Chapter 14.S, Problem 8P
Summary Introduction
To determine: How many hours to run the production process of firm to maximize the profit by formulating and solving linear program
Introduction: Linear programming is used to obtain the best possible outcome from the given real-world problem which is subjective to constraints and inequalities. It is used to make decisions based on business objectives. It is used in business planning, industrial engineering, and physical science. Express the real-world problem into the mathematical expression to get the optimal solution from the linear programming.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Abbott Manufacturing produces plastic cases for solar photovoltaic panels and has decided to combine orders from customers to increase work order size, and thereby, make one large production run per model type.
Plastic injection molding machines are used to make these parts, and it is time consuming to clean and re-setup the machines between production runs. Each molding machine and operator works one 10-hour shift with
a one-hour lunch break and one-half hour for operator breaks.
Consolidated
Work Orders
Model XVT-5 Case
Model UYT-3 Case
Model KLY-6 Case
Work Order
Quantity
9,600 panels
7,900
12,000
Setup
(Changeover)
Time per
Work Order
(minutes)
98
160
What is the total workload (demand) in hours for this work order mix? Round your answer to one decimal place.
The total workload is
hours.
How many machines will it take to do this work in one, two, or three days? Round your answers up to the nearest whole number.
To do this work in 1 day they need
machine(s).
machine(s).
To do this…
Abbott Manufacturing produces plastic cases for solar photovoltaic panels and has decided to combine orders from customers to increase work order
size, and thereby, make one large production run per model type. Plastic injection molding machines are used to make these parts, and it is time
consuming to clean and re-setup the machines between production runs. Each molding machine and operator works one 10-hour shift with a one-
hour lunch break and one-half hour for operator breaks.
Consolidated
Work Orders
Model XVT-5 Case
Model UYT-3 Case
Model KLY-6 Case
Work Order
Quantity
8,800 panels
8,700
12,400
Setup
(Changeover)
Time per
Work Order
(minutes)
86
63
135
Processing
Time per
Panel
(seconds)
2.50
2.22
4.11
What is the total workload (demand) in hours for this work order mix? Round your answer to one decimal place.
The total workload is
hours.
How many machines will it take to do this work in one, two, or three days? Round your answers up to the nearest whole number.
To do this work…
Chris has three different workstations: one for drip coffee, one for espresso drinks, and one to prepare food. During the morning rush, Chris has 5 people working: one person at the drip coffee station, two at the espresso station, and two at the food prep station. These employees are not cross-trained, and thus must stay at their station.
On average, it takes the person at the drip coffee station 1 minute to make the coffee. On average, it takes one person working at the espresso station 3 minutes to make one espresso drink. On average, it takes one person working at the food station 4.5 minutes to prepare the food for one customer.
The customer mix is as follows. 10% order just a drip coffee, 30% order a drip coffee and food, 35% order just an espresso drink, and 25% order an espresso drink plus food.
A total of 40 customers/ hour frequent Chris'. What is the implied utilization at the espresso station? Provide your answer in decimal form, and round to 4 decimal places. (So, if your…
Chapter 14 Solutions
Operations and Supply Chain Management 9th edition
Ch. 14.S - Prob. 1QCh. 14.S - Prob. 2QCh. 14.S - Prob. 3QCh. 14.S - Prob. 4QCh. 14.S - Prob. 5QCh. 14.S - Prob. 6QCh. 14.S - Prob. 7QCh. 14.S - Prob. 8QCh. 14.S - Prob. 1PCh. 14.S - The Tycron Company produces three electrical...
Ch. 14.S - Prob. 3PCh. 14.S - The Pinewood Cabinet and Furniture Company...Ch. 14.S - The Mystic Coffee Shop blends coffee on the...Ch. 14.S - Prob. 6PCh. 14.S - Prob. 7PCh. 14.S - Prob. 8PCh. 14.S - Prob. 9PCh. 14.S - Prob. 10PCh. 14.S - Prob. 11PCh. 14.S - Prob. 12PCh. 14.S - Prob. 13PCh. 14.S - Prob. 14PCh. 14.S - Prob. 15PCh. 14.S - Prob. 16PCh. 14.S - Prob. 17PCh. 14.S - Prob. 18PCh. 14.S - Prob. 19PCh. 14.S - Prob. 20PCh. 14.S - Prob. 22PCh. 14.S - Prob. 23PCh. 14.S - Prob. 24PCh. 14.S - Prob. 25PCh. 14.S - Prob. 27PCh. 14.S - Prob. 28PCh. 14.S - Prob. 1.1CPCh. 14.S - Prob. 1.2CPCh. 14.S - Prob. 1.3CPCh. 14.S - Prob. 1.4CPCh. 14.S - Prob. 1.5CPCh. 14.S - Prob. 1.6CPCh. 14.S - Prob. 1.7CPCh. 14.S - Prob. 1.8CPCh. 14.S - Prob. 1.9CPCh. 14.S - Prob. 2.1CPCh. 14 - Prob. 1.1ASCCh. 14 - Prob. 1.2ASCCh. 14 - Supply and Demand in the Spirits Industry A...Ch. 14 - Supply and Demand in the Spirits Industry A...Ch. 14 - Supply and Demand in the Spirits Industry A...Ch. 14 - Disneys Magic Numbers Sales and operations...Ch. 14 - Disneys Magic Numbers Sales and operations...Ch. 14 - Prob. 1QCh. 14 - List several alternatives for adjusting capacity....Ch. 14 - Prob. 3QCh. 14 - How do linear programming, the linear decision...Ch. 14 - Prob. 5QCh. 14 - What options are available for altering the...Ch. 14 - Prob. 7QCh. 14 - Prob. 8QCh. 14 - Explain the process of collaborative planning. How...Ch. 14 - Prob. 11QCh. 14 - Prob. 12QCh. 14 - Prob. 1PCh. 14 - Prob. 2PCh. 14 - Prob. 3PCh. 14 - Prob. 4PCh. 14 - Mamas Stuffin is a popular food item during the...Ch. 14 - Prob. 6PCh. 14 - Slopes Sleds (SS) makes skis, snowboards, and...Ch. 14 - Prob. 8PCh. 14 - Midlife Shoes, Inc, is a manufacturer of sensible...Ch. 14 - Design a production plan for Mamas Stuffin in...Ch. 14 - Design a production plan for FansForYou in Problem...Ch. 14 - Prob. 16PCh. 14 - Prob. 17PCh. 14 - Prob. 18PCh. 14 - Prob. 19PCh. 14 - Prob. 20PCh. 14 - Prob. 21PCh. 14 - Prob. 22PCh. 14 - How many units are available-to-promise in period...Ch. 14 - Complete the available-to-promise table below.Ch. 14 - Complete the available-to-promise table below.Ch. 14 - Calculate the available-to-promise row in the...Ch. 14 - Complete the following table. How many Bs are...Ch. 14 - Managers at the Dew Drop Inn are concerned about...Ch. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Prob. 31PCh. 14 - Prob. 32PCh. 14 - The Forestry Club sells Christmas trees each year...Ch. 14 - Prob. 34PCh. 14 - Tariott Hotel rents rooms for 125 a night that...Ch. 14 - Prob. 36PCh. 14 - Prob. 1.1CPCh. 14 - Prob. 1.2CPCh. 14 - Prob. 1.3CP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- bama pie company's assembly line operations (the assembly line operates for six hundred minutes per day) comprise of eleven tasks, with the longest task time being 2.4 minutes and the shortest task time being 0.4 minutes; the sum of the task times is eighteen minutes. the firm is working on balancing its assembly line operations. the firm needs to produce 200 pies per day; to achieve this, the firm calculates the required cycle time as ---- minutes?arrow_forwardA machine used for cutting materials in a factory has the following outputs per hour at various speeds and required periodic tool regrinding at intervals cited. Speed Hour Output per Tool RegrindingA 200 pieces every 8 hours B 280 pieces every 5 hours A set of tools costs 560 and can be ground twenty times. Each regrinding costs 54.00 and the time needed to regrind and change tools is 1 hour. The machine operator is paid 35.00 per hour including the time the tool is changed. The tool grinder who also sets the tools to the machine is paid 40.00 per hour. The hourly rate chargeable against the machine is 38.00, regardless of machine speed. Which speed is more ecomical? A. Speed B, 0.096/pc B Speed B, 0.087/pc C. Speed A, .054/pc D. Speed A >037/pcarrow_forwardA veterinary office with three processes (examination, greeting, and checkout) has two types of customers (boarding and medical). A veterinary office has a demand of 2 boarding customers per hour and 5 medical customers per hour. Boarding customers visit the greeting and checkout processes while medical customers visit all three processes. What is the total demand at the checkout process each hour? customers per hourarrow_forward
- Cakes baked by the Freshfood Bakery are transported from the ovens to be packaged by one of three wrappers. Each wrapper can wrap an average of 200 cakes per hour. The cakes are brought to the wrappers at the rate of 500 per hour. If a cake sits longer than 5 minutes before being wrapped, it will not be fresh enough to meet the bakery’s quality control standards. Does the bakery need to hire another wrapper?arrow_forwardPanini, a popular sandwich shop, offers 3 types of sandwiches: grilled vegetables, grilled chicken, and pastrami. Demand (sandwiches per hour) are Grilled Vegetables = 25, Grilled Chicken = 15, and Pastrami = 10. There are up to five steps in the process of making sandwiches, listed below with processing times. Step Grilled Vegetables Grilled Chicken Pastrami Cut bread 0.75 minutes 0.75 minutes 0.75 minutes Grill 1.4 minutes 1.4 minutes Slice meat 3 minutes Toast 2 minutes 2 minutes 2 minutes Wrap 0.5 minutes 0.5 minutes 0.5 minutes Only 50 percent of customers want their sandwich toasted, no mattor which sandwich is ordered. Suppose Panini employs 1 worker at each step. Instructions: Round all answers to 1 decimal place. (a) What is the implied utilization of each of the five steps in this process? 62.5 % 93.3 % 50.이% 83.3 % 41.7 % Cut Grill Slice Toast Wrap (b) What is the actual and maximum flow rates of the three sandwich types? per hour Veg Chicken per hourarrow_forwardA work cell in a local manufacturer has a workstation with 4 machines that form a line (Machine 1-Machine 2-Machine 3-Machine 4). Each unit needs to pass through each machine in order to be completed. Each machine has a production capacity of four units per hour. What is the process time of the work cell in minutes per unit? 15 4 8 16arrow_forward
- In the welding operations of a bicycle manufacturer, a bike frame has a flow time of about 11.5 hours. The time in the welding operation is spent as follows: 2 hours waiting in front of the cutting machine for the batch to start, 2 hours waiting for the setup of the machine, 1 hour waiting for the other pieces of the batch to go through cutting, 1 minute at the cutting machine, and 3 hours waiting for the transfer to the welding machine. Then, at the welding machine, the unit spends 1 hour waiting in front of the welding machine for the batch to start, 1 hour waiting for the setup of the welding machine, 0.5 hour waiting for the other pieces of the batch to go through welding, 0.5 minute at the welding machine, and 1 hour waiting for the transfer to the next department. Determine the exact flow time. What is the value-added percentage of the flow time?(round percentage answer to 4 decimal places.) answer:_______percentarrow_forwardIn the welding operations of a bicycle manufacturer, a bike frame has a flow time of about 12.75 hours. The time in the welding operation is spent as follows: 2 hours waiting in front of the cutting machine for the batch to start, 2 hours waiting for the setup of the machine, 2 hour waiting for the other pieces of the batch to go through cutting, 1 minute at the cutting machine, and 2 hours waiting for the transfer to the welding machine. Then, at the welding machine, the unit spends 1 hour waiting in front of the welding machine for the batch to start, 1 hour waiting for the setup of the welding machine, 0.75 hour waiting for the other pieces of the batch to go through welding, 0.25 minute at the welding machine, and 2 hour waiting for the transfer to the next department. (Round your percentage answer to 4 decimal places.) Determine the exact flow time. What is the value-added percentage of the flow time? 0.0604 percentarrow_forwardAs an analyst, we would like to perform a work sampling study on an assembly line. The jobs can bedifferentiated on the basis of the product size: A, B, and C. We perform a study over a five-week periodthat equals to 200 working hours. There are 12 workers to be examined. In total, we perform 1140observations. Yet, the worker absences lead to 15 worker-day deduction from the total working hourswhere workers work 8 hour each day. The study results are tabulated below. Q: For the C size product, construct a 96% confidence interval about the mean assembly time per productin terms of hours.a) (0,3702 0,4298)b) (0,4004 0,3996)c) (0,1805 0,1209)d) (0,3746 0,4254)e) (0,1253 0,1761)arrow_forward
- As an analyst, we would like to perform a work sampling study on an assembly line. The jobs can bedifferentiated on the basis of the product size: A, B, and C. We perform a study over a five-week periodthat equals to 200 working hours. There are 12 workers to be examined. In total, we perform 1140observations. Yet, the worker absences lead to 15 worker-day deduction from the total working hourswhere workers work 8 hour each day. The study results are tabulated below. Q: What is the mean assembly time per product unit for size C in terms of hour?a) 0,1136b) 0,0251c) 0,3015d) 0,7537e) 0,0661arrow_forwardConsider a process consisting of five resources that are operated eight hours per day. Demand for the three different products is as follows: Product A, 40 units per day, Product B, 50 Units per day, and product C, 60 units per day. What is the bottleneck? What is the flow rate for each flow unit assuming that demand must be served in the mix described above (i.e., for every four units of A, there are five units of B and six units of C)?arrow_forwardIn the welding operations of a bicycle manufacturer, a bike frame has a flow time of about 16.65 hours. The time in the welding operation is spent as follows: 3 hours waiting in front of the cutting machine for the batch to start, 3 hours waiting for the setup of the machine, 1 hour waiting for the other pieces of the batch to go through cutting, 1 minute at the cutting machine, and 3 hours waiting for the transfer to the welding machine. Then, at the welding machine, the unit spends 2 hour waiting in front of the welding machine for the batch to start, 2 hour waiting for the setup of the welding machine, 0.65 hour waiting for the other pieces of the batch to go through welding, 0.4 minute at the welding machine, and 2 hour waiting for the transfer to the next department. (Round your percentage answer to 4 decimal places.) Determine the exact flow time. What is the value-added percentage of the flow time? percent cetion MacBook Air ww.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,