a)
Summary Introduction
To determine: The production plan and cost for plan of the company Q to level the production using
Introduction: Quarterly operation planning is subjective to annual sales and operation planning. The purpose of this plan is to achieve short term goal that helps to drive company’s long term strategy. The period of quarterly operation planning is 90 days.
b)
Summary Introduction
To determine: The production plan and cost for plan of the company Q to chase demand using forecasted demand.
c)
Summary Introduction
To determine: The production of 70000 units in period 1, and 100000 units in periods 2 through 4.
d)
Summary Introduction
To determine: The production of 90000 units in periods 1 through 3, and 100000 units in periods 4.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Bioway, Inc., a manufacturer of medical supplies, uses ag- gregate planning to set labor and inventory levels for the year. While a variety of items are produced, a standard kit composed of basic supplies is used for planning purposes. Demand varies with seasonal illnesses and the quarterly or- dering policies of hospitals. The average worker at Bioway can produce 1000 kits a month at a cost of $9 per kit dur- ing regular production hours and $10 a kit during overtime production. Completed kits can also be purchased from outside suppliers at $12 each. Inventory carrying costs are $2 per kit per month. Overtime is limited to regular pro- duction, but subcontracting is unlimited. Due to high quality standards and extensive training, hiring and firing costs are $1500 per worker. Bioway currently employs 25 workers. Given the demand forecast below, develop a six-month ag- gregate production plan for Bioway using (a) chase demand and (b) a mixed strategy where the current workforce is kept…
Ajax Manufacturing produces a single product, which takes 8.0 pounds of direct materials per unitproduced. Assume that it is currently at the end of the first quarter of the year, and there are 50,000pounds of material on hand. The company’s policy is to maintain an end-of-quarter inventoryof materials equal to 25 percent of the following quarter’s material requirements for production.How many units of product were produced in the first quarter of the year? Under the assumptionthat production will increase by 10 percent in the second quarter, what are the direct materialsrequirements (in pounds) for planned production in the second quarter?
Green Gardens' owner has asked your advice about a possible problem at his business. Over the last 6 months the large-sized lawn and garden inventory (ie, tables, chairs, planters, etc.) has appeared to be short. The inventory records that employees use to determine what is on hand show that more inventory is available than can actually be located. This has cause frustration and mis-trust in the inventory records for the sales employees. The owner realizes that the problem is bigger than just frustrated employees. He is afraid that inventory is being stolen, a problem he didn't think possible given that these are large items that are not easily moved.
Requirements:
Provide the owner with two internal controls that he could implement to reduce the likelihood of theft of the lawn and garden inventory.
Chapter 14 Solutions
Operations and Supply Chain Management 9th edition
Ch. 14.S - Prob. 1QCh. 14.S - Prob. 2QCh. 14.S - Prob. 3QCh. 14.S - Prob. 4QCh. 14.S - Prob. 5QCh. 14.S - Prob. 6QCh. 14.S - Prob. 7QCh. 14.S - Prob. 8QCh. 14.S - Prob. 1PCh. 14.S - The Tycron Company produces three electrical...
Ch. 14.S - Prob. 3PCh. 14.S - The Pinewood Cabinet and Furniture Company...Ch. 14.S - The Mystic Coffee Shop blends coffee on the...Ch. 14.S - Prob. 6PCh. 14.S - Prob. 7PCh. 14.S - Prob. 8PCh. 14.S - Prob. 9PCh. 14.S - Prob. 10PCh. 14.S - Prob. 11PCh. 14.S - Prob. 12PCh. 14.S - Prob. 13PCh. 14.S - Prob. 14PCh. 14.S - Prob. 15PCh. 14.S - Prob. 16PCh. 14.S - Prob. 17PCh. 14.S - Prob. 18PCh. 14.S - Prob. 19PCh. 14.S - Prob. 20PCh. 14.S - Prob. 22PCh. 14.S - Prob. 23PCh. 14.S - Prob. 24PCh. 14.S - Prob. 25PCh. 14.S - Prob. 27PCh. 14.S - Prob. 28PCh. 14.S - Prob. 1.1CPCh. 14.S - Prob. 1.2CPCh. 14.S - Prob. 1.3CPCh. 14.S - Prob. 1.4CPCh. 14.S - Prob. 1.5CPCh. 14.S - Prob. 1.6CPCh. 14.S - Prob. 1.7CPCh. 14.S - Prob. 1.8CPCh. 14.S - Prob. 1.9CPCh. 14.S - Prob. 2.1CPCh. 14 - Prob. 1.1ASCCh. 14 - Prob. 1.2ASCCh. 14 - Supply and Demand in the Spirits Industry A...Ch. 14 - Supply and Demand in the Spirits Industry A...Ch. 14 - Supply and Demand in the Spirits Industry A...Ch. 14 - Disneys Magic Numbers Sales and operations...Ch. 14 - Disneys Magic Numbers Sales and operations...Ch. 14 - Prob. 1QCh. 14 - List several alternatives for adjusting capacity....Ch. 14 - Prob. 3QCh. 14 - How do linear programming, the linear decision...Ch. 14 - Prob. 5QCh. 14 - What options are available for altering the...Ch. 14 - Prob. 7QCh. 14 - Prob. 8QCh. 14 - Explain the process of collaborative planning. How...Ch. 14 - Prob. 11QCh. 14 - Prob. 12QCh. 14 - Prob. 1PCh. 14 - Prob. 2PCh. 14 - Prob. 3PCh. 14 - Prob. 4PCh. 14 - Mamas Stuffin is a popular food item during the...Ch. 14 - Prob. 6PCh. 14 - Slopes Sleds (SS) makes skis, snowboards, and...Ch. 14 - Prob. 8PCh. 14 - Midlife Shoes, Inc, is a manufacturer of sensible...Ch. 14 - Design a production plan for Mamas Stuffin in...Ch. 14 - Design a production plan for FansForYou in Problem...Ch. 14 - Prob. 16PCh. 14 - Prob. 17PCh. 14 - Prob. 18PCh. 14 - Prob. 19PCh. 14 - Prob. 20PCh. 14 - Prob. 21PCh. 14 - Prob. 22PCh. 14 - How many units are available-to-promise in period...Ch. 14 - Complete the available-to-promise table below.Ch. 14 - Complete the available-to-promise table below.Ch. 14 - Calculate the available-to-promise row in the...Ch. 14 - Complete the following table. How many Bs are...Ch. 14 - Managers at the Dew Drop Inn are concerned about...Ch. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Prob. 31PCh. 14 - Prob. 32PCh. 14 - The Forestry Club sells Christmas trees each year...Ch. 14 - Prob. 34PCh. 14 - Tariott Hotel rents rooms for 125 a night that...Ch. 14 - Prob. 36PCh. 14 - Prob. 1.1CPCh. 14 - Prob. 1.2CPCh. 14 - Prob. 1.3CP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Bhatti Company produces plastic photo frames. Two departments, molding and finishing, are involved in the manufacturing. The molding department fills the molds with hot liquid plastic that is left to cool and then opens them. The finishing department removes the plastic frame from the mold and strips the edges of the frames of extra plastic. The following information is available for the month of January: January 1 Quantity (pounds) January 31 Quantity (pounds) Work-in-Process Inventory Cost Cost Molding department Finishing department None None 5,000 $ 15,000 2,000 The WIP Inventory in the finishing department is estimated to be 40% complete for conversion both at the beginning and end of January. Costs of production for January follow: Direct Costs of Production Materials Conversion Molding department Finishing department $ 450,000 $ 90,000 80,290 The molding department started 50,000 pounds of product in January. The firm uses the FIFO method of process costing. Required: 1. Prepare…arrow_forwardDemand for stereo headphones and MP3 players for joggers has caused Nina Industries to grow almost 50 percent over the past year. The number of joggers continues to expand, so Nina expects demand for headsets to also expand, because, as yet, no safety laws have been passed to prevent joggers from wearing them. Demand for the players for last year was as follows: MONTH DEMAND (UNITS) January February 4,100 4,200 March 3,900 April 4,300 May 4,900 June 4,600 July 5,200 August 4,800 September 5,300 October 5,600 November 6,200 December 5,900arrow_forwardGiven the following data, calculate a level production plan, quarterly ending inventory, and average quarterly inventory. If inventory carrying costs are $3 per unit perquarter, what is the annual carrying cost? Opening and ending inventories are zero.arrow_forward
- B15. The restaurant uses 24 bottles of wine to operate and it has 3 bottles in hand. Calculate the Desired Ending Inventory (DEl) if the number of days in the delivery period is 2 and the safety factor is 10%. Using the Periodic Order Method, calculate the number of bottles that the restaurant should order.arrow_forwardCalculate the available-to-promise row in the following ma-trix.arrow_forwardMadonna’s Burgers is considering making hamburger buns in-house instead of buying them from its supplier. It has estimated the fixed costs for a used over to be $7,000 and the variable costs for the buns to be $0.25. It purchases buns for $0.50 each, and there are no fixed purchase costs. Its annual demand for buns is forecasted to be 15,000. Madonna’s wants to know how many buns it has to make to break even.arrow_forward
- Caltex uses overtime, inventory, and subcontracting to ab-sorb fluctuations in demand. An annual production plan isdevised and updated quarterly. Expected demand, availablecapacities, and costs for the next four quarters are givenbelow. Design a production plan that will satisfy demand atminimum cost.Regular production cost per unit $10Overtime production cost per unit $15Subcontracting cost per unit $20Inventory holding cost per unit per period $ 2 Regular Overtime SubcontractingPeriod Demand Capacity Capacity Capacity1 1500 1000 200 5002 1900 1000 200 5003 500 1000 200 5004 2000 1000 200 500arrow_forwardSouth African rapper, Cassper Nyovest, has launched a business venture manufacturing his very own clothing and shoes. Cassper wishes to ensure the highest levels of customer satisfaction. Argue the importance of accurate demand forecasting as a principle of an inventory management system for Cassper. Note: Provide at least two application points.arrow_forwardThe annual demand of ABC Inc. sole product totaled 450,000 units. Due to uncertainty in supply of items, the maximum possible lead time for the orders is 2 weeks and 1 day. A safety stock of 6,250 units is determined. What is the normal lead time? (Use 360 days) Choices: 1 week and 5 days 1 week 9 days 10 daysarrow_forward
- Black Instrument Company replenishes highly specialized replacement (service) parts based on statistical reorder point. One part is a 40-mm thumbscrew. Relevant data for the thumbscrew are: Planned stock out frequency= Six per year. Planned lead time = 2 weeks Forecast for next week= 300 Batch size = 400 Standard deviation of demand = 20 (per week) What is the reorder point? What would be the effect on the ROP if lead time were five weeks instead of two? What other factors might impact your decision on when to reorder parts?arrow_forwardConsider a two-stage plant-retailer supply chain. Lead time for the plant to fill retail orders is one week. The plant produces exactly to demand and does not keep inventory. Desired safety stock at the retailer is equal to half-week demand, and future demand is estimated by the average of the past two weeks. Find the impact on plan production (customer orders) if demand permanently increases from 100 to 110 units per period.arrow_forwardDemand for stereo headphones and MP3 players for joggers has caused Nina Industries to grow almost 50 percent over the past year. The number of joggers continues to expand, so Nina expects demand for headsets to also expand, because, as yet, no safety laws have been passed to prevent joggers from wearing them. Demand for the players for last year was as follows: MONTH DEMAND (UNITS) January 4,120 February 4,220 March 3,920 April 4,320 May 4,920 June 4,620 July 5,220 August 4,820 September 5,320 October 5,620 November 6,220 December 5,920 a. Using linear regression analysis, what would you estimate demand to be for each month next year? (Do not round intermediate calculations. Round your answers to 2 decimal places.) b. To be reasonably confident of meeting demand, Nina decides to use 3 standard errors of estimate for safety. How many additional units should be held to meet this level of confidence? (Do not round intermediate calculations. Round…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.