Completion time | Late | |
RG-05 | 40 | 360 | 40 | 280 | 0 |
DE-06 | 35 | 320 | 75 | 315 | 0 |
SY-11 | 30 | 310 | 105 | 345 | 35 |
CX-01 | 25 | 270 | 130 | 370 | 100 |
BR-02 | 15 | 300 | 145 | 385 | 85 |
Total | 495 | 220 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 241.
Largest Processing Time (LPT):
Completion day of RG-05:
Jobs arrival rate is given as 241. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 280.
Completion day of DE-06:
Start day of DE-06 is the next day of the completion day of RG-05. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 315.
Completion day of SY-11:
Start day of SY-11 is the next day of the completion day of DE-06. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 345.
Completion day of CX-01:
Start day of CX-01 is the next day of the completion day of SY-11. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 370.
Completion day of BR-02:
Start day of BR-02 is the next day of the completion day of CX-01. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 385.
Lateness of RG-05 and DE-06:
Completion day of RG-05 and DE-06 is less than its respective due date. Hence, there would be no lateness.
Lateness of SY-11:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 35.
Lateness of CX-01:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 100.
Lateness of BR-02:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 85.
Determine the sequence of the job using EDD:
Processing time | Due date | Flow time | Completion time | Late | |
CX-01 | 25 | 270 | 25 | 265 | 0 |
BR-02 | 15 | 300 | 40 | 280 | 0 |
SY-11 | 30 | 310 | 70 | 310 | 0 |
DE-06 | 35 | 320 | 105 | 345 | 25 |
RG-05 | 40 | 360 | 145 | 385 | 25 |
Total | 385 | 50 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 241.
Earliest Due Date (EDD):
Completion day of CX-01:
Jobs arrival rate is given as 241. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 265.
Completion day of BR-02:
Start day of BR-02 is the next day of the completion day of CX-01. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 280.
Completion day of SY-11:
Start day of SY-11 is the next day of the completion day of DE-06. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day of SY-11 is 310.
Completion day of DE-06:
Start day of DE-06 is the next day of the completion day of BR-02. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day of DE-06 is 345.
Completion day of RG-05:
Start day of RG-05 is the next day of the completion day of SY-11. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day of RG-05 is 385.
Lateness of CX-01, BR-02, and SY-11:
Completion day of CX-01, BR-02, and SY-11 is less than its respective due date. Hence, there would be no lateness.
Lateness of DE-06:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 25.
Lateness of RG-05:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 25.
Summary:
Dispatching rule | Job sequence | Flow time | Utilization rating | Average number of jobs | Average lateness |
EDD | CX-BR-SY-DE-RG | 385 | 37.60% | 2.66 | 10 |
SPT | BR-CX-SY-DE-RG | 375 | 38.60% | 2.59 | 12 |
LPT | RG-DE-SY-CX-BR | 495 | 29.30% | 3.41 | 44 |
FCFS | CX-BR-DE-SY-RG | 390 | 37.20% | 2.69 | 12 |
Working note:
Job sequence and flow time have been calculated in the above segments.
Earliest Due Date (EDD):
Average lateness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 10.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.66.
Utilization rating:
It is calculated by dividing total processing time and total flow time. Hence, the utilization rating is 38.6%.
Shortest Processing Time (SPT):
Average lateness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 12.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.59.
Utilization rating:
It is calculated by dividing total processing time and total flow time. Hence, the utilization rating is 38.6%.
Largest Processing Time (LPT):
Average lateness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 44.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 3.41.
Utilization rating:
It is calculated by dividing total processing time and total flow time. Hence, the utilization rating is 29.3%.
First Come First Served (FCFS):
Average lateness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 44.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.69.
Utilization rating:
It is calculated by dividing total processing time and total flow time. Hence, the utilization rating is 37.2%.
b)
To determine: The dispatching rule that has the best score in flow time.
Introduction: Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan on allocating human resources and machinery.
b)

Answer to Problem 18P
Shortest Processing Time has the best flow time.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Date order due |
BR-02 | 228 | 15 | 300 |
CX-01 | 225 | 25 | 270 |
DE-06 | 230 | 35 | 320 |
RG-05 | 235 | 40 | 360 |
SY-11 | 231 | 30 | 310 |
Best score in flow time:
Dispatching rule | Job sequence | Flow time | Utilization rating | Average number of jobs | Average lateness |
EDD | CX-BR-SY-DE-RG | 385 | 37.60% | 2.66 | 10 |
SPT | BR-CX-SY-DE-RG | 375 | 38.60% | 2.59 | 12 |
LPT | RG-DE-SY-CX-BR | 495 | 29.30% | 3.41 | 44 |
FCFS | CX-BR-DE-SY-RG | 390 | 37.20% | 2.69 | 12 |
According to the above table, Shortest Processing Time (SPT) has the best score in flow time. It has less flow time when compare to EDD, LPT, and FCFS.
Hence, SPT has the best score in flow time.
c)
To determine: The dispatching rule that has the best score in utilization metric.
Introduction: Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan on allocating human resources and machinery.
c)

Answer to Problem 18P
Shortest Processing Time has the best utilization metric.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Date order due |
BR-02 | 228 | 15 | 300 |
CX-01 | 225 | 25 | 270 |
DE-06 | 230 | 35 | 320 |
RG-05 | 235 | 40 | 360 |
SY-11 | 231 | 30 | 310 |
Best score in utilization metric:
Dispatching rule | Job sequence | Flow time | Utilization rating | Average number of jobs | Average lateness |
EDD | CX-BR-SY-DE-RG | 385 | 37.60% | 2.66 | 10 |
SPT | BR-CX-SY-DE-RG | 375 | 38.60% | 2.59 | 12 |
LPT | RG-DE-SY-CX-BR | 495 | 29.30% | 3.41 | 44 |
FCFS | CX-BR-DE-SY-RG | 390 | 37.20% | 2.69 | 12 |
According to the above table, Shortest Processing Time (SPT) has the best score in utilization metric. It has maximum utilization metric when compare to EDD, LPT, and FCFS.
Hence, SPT has the best score in utilization metric.
d)
To determine: The dispatching rule that has the best score in average lateness.
Introduction: Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan allocating human resources and machinery.
d)

Answer to Problem 18P
Earliest Due Date has the best utilization metric.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Date order due |
BR-02 | 228 | 15 | 300 |
CX-01 | 225 | 25 | 270 |
DE-06 | 230 | 35 | 320 |
RG-05 | 235 | 40 | 360 |
SY-11 | 231 | 30 | 310 |
Best score in average lateness:
Dispatching rule | Job sequence | Flow time | Utilization rating | Average number of jobs | Average lateness |
EDD | CX-BR-SY-DE-RG | 385 | 37.60% | 2.66 | 10 |
SPT | BR-CX-SY-DE-RG | 375 | 38.60% | 2.59 | 12 |
LPT | RG-DE-SY-CX-BR | 495 | 29.30% | 3.41 | 44 |
FCFS | CX-BR-DE-SY-RG | 390 | 37.20% | 2.69 | 12 |
According to the above table, Earliest Due Date (EDD) has the best score in average lateness. It has less average lateness when compare to SPT, LPT, and FCFS.
Hence, EDD has the best score in average lateness.
e)
To determine: The dispatching rule that would be selected by Person X.
Introduction: Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan allocating human resources and machinery.
e)

Answer to Problem 18P
Person X would select Earliest Due Date.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Date order due |
BR-02 | 228 | 15 | 300 |
CX-01 | 225 | 25 | 270 |
DE-06 | 230 | 35 | 320 |
RG-05 | 235 | 40 | 360 |
SY-11 | 231 | 30 | 310 |
Best score in average lateness:
Dispatching rule | Job sequence | Flow time | Utilization rating | Average number of jobs | Average lateness |
EDD | CX-BR-SY-DE-RG | 385 | 37.60% | 2.66 | 10 |
SPT | BR-CX-SY-DE-RG | 375 | 38.60% | 2.59 | 12 |
LPT | RG-DE-SY-CX-BR | 495 | 29.30% | 3.41 | 44 |
FCFS | CX-BR-DE-SY-RG | 390 | 37.20% | 2.69 | 12 |
According to the above table, EDD has the less average lateness and other values are also having a slight difference when compared with SPT. Thus, EDD should be selected.
Hence, Person X would choose Earliest Due Date (EDD).
Want to see more full solutions like this?
Chapter 15 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
- What do you think is more effective in the long run, bringing in more staff during peak times or investing in cross-training and process redesign to manage demand variability better? With a Referencearrow_forward5. Glenn Dental Clinic provides general dental care to residents of Philadelphia on a walk-in basis. The clinic has started receiving complaints from patients that the waiting time is too long and has asked you to investigate whether this problem can be solved. Upon arrival, customers first receive a series of paperwork from the receptionist and fill out relevant information such as personal health records and insurance provider. The form is then handed back to the receptionist who enters the information into the computer system for the dentist to see. A dental assistant then takes an X-ray from the patient. A dentist then performs the checkup and discusses any issues with the patient. Based on conversations with staff members at the clinic, you have obtained the following information on the process: a. It takes about 5 minutes for a customer to fill out the paperwork. b. Entry of information on the paperwork into the system and verification with past records takes another 5 minutes…arrow_forwardWhy should businesses not set efficiency as the only goal? • Note: Include a reference with supportive citations in the discussion reply in your post.arrow_forward
- Do you think there are other methods to achieve efficiency, such as specialization or using technology to alleviate the bottleneck, like patient wait time?arrow_forwardIs it hard to improve efficiency in a process? Why or why not? Give an example of how to improve the efficiency of a process. Please provide a reference in APA formarrow_forwardSimplex Method Three types of paints are manufactured in one machine; Interior paint, Exterior paint and Paint for metal structures. The preparation time for each type of paint is 2, 3 and 4 minutes respectively and the processing time is 3, 2 and 1 minute. The profit contributed by each product is 12, 10 and 15 dollars respectively. The machine availability is 100 minutes and 200 minutes for machine setup. 1. Determine the optimum number of types of paints to be manufactured. 2. Determine the optimal utility value.arrow_forward
- The company LED S.A DE C.V. produces 2 devices for lamps, devices 1 and 2 that require metal parts and electrical parts. The manager wants to determine how many units of each product should be manufactured to maximize the profit for each unit, device 1 requires 2 metal parts and 4 electrical parts, device 2 requires 4 metal parts and 2 electrical parts, the company has 24 units of each material available for batch production, device 1 generates $4 profit and device 2 generates $6 profit. a) Formulate PL model. b) Solve by the graphical method and determine what is the resulting maximum profit. Translated with DeepL.com (free version)arrow_forwardQuestion 3 i. Using the Center of Gravity method, determine the optimal location (X, Y) for the new distribution center. [7 marks] [TOTAL 25 MARKS] Time (sec.) Power steering assembly firm wants to set up an assembly line which must have an output of 60 units per hour. The work elements, task times and their precedence relationships are shown in Table 2: Table 1 Work Element Immediate Predecessor(s) A 30 NONE B 26 A C 50 A D 44 B E 10 с F 20 с G 15 D.E H 30 E,G,F Required: a. Draw the precedence diagram showing the task precedence and their times b. Determine the cycle time associated with the rate of output required. [3 marks] c. What is the theoretical number of work stations required to satisfy this output rate? [3 marks] [4 marks] d. Allocate the tasks to work stations taking into consideration the precedence requirements and using the LOT rule to break ties between feasible tasks. e. Calculate the total idle time [8 marks] [3 marks] f. What is the efficiency of the line and the…arrow_forwardHyundai Motors is considering three sites-A, B, and C-at which to locate a factory to build its new electric car batteries. The goal is to locate at a minimum-cost site, where cost is measured by the annual fixed plus variable costs of production. Hyundai Motors has gathered the following data: Site Annualized Fixed Cost Variable Cost per Battery Produced A $11,000,000 $2,600 B C $2,000 $1,100 $20,000,000 $25,000,000 The firm knows it will produce between 0 and 60,000 batteries at the new plant each year, but, thus far, that is the extent of its knowledge about production plans. a) The value of volume, V, of production above which site C is recommended = batteries (round your response up to the next whole number).arrow_forward
- Hyundai Motors is considering three sites-A, B, and C-at which to locate a factory to build its new electric car batteries. The goal is to locate at a minimum-cost site, where cost is measured by the annual fixed plus variable costs of production. Hyundai Motors has gathered the following data: Site Annualized Fixed Cost Variable Cost per Battery Produced A $11,000,000 $2,500 B C $2,100 $1,050 $20,000,000 $25,000,000 The firm knows it will produce between 0 and 60,000 batteries at the new plant each year, but, thus far, that is the extent of its knowledge about production plans. a) The value of volume, V, of production above which site C is recommended = batteries (round your response up to the next whole number).arrow_forwardThe importance of keeping track of invoices and budgeting in a nursing home kitchen and how can a nutritionist utilize this in their career? Please not just a short explanation.arrow_forwardThe importance of interviewing potential food service aides and how can a nutritionist utilize this in their career? Please not just a short explanation.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Foundations of Business (MindTap Course List)MarketingISBN:9781337386920Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage LearningFoundations of Business - Standalone book (MindTa...MarketingISBN:9781285193946Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage Learning