Mylab Operations Management With Pearson Etext -- Access Card -- For Operations Management: Sustainability And Supply Chain Management (13th Edition)
13th Edition
ISBN: 9780135225899
Author: Jay Heizer, Barry Render, Chuck Munson
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Question
Chapter 13, Problem 5P
Summary Introduction
To evaluate: Plan C
Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
2
Costs
Previous quarter's output
Beginning inventory
Stockout cost for backorders
Inventory holding cost
1,500 units
O units
$50 per unit
$10 per unit for every unit held
at the end of the quarter
$40 per unit
$80 per unit
$30 per unit
$15 extra per unit
Not available
Hiring workers
Layoff workers
Unit cost
Overtime
Subcontracting
a) Use Chase Demand Strategy
b) Use Level Production Strategy with Backordering
3. Your independent oil and gas company is considering the purchase at time zero of a
100 % working interest in a property. If you elect to develop the lease for an 87.5%
revenue interest, the following costs will be incurred: in time zero, the lease bonus
cost is $100,00o, intangible drilling costs are estimated at $550,000 while tangible
completion costs are estimated at $300,000. Operating costs are estimated to
remain constant at $8.00 per barrel (includes production costs, severance taxes and
ad-valorem taxes) in each of years 1, 2, 3 and 4. Oil prices are forecasted to be
$50.00 per barrel in each of years 1, 2, 3, and 4. Production is summarized in the
following table. The escalated dollar minimum rate of return is 12.0%. Use net
present value analysis to determine if the acquisition and development of this lease
is economically viable: (a) Before considering income taxes, (b) Assuming income
tax rate of 30%. (Expense 100% of intangible drilling costs at the end of first year,…
Chapter 13 Solutions
Mylab Operations Management With Pearson Etext -- Access Card -- For Operations Management: Sustainability And Supply Chain Management (13th Edition)
Ch. 13 - Prob. 1DQCh. 13 - Why are SOP teams typically cross-functional?Ch. 13 - Prob. 3DQCh. 13 - Prob. 4DQCh. 13 - Prob. 5DQCh. 13 - Prob. 6DQCh. 13 - Question: 7. What is level scheduling? What is the...Ch. 13 - Question: 8. Define mixed strategy. Why would a...Ch. 13 - Prob. 9DQCh. 13 - Prob. 10DQ
Ch. 13 - Question: 11. What is the relationship between the...Ch. 13 - Prob. 12DQCh. 13 - Question: 13. What are major limitations of using...Ch. 13 - Prob. 14DQCh. 13 - Question: 13.1 Prepare a graph of the monthly...Ch. 13 - Prob. 2PCh. 13 - The president of Hill Enterprises, Terri Hill,...Ch. 13 - Prob. 4PCh. 13 - Prob. 5PCh. 13 - Prob. 6PCh. 13 - Prob. 7PCh. 13 - Prob. 8PCh. 13 - Prob. 9PCh. 13 - Question: 13.10 The SOP team (see Problem 13.9)...Ch. 13 - Prob. 11PCh. 13 - Prob. 12PCh. 13 - Prob. 13PCh. 13 - Question: 13.14 Jerusalem Medical Ltd., an...Ch. 13 - Prob. 15PCh. 13 - Prob. 16PCh. 13 - Prob. 17PCh. 13 - Question: 13.18 Jose Martinez of El Paso has...Ch. 13 - Prob. 19PCh. 13 - Prob. 23PCh. 13 - Prob. 24PCh. 13 - Prob. 25PCh. 13 - Prob. 26PCh. 13 - Prob. 1CSCh. 13 - Prob. 2CSCh. 13 - Prob. 1.1VCCh. 13 - Prob. 1.2VCCh. 13 - Question: 3. What are some concerns the team needs...
Knowledge Booster
Similar questions
- Question 6 Table below is a time-phased net requirements for Widgets over the next six weeks. Week 1 Requirements 335 The setup cost is $200 and the holding cost is $0.30 per unit per week. Using the Silver-Meal heuristics, indicate the number of units to produce for each of the following period. Enter your answer as integer. Week 1 2 3 4 5 6 2 200 Production Quantity 3 140 4 440 5 300 The total holding and setup cost for the Silver-Meal lot sizing method is $ Note: Enter your value with exactly 2 decimal places, as in 12345.67 6 200arrow_forwardExplain AGGREGATE PLANNING TECHNIQUES?arrow_forwardQuestion 4 An alternative will have fixed costs of $10,000 per month, variable costs of $50 per unit, and revenue of $70 per unit. The break-even point volume is:arrow_forward
- What is the managerial significance of aggregate planning. Explainarrow_forwardQUESTION 1 AJ Fabrication has the following aggregate demand requirements and other data for the upcoming four quarters. Quarter Demand 1 1300 2 1400 3 1500 4 1300 Previous quarter's output = 1,500units Beginning inventory = 200units Stockout costs = $50 per unit Inventory holding cost = $10 per unit at end of quarter Hiring workers = $4 per unit Firing workers = $8 per unit Unit cost = $30 per unit Overtime = $10 extra per unit a) Which of the following production plans is better: Plan A - chase demand by hiring and firing: or plan B - product at a constant rate of 1200 and obtain remainder from overtime? b) Explain the differences between repair and preventive maintenance? c) Explain the implications of each approach when developing an asset maintenance strategy? d) Explain the benfits and challenges associated with the implementation of an MRP system?arrow_forwardQ7. The president of Rose Bowl Enterprises, Desmond Howard, projects the firms aggregate DEMAND requirements over the next 8 months as follows: These are the monthly DEMAND, not production. MONTH JAN FEB MAR APR MAY JUN JULY AUG DEMAND 1,400 1,600 1,800 1,800 2,200 2,200 1,800 1,800 PRODUCTION 1,600 from December INVENTORY 200 from Dec plus 200 His operations manager is considering a new plan, which begins in January with 200 units on hand. Stockout cost of lost sales is $100 per unit. Inventory holding cost is $20 per unit per month. Ignore any idle time costs. The plan is called plan A. Plan A: Vary the workforce level to execute a strategy that produces the quantity demanded in the prior month. The December demand was given as 1,600 units per month. Therefore, the production for JAN will be 1,600. However, only 1,400 are needed. Therefore, the extra 200 produced go into inventory and there is a holding cost for inventory. Also, per the above, you already have 200 units in inventory…arrow_forward
- APP Trial and Error Given the following information: Quarter Demand 2 9,000 3 10,200 4 3,300 Regular Prod. Capacity = 7,225 units/qtr Regular Prod. Cost = $12/unit Overtime Prod. Capacity = 2,000 units/qtr Overtime Prod. Cost = $17/unit Subcontracting Capacity = 10,000 units/qtr Subcontracting Cost = $22/unit Inventory Cost = $5/unit/qtr Beginning Inventory = 0 units Backordering Cost = $12/unit/qtr Beginning workforce = 50 workers Hiring Cost = $2000/worker Production rate/worker = 200 units/qtr Firing Cost = $5000/worker Develop a Production Plan using Level Production with Overtime and Subcontracting Strategies. A) How many units will be…arrow_forwardQUESTION 1 A master production schedule shows the following information MPS Week Week Week Week Beginning inventory = 300 31 Forecast 1.000 1,200 1,300 1.200 800 700 Actual customer orders Projected on-hand inventory Available to promise 800 1,000 MPS Based on the information in the MPS, what is the amount that is available to promise in week 4? O a. 1,200 Ob.700 Oc. 1.500 O d. 500arrow_forwardNeed solutions in only text not in images and tablesarrow_forward
- SOLVED FIXED TIME PERIOD MODEL PROBLEMS Activities/Assessments:Activity 13• The weekly demand for a product is 770 units. The standard deviation of daily demand is 10 units. The firm reviews its inventory every 28 days. Each order for the product arrives 9 days after placement. At the time of review, there are 10 units backorder. If 95 percent of all demand is to be satisfied from items in stock:a) How many units should be the safety stock?b) What’s the product’s inventory status?c) How many units should be ordered for this period?arrow_forwardProblem 4. Considered a (s,S) system, with s = 80 and S = 200. The forecasted demand for the next 12 months is given in the following table. Initial inventory is 180, lead time is zero, and review is done at the end of every month. Find the order quantity. Mes, t 1 2 3 4 5 6 7 8 9 10 11 12 Demanda, D 65 110 | 80 150 120 90 50 170 140 125 55 80arrow_forward5) How does revenue management impact an aggregate plan?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.