Concept explainers
a)
To determine: Thesequence of jobs that are based on decision rule First Come First Served (FCFS).
Introduction: First Come First Served is the
a)

Answer to Problem 17P
The sequence is A-B-C-D.
Explanation of Solution
Given information:
The following information has been given:
Job | Due date | Duration (days) |
A | 212 | 6 |
B | 209 | 3 |
C | 208 | 3 |
D | 210 | 8 |
All the jobs are arrived on day 205.
Determine the sequence of the job using FCFS:
Job | Processing time | Flow time | Due date | Start | End | Lateness |
A | 6 | 6 | 212 | 205 | 210 | 0 |
B | 3 | 9 | 209 | 211 | 213 | 4 |
C | 3 | 12 | 208 | 214 | 216 | 8 |
D | 8 | 20 | 210 | 217 | 224 | 14 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 205.
End day of Job A:
Jobs arrival rate is given as 205. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 210.
End day of Job B:
Start day of Job B is the next day of the end day of Job A. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 213.
End day of Job C:
Start day of Job C is the next day of the end day of Job B. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 216.
End day of Job D:
Start day of Job D is the next day of the end day of Job C. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 224.
Lateness of Job A:
End day of Job A is less than its respective due date. Hence, there would be no lateness.
Lateness of Job B:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job B is 4.
Lateness of Job C:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job C is 8.
Lateness of Job D:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job D is 14.
b)
To determine: The sequence of jobs based on decision rule Shortest Processing Time (SPT).
Introduction: Shortest Processing Tine is the scheduling rule, which helps to arrange the sequence in the order. Here, job with the shortest duration would be served first. Then, the process would go on from the shortest to largest duration.
b)

Answer to Problem 17P
The sequence is B-C-A-D.
Explanation of Solution
Given information:
The following information has been given:
Job | Due date | Duration (days) |
A | 212 | 6 |
B | 209 | 3 |
C | 208 | 3 |
D | 210 | 8 |
All the jobs are arrived on day 205.
Determine the sequence of the job using SPT:
Job | Processing time | Flow time | Due date | Start | End | Lateness |
B | 3 | 3 | 209 | 205 | 207 | 0 |
C | 3 | 9 | 208 | 208 | 210 | 2 |
A | 6 | 15 | 212 | 211 | 216 | 4 |
D | 8 | 20 | 210 | 217 | 224 | 14 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 205. The job should be arranged based on duration (processing time). Duration should be assembled in the ascending order.
End day of Job B:
Jobs arrival rate is given as 205. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 207.
End day of Job C:
Start day of Job C is the next day of the end day of Job B. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 210.
End day of Job A:
Start day of Job A is the next day of the end day of Job C. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 216.
End day of Job D:
Start day of Job D is the next day of the end day of Job A. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 224.
Lateness of Job B:
End day of Job Bare less than its respective due date. Hence, there would be no lateness.
Lateness of Job C:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job C is 2.
Lateness of Job A:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job A is 4.
Lateness of Job D:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job D is 14.
c)
To determine: The sequence of jobs based on decision rule Longest Processing Time (LPT).
Introduction: Largest Processing Tine is the scheduling rule, which helps to arrange the sequence in the order. Here, job with the largest duration would be served first. Then, the process would go on from the largest to shortest duration.
c)

Answer to Problem 17P
The sequence is D-A-C-B.
Explanation of Solution
Given information:
The following information has been given:
Job | Due date | Duration (days) |
A | 212 | 6 |
B | 209 | 3 |
C | 208 | 3 |
D | 210 | 8 |
All the jobs are arrived on day 205.
Determine the sequence of the job using LPT:
Job | Processing time | Flow time | Due date | Start | End | Lateness |
D | 8 | 8 | 210 | 205 | 212 | 2 |
A | 6 | 14 | 212 | 213 | 218 | 6 |
C | 3 | 17 | 208 | 219 | 221 | 13 |
B | 3 | 20 | 209 | 222 | 224 | 15 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 205. The job should be arranged based on duration (processing time). Duration should be assembled in the descending order
End day of Job D:
Jobs arrival rate is given as 205. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 212.
End day of Job A:
Start day of Job A is the next day of the end day of Job D. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 218.
End day of Job C:
Start day of Job C is the next day of the end day of Job B. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 221.
End day of Job B:
Start day of Job B is the next day of the end day of Job C. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 224.
Lateness of Job D:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job D is 2.
Lateness of Job A:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job A is 6.
Lateness of Job C:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job C is 13.
Lateness of Job B:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job B is 15.
d)
To determine: The sequence of jobs based on decision rule Earliest Due Date (EDD).
Introduction: Earliest Due Date is the scheduling rule, which helps to arrange the sequence in the order. Here, job with the earliest due date would be served first. Then, the process would go on from the earliest due date to latest due date.
d)

Answer to Problem 17P
The sequence is C-B-D-A.
Explanation of Solution
Given information:
The following information has been given:
Job | Due date | Duration (days) |
A | 212 | 6 |
B | 209 | 3 |
C | 208 | 3 |
D | 210 | 8 |
All the jobs are arrived on day 205.
Determine the sequence of the job using EDD:
Job | Processing time | Flow time | Due date | Start | End | Lateness |
C | 3 | 3 | 208 | 205 | 207 | 0 |
B | 3 | 6 | 209 | 208 | 210 | 1 |
D | 8 | 14 | 210 | 211 | 218 | 8 |
A | 6 | 20 | 212 | 219 | 224 | 12 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 205. The job should be arranged based on due date. Due date should be assembled in the ascending order.
End day of Job C:
Jobs arrival rate is given as 205. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 207.
End day of Job B:
Start day of Job B is the next day of the end day of Job C. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 210.
End day of Job D:
Start day of Job D is the next day of the end day of Job B. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 218.
End day of Job A:
Start day of Job A is the next day of the end day of Job D. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 224.
Lateness of Job C:
End day of Job Care less than its respective due date. Hence, there would be no lateness.
Lateness of Job B:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job B is 1.
Lateness of Job D:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job D is 8.
Lateness of Job A:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job A is 12.
e)
To determine: The sequence of jobs based on critical ratio.
Introduction: Critical ratio is kind of scheduling rule that helps to identify that, the task or job is on the correct track. It would help to identify if the task is behind or ahead of the schedule.
e)

Answer to Problem 17P
The sequence is D-C-A-B.
Explanation of Solution
Given information:
The following information has been given:
Job | Due date | Duration (days) |
A | 212 | 6 |
B | 209 | 3 |
C | 208 | 3 |
D | 210 | 8 |
All the jobs are arrived on day 205.
Calculate the critical ratio:
Job | Due date | Processing time | Critical ratio |
A | 212 | 6 | 1.17 |
B | 209 | 3 | 1.33 |
C | 208 | 3 | 1 |
D | 210 | 8 | 0.63 |
Calculate the critical ratio of Job A:
It is calculated by dividing the value attained by subtracting the present date from the due date and the remaining days. Hence, the critical ratio is 1.17.
Calculate the critical ratio of Job B:
It is calculated by dividing the value attained by subtracting the present date from the due date and the remaining days. Hence, the critical ratio is 1.33.
Calculate the critical ratio of Job C:
It is calculated by dividing the value attained by subtracting the present date from the due date and the remaining days. Hence, the critical ratio is 1.00.
Calculate the critical ratio of Job D:
It is calculated by dividing the value attained by subtracting the present date from the due date and the remaining days. Hence, the critical ratio is 0.63.
Sequence based on critical ratio:
Job | Critical ratio |
D | 0.63 |
C | 1 |
A | 1.17 |
B | 1.33 |
Determine the sequence of the job using EDD:
Job | Processing time | Flow time | Due date | Start | End | Lateness |
D | 8 | 8 | 210 | 205 | 212 | 2 |
C | 3 | 11 | 208 | 213 | 215 | 7 |
A | 6 | 17 | 212 | 216 | 221 | 9 |
B | 3 | 20 | 209 | 222 | 224 | 15 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 205. The job should be arranged based on due date. Due date should be assembled in the ascending order.
End day of Job D:
Jobs arrival rate is given as 205. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 212.
End day of Job C:
Start day of Job C is the next day of the end day of Job D. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 215.
End day of Job A:
Start day of Job A is the next day of the end day of Job C. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 221.
End day of Job B:
Start day of Job B is the next day of the end day of Job A. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 224.
Lateness of Job D:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job D is 2.
Lateness of Job C:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job C is 7.
Lateness of Job A:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job A is 9.
Lateness of Job B:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job B is 15.
Summary:
Scheduling rule | Average lateness | Average flow time | Average number of jobs in system |
FCFS | 6.5 | 11.8 | 2.4 |
SPT | 5 | 10.25 | 2.1 |
LPT | 9 | 14.8 | 3 |
EDD | 5.25 | 10.8 | 2.2 |
Critical ratio | 8.3 | 14 | 2.8 |
First Come First Served (FCFS):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 6.5.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 11.8.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.4.
Shortest Processing Time (SPT):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 5.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 10.25.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.1.
Largest Processing Time (LPT):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 9.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 14.8.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 3.
Earliest Due Date (EDD):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 5.25.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 10.8.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.2.
Critical ratio:
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 8.3.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 14.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.8.
Shortest processing time has the minimum average tardiness, average flow time, and average number of jobs in systems. Hence, SPT is the best decision rule.
Want to see more full solutions like this?
Chapter 15 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
- The Donald Fertilizer Company produces industrial chemical fertilizers. The projected manufacturing requirements (in gallons) for the next four quarters are 60,000, 90,000, 90,000, and 140,000 respectively. A level workforce is desired, relying only on anticipation inventory as a supply option. Stockouts and backorders are to be avoided, as are overtime and undertime. a. Determine the quarterly production rate required to meet total demand for the year, and minimize the anticipation inventory that would be left over at the end of the year. Beginning inventory is 0. The quarterly production rate is ☐ gallons. (Enter your response as an integer.)arrow_forwardHow would you design an operations plan and schedule for a new product/service? What factors would you consider and what challenges would you anticipate? Why are these factors and challenges relevant and how would you address them?arrow_forwardYou are the newly appointed CEO of TechSouth, a South African multinational technology company based in Cape Town. TechSouth specialises in manufacturing smartphones, laptops, and smart home devices. The company has a significant presence in the African market and has recently expanded into Europe and Asia. However, TechSouth is facing several critical challenges:· Declining Market Share - Over the past three years, TechSouth has lost considerable market share to both localcompetitors and international giants like Samsung and Apple. The company's products are perceived as outdated and lacking innovation.· Employee Engagement Issues - Recent employee surveys indicate low morale and engagement levels, particularly among the younger workforce, leading to high turnover rates. Many employees feel disconnected from the company's vision and mission.· Siloed Departments - The organizational structure at TechSouth is highly siloed, with departments operatingindependently rather than…arrow_forward
- What is the best way to manage emotions and thoughts? How to work through Emotions and thoughts?arrow_forwardWhat are the emotions or stressful thoughts? What are the differences between them? How can we work through the emotions or stressful thoughts? How can we avoid or prevent emotions or stressful thoughts from happening or occurring? What are the obstacles?arrow_forwardMain Challenges at TechInnovateStrategic DirectionTechInnovate's board of directors is pushing for a more aggressive expansion into emerging markets, particularly in Africaand Southeast Asia. However, there's internal disagreement about whether to focus on these new markets or consolidatetheir position in existing ones. Sarah Chen favors rapid expansion, while some senior executives advocate for a morecautious approach.Ethical ConcernsThe company's AI algorithms have come under scrutiny for potential biases, particularly in facial recognition technology.There are concerns that these biases disproportionately affect minority groups. Some employees have voiced ethicalconcerns about selling this technology to law enforcement agencies without addressing these issues.Team Leadership and DiversityTechInnovate's leadership team is predominantly male and Western, despite its global presence. There's growing pressurefrom employees and some board members to diversify the leadership team to…arrow_forward
- Sarah Anderson, the Marketing Manager at Exeter Township's Cultural Center, is conducting research on the attendance history for cultural events in the area over the past ten years. The following data has been collected on the number of attendees who registered for events at the cultural center. Year Number of Attendees 1 700 2 248 3 633 4 458 5 1410 6 1588 7 1629 8 1301 9 1455 10 1989 You have been hired as a consultant to assist in implementing a forecasting system that utilizes various forecasting techniques to predict attendance for Year 11. a) Calculate the Three-Period Simple Moving Average b) Calculate the Three-Period Weighted Moving Average (weights: 50%, 30%, and 20%; use 50% for the most recent period, 30% for the next most recent, and 20% for the oldest) c) Apply Exponential Smoothing with the smoothing constant alpha = 0.2. d) Perform a Simple Linear Regression analysis and provide the adjusted…arrow_forwardRuby-Star Incorporated is considering two different vendors for one of its top-selling products which has an average weekly demand of 70 units and is valued at $90 per unit. Inbound shipments from vendor 1 will average 390 units with an average lead time (including ordering delays and transit time) of 4 weeks. Inbound shipments from vendor 2 will average 490 units with an average lead time of 2 weeksweeks. Ruby-Star operates 52 weeks per year; it carries a 4-week supply of inventory as safety stock and no anticipation inventory. Part 2 a. The average aggregate inventory value of the product if Ruby-Star used vendor 1 exclusively is $enter your response here.arrow_forwardSam's Pet Hotel operates 50 weeks per year, 6 days per week, and uses a continuous review inventory system. It purchases kitty litter for $13.00 per bag. The following information is available about these bags: > Demand 75 bags/week > Order cost = $52.00/order > Annual holding cost = 20 percent of cost > Desired cycle-service level = 80 percent >Lead time = 5 weeks (30 working days) > Standard deviation of weekly demand = 15 bags > Current on-hand inventory is 320 bags, with no open orders or backorders. a. Suppose that the weekly demand forecast of 75 bags is incorrect and actual demand averages only 50 bags per week. How much higher will total costs be, owing to the distorted EOQ caused by this forecast error? The costs will be $higher owing to the error in EOQ. (Enter your response rounded to two decimal places.)arrow_forward
- Yellow Press, Inc., buys paper in 1,500-pound rolls for printing. Annual demand is 2,250 rolls. The cost per roll is $625, and the annual holding cost is 20 percent of the cost. Each order costs $75. a. How many rolls should Yellow Press order at a time? Yellow Press should order rolls at a time. (Enter your response rounded to the nearest whole number.)arrow_forwardPlease help with only the one I circled! I solved the others :)arrow_forwardOsprey Sports stocks everything that a musky fisherman could want in the Great North Woods. A particular musky lure has been very popular with local fishermen as well as those who buy lures on the Internet from Osprey Sports. The cost to place orders with the supplier is $40/order; the demand averages 3 lures per day, with a standard deviation of 1 lure; and the inventory holding cost is $1.00/lure/year. The lead time form the supplier is 10 days, with a standard deviation of 2 days. It is important to maintain a 97 percent cycle-service level to properly balance service with inventory holding costs. Osprey Sports is open 350 days a year to allow the owners the opportunity to fish for muskies during the prime season. The owners want to use a continuous review inventory system for this item. Refer to the standard normal table for z-values. a. What order quantity should be used? lures. (Enter your response rounded to the nearest whole number.)arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Foundations of Business (MindTap Course List)MarketingISBN:9781337386920Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage LearningFoundations of Business - Standalone book (MindTa...MarketingISBN:9781285193946Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage Learning
- Understanding Management (MindTap Course List)ManagementISBN:9781305502215Author:Richard L. Daft, Dorothy MarcicPublisher:Cengage Learning