To determine: Thesequence of jobs that are based on decision rule First Come First Served (FCFS).
Introduction: First Come First Served is the
a)
Answer to Problem 17P
The sequence is A-B-C-D.
Explanation of Solution
Given information:
The following information has been given:
Job | Due date | Duration (days) |
A | 212 | 6 |
B | 209 | 3 |
C | 208 | 3 |
D | 210 | 8 |
All the jobs are arrived on day 205.
Determine the sequence of the job using FCFS:
Job | Processing time | Flow time | Due date | Start | End | Lateness |
A | 6 | 6 | 212 | 205 | 210 | 0 |
B | 3 | 9 | 209 | 211 | 213 | 4 |
C | 3 | 12 | 208 | 214 | 216 | 8 |
D | 8 | 20 | 210 | 217 | 224 | 14 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 205.
End day of Job A:
Jobs arrival rate is given as 205. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 210.
End day of Job B:
Start day of Job B is the next day of the end day of Job A. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 213.
End day of Job C:
Start day of Job C is the next day of the end day of Job B. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 216.
End day of Job D:
Start day of Job D is the next day of the end day of Job C. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 224.
Lateness of Job A:
End day of Job A is less than its respective due date. Hence, there would be no lateness.
Lateness of Job B:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job B is 4.
Lateness of Job C:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job C is 8.
Lateness of Job D:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job D is 14.
b)
To determine: The sequence of jobs based on decision rule Shortest Processing Time (SPT).
Introduction: Shortest Processing Tine is the scheduling rule, which helps to arrange the sequence in the order. Here, job with the shortest duration would be served first. Then, the process would go on from the shortest to largest duration.
b)
Answer to Problem 17P
The sequence is B-C-A-D.
Explanation of Solution
Given information:
The following information has been given:
Job | Due date | Duration (days) |
A | 212 | 6 |
B | 209 | 3 |
C | 208 | 3 |
D | 210 | 8 |
All the jobs are arrived on day 205.
Determine the sequence of the job using SPT:
Job | Processing time | Flow time | Due date | Start | End | Lateness |
B | 3 | 3 | 209 | 205 | 207 | 0 |
C | 3 | 9 | 208 | 208 | 210 | 2 |
A | 6 | 15 | 212 | 211 | 216 | 4 |
D | 8 | 20 | 210 | 217 | 224 | 14 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 205. The job should be arranged based on duration (processing time). Duration should be assembled in the ascending order.
End day of Job B:
Jobs arrival rate is given as 205. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 207.
End day of Job C:
Start day of Job C is the next day of the end day of Job B. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 210.
End day of Job A:
Start day of Job A is the next day of the end day of Job C. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 216.
End day of Job D:
Start day of Job D is the next day of the end day of Job A. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 224.
Lateness of Job B:
End day of Job Bare less than its respective due date. Hence, there would be no lateness.
Lateness of Job C:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job C is 2.
Lateness of Job A:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job A is 4.
Lateness of Job D:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job D is 14.
c)
To determine: The sequence of jobs based on decision rule Longest Processing Time (LPT).
Introduction: Largest Processing Tine is the scheduling rule, which helps to arrange the sequence in the order. Here, job with the largest duration would be served first. Then, the process would go on from the largest to shortest duration.
c)
Answer to Problem 17P
The sequence is D-A-C-B.
Explanation of Solution
Given information:
The following information has been given:
Job | Due date | Duration (days) |
A | 212 | 6 |
B | 209 | 3 |
C | 208 | 3 |
D | 210 | 8 |
All the jobs are arrived on day 205.
Determine the sequence of the job using LPT:
Job | Processing time | Flow time | Due date | Start | End | Lateness |
D | 8 | 8 | 210 | 205 | 212 | 2 |
A | 6 | 14 | 212 | 213 | 218 | 6 |
C | 3 | 17 | 208 | 219 | 221 | 13 |
B | 3 | 20 | 209 | 222 | 224 | 15 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 205. The job should be arranged based on duration (processing time). Duration should be assembled in the descending order
End day of Job D:
Jobs arrival rate is given as 205. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 212.
End day of Job A:
Start day of Job A is the next day of the end day of Job D. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 218.
End day of Job C:
Start day of Job C is the next day of the end day of Job B. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 221.
End day of Job B:
Start day of Job B is the next day of the end day of Job C. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 224.
Lateness of Job D:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job D is 2.
Lateness of Job A:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job A is 6.
Lateness of Job C:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job C is 13.
Lateness of Job B:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job B is 15.
d)
To determine: The sequence of jobs based on decision rule Earliest Due Date (EDD).
Introduction: Earliest Due Date is the scheduling rule, which helps to arrange the sequence in the order. Here, job with the earliest due date would be served first. Then, the process would go on from the earliest due date to latest due date.
d)
Answer to Problem 17P
The sequence is C-B-D-A.
Explanation of Solution
Given information:
The following information has been given:
Job | Due date | Duration (days) |
A | 212 | 6 |
B | 209 | 3 |
C | 208 | 3 |
D | 210 | 8 |
All the jobs are arrived on day 205.
Determine the sequence of the job using EDD:
Job | Processing time | Flow time | Due date | Start | End | Lateness |
C | 3 | 3 | 208 | 205 | 207 | 0 |
B | 3 | 6 | 209 | 208 | 210 | 1 |
D | 8 | 14 | 210 | 211 | 218 | 8 |
A | 6 | 20 | 212 | 219 | 224 | 12 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 205. The job should be arranged based on due date. Due date should be assembled in the ascending order.
End day of Job C:
Jobs arrival rate is given as 205. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 207.
End day of Job B:
Start day of Job B is the next day of the end day of Job C. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 210.
End day of Job D:
Start day of Job D is the next day of the end day of Job B. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 218.
End day of Job A:
Start day of Job A is the next day of the end day of Job D. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 224.
Lateness of Job C:
End day of Job Care less than its respective due date. Hence, there would be no lateness.
Lateness of Job B:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job B is 1.
Lateness of Job D:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job D is 8.
Lateness of Job A:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job A is 12.
e)
To determine: The sequence of jobs based on critical ratio.
Introduction: Critical ratio is kind of scheduling rule that helps to identify that, the task or job is on the correct track. It would help to identify if the task is behind or ahead of the schedule.
e)
Answer to Problem 17P
The sequence is D-C-A-B.
Explanation of Solution
Given information:
The following information has been given:
Job | Due date | Duration (days) |
A | 212 | 6 |
B | 209 | 3 |
C | 208 | 3 |
D | 210 | 8 |
All the jobs are arrived on day 205.
Calculate the critical ratio:
Job | Due date | Processing time | Critical ratio |
A | 212 | 6 | 1.17 |
B | 209 | 3 | 1.33 |
C | 208 | 3 | 1 |
D | 210 | 8 | 0.63 |
Calculate the critical ratio of Job A:
It is calculated by dividing the value attained by subtracting the present date from the due date and the remaining days. Hence, the critical ratio is 1.17.
Calculate the critical ratio of Job B:
It is calculated by dividing the value attained by subtracting the present date from the due date and the remaining days. Hence, the critical ratio is 1.33.
Calculate the critical ratio of Job C:
It is calculated by dividing the value attained by subtracting the present date from the due date and the remaining days. Hence, the critical ratio is 1.00.
Calculate the critical ratio of Job D:
It is calculated by dividing the value attained by subtracting the present date from the due date and the remaining days. Hence, the critical ratio is 0.63.
Sequence based on critical ratio:
Job | Critical ratio |
D | 0.63 |
C | 1 |
A | 1.17 |
B | 1.33 |
Determine the sequence of the job using EDD:
Job | Processing time | Flow time | Due date | Start | End | Lateness |
D | 8 | 8 | 210 | 205 | 212 | 2 |
C | 3 | 11 | 208 | 213 | 215 | 7 |
A | 6 | 17 | 212 | 216 | 221 | 9 |
B | 3 | 20 | 209 | 222 | 224 | 15 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 205. The job should be arranged based on due date. Due date should be assembled in the ascending order.
End day of Job D:
Jobs arrival rate is given as 205. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 212.
End day of Job C:
Start day of Job C is the next day of the end day of Job D. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 215.
End day of Job A:
Start day of Job A is the next day of the end day of Job C. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 221.
End day of Job B:
Start day of Job B is the next day of the end day of Job A. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 224.
Lateness of Job D:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job D is 2.
Lateness of Job C:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job C is 7.
Lateness of Job A:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job A is 9.
Lateness of Job B:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job B is 15.
Summary:
Scheduling rule | Average lateness | Average flow time | Average number of jobs in system |
FCFS | 6.5 | 11.8 | 2.4 |
SPT | 5 | 10.25 | 2.1 |
LPT | 9 | 14.8 | 3 |
EDD | 5.25 | 10.8 | 2.2 |
Critical ratio | 8.3 | 14 | 2.8 |
First Come First Served (FCFS):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 6.5.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 11.8.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.4.
Shortest Processing Time (SPT):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 5.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 10.25.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.1.
Largest Processing Time (LPT):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 9.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 14.8.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 3.
Earliest Due Date (EDD):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 5.25.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 10.8.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.2.
Critical ratio:
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 8.3.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 14.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.8.
Shortest processing time has the minimum average tardiness, average flow time, and average number of jobs in systems. Hence, SPT is the best decision rule.
Want to see more full solutions like this?
Chapter 15 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
- 3. [25 pts.] Four projects are available for investment. The projects require the cash flows and yield the net present values (NPV) (in millions) shown in the following table. Project id. 1 2 Cash outflow at time 0 (million Lira) 8 8 NPV (million Lira) 12 11 3 4 6 5 8 6 If 20 million Lira is available for investment at time 0, find the investment plan that maximizes NPV. All investments are required to be 0 or 1 (fractional investment values are not permitted). a. Formulate the mathematical model. (Write the decision variables, objective function and the constraints.) [10 pts.] b. Find the optimal solution by using Branch and Bound method (Draw the branch and bound tree clearly, write also lower bounds(LB)) (Left branches x=0, right branches x =1) [15 pts.].arrow_forwardexamine the production concept and operations management, what are the key steps required to achieve success? Be specific in your response.arrow_forwardProduce a 3000 report with references on one international organization of your choice and Address the following: Provide a brief introduction of the organisation and sector it operates in, including its mission and vision statements, its core values, a summary of its financial performance and a general overview of the business’s operational activities. From the relevant literature explain the Total Quality Management (TQM) processes the chosen organization follows and identify one quality challenge/issue that the organization faced or is currently facing. Explain how the organization managed/or still managing the particular quality challenge/issue. Critically analyze whether the organization failed or succeeded in achieving and maintaining quality performance. Provide a few critical recommendations for business managers in order to highlight the importance of Total Quality Management (TQM) within an organization.arrow_forward
- 問題2 Production system design involves determining the arrangement of workstations and the... O allocation of resources to workstations design of the process O production schedule all of the abovearrow_forwardElaborate on the need for and the benefits of an effective supply chain management (SCM) system in the context of a globalized and networked economy. In your answer, explain how organizations like Dell and Hewlett-Packard leverage supply chain networks to maintain competitiveness, and analyse the impact of globalization, technological advancements, and business environment changes on supply chain structures. Additionally, evaluate the key components of SCM, including distribution network configuration, inventory management, and cash-flow management, and discuss how these components contribute to creating an effective and integrated supply chain. (15) 3.2. Critically evaluate the requirements for effective inventory management within an organization. In your answer, discuss the importance of inventory accounting systems, the role of cost information (holding, ordering, and shortage costs), and the significance of classification systems like ABC analysis. Additionally, analyse how…arrow_forwardAssess the role of EDI in ensuring supply chain security and data integrity. How does EDI contribute to reducing vulnerabilities in supply chain operations, and what best practices should organizations adopt to maintain a secure and reliable EDI system? (10) 1.3. Examine how the adoption of modern EDI systems influences the strategic decision-making process in supply chain management. How does EDI provide supply chain managers with actionable insights, and what are the implications of these insights for long-term supply chain planning? (10) 1.4. Evaluate the potential challenges and risks associated with the modernization of EDI systems in supply chain management. How can organizations effectively manage these challenges to ensure successful EDI implementation and ongoing optimization? (10)arrow_forward
- Analyse the impact of integrating EDI (Electronic Data Interchange) with API (Application Programming Interface) on supply chain management, particularly focusing on how this integration enhances information flow and operational efficiency. Consider the challenges that might arise from this integration in terms of managing legacy systems alongside modern applications.arrow_forward1) View the video What is Operations Management (14.01 minutes, Ctrl+Click on the link); what are your key takeaways (tie to one or more of the topics discussed in Chapters 1 and/or 2) after watching this video. (https://www.viddler.com/embed/d01189e1) Note: As a rough guideline, please try to keep the written submission to one or two paragraphs. 2) View the video What McDonald’s is serving up at its new CosMc’s Chain (3.42 mins, Ctrl+Click in the link), and answer the following questions: (https://www.youtube.com/watch?v=k7ojpUzE8q4) i) From a strategic perspective, why do you think McDonald’s is opting for this new chain rather than trying to launch the new menu in its existing restaurants? ii) What factors do you think in McDonald’s external and internal environments are driving its decision to open the CosMc’s locations? iii) How do you think this format will improve McDonald’s profit margin as compared to its regular fast-food restaurants? Note: As a…arrow_forwardSince the end of World War II, globalization has steadily increased with rapid expansion around the turn of the 21st century. What are some of the forces driving globalization and international business? What are some of the challenges of engaging in international business compared to doing business in your home country?arrow_forward
- PS.53 Brother I.D. Ricks is a faculty member at BYU-Idaho whose grandchildren live in Oklahoma and California. He and his wife would like to visit their grandchildren at least once a year in these states. They currently have one vehicle with well over 100,000 miles on it, so they want to buy a newer vehicle with fewer miles and that gets better gas mileage. They are considering two options: (1) a new subcompact car that would cost $18,750 to purchase or (2) a used sedan that would cost $12,750.They anticipate that the new subcompact would get 37 miles per gallon (combined highway and around town driving) while the sedan would get 26 miles per gallon. Based on their road tripping history they expect to drive 13,000 miles per year. For the purposes of their analysis they are assuming that gas will cost $2.93 per gallon.Question: How many miles would the Ricks need to drive before the cost of these two options would be the same? (Display your answer to the nearest whole number.) (Hint:…arrow_forwardChoose one major approach to job design, and then discuss how best that approach can be utilized in either your current or previous employer, including a discussion of its strengths and weaknesses.arrow_forwardThe results of your four plans will provide an indicative EOQ value. State this value and discuss in a precise manner, why it is not the exact, true value. Additional calculations in the form of plans E, F etc. may also assist your explanation of the EOQ and can be includedarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Foundations of Business (MindTap Course List)MarketingISBN:9781337386920Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage LearningFoundations of Business - Standalone book (MindTa...MarketingISBN:9781285193946Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage Learning
- Understanding Management (MindTap Course List)ManagementISBN:9781305502215Author:Richard L. Daft, Dorothy MarcicPublisher:Cengage Learning