Question
Chapter 13, Problem 10DQ
Summary Introduction
To determine: Thedifference between aggregate planning in service and aggregate planning in manufacturing
Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
QUESTION 1
A master production schedule shows the following information
MPS
Week
Week
Week
Week
Beginning inventory =
300
31
Forecast
1.000
1,200
1,300
1.200
800
700
Actual customer orders
Projected on-hand
inventory
Available to promise
800
1,000
MPS
Based on the information in the MPS, what is the amount that is available to promise in week 4?
O a. 1,200
Ob.700
Oc. 1.500
O d. 500
Question 5
Question 4) APP Linear Programming
Given the following information:
Quarter Demand
Regular Prod. Capacity = 3,000 units/gt
8,000 Overtime Prod. Capacity = 800 units/gtg
4,000 Subcontracting Capacity = 1,800 units/gt
Regular Prod. Cost = $20/unit
Overtime Prod. Cost = $25/unit
1
2
2,000 Inventory Capacity
= 6,000 untis/atr
Subcontracting Cost = $35/unit
Inventory Cost
3
Beginning Inventory
= 500 units
= $4/unit/gtr
Linear programming is to be used to determine a production plan strategy of Level Production,
Overtime, and Subcontracting.
a. Formulate the Objective Function (note that there are 3 quarters).
b. Formulate all Constraints (standardized).
c. How many decision variables are in the model?
d. How many constraints are in the model? (do not include non-negativity constraints)
Chapter 13 Solutions
Mylab Operations Management With Pearson Etext -- Access Card -- For Operations Management: Sustainability And Supply Chain Management (13th Edition)
Ch. 13 - Prob. 1DQCh. 13 - Why are SOP teams typically cross-functional?Ch. 13 - Prob. 3DQCh. 13 - Prob. 4DQCh. 13 - Prob. 5DQCh. 13 - Prob. 6DQCh. 13 - Question: 7. What is level scheduling? What is the...Ch. 13 - Question: 8. Define mixed strategy. Why would a...Ch. 13 - Prob. 9DQCh. 13 - Prob. 10DQ
Ch. 13 - Question: 11. What is the relationship between the...Ch. 13 - Prob. 12DQCh. 13 - Question: 13. What are major limitations of using...Ch. 13 - Prob. 14DQCh. 13 - Question: 13.1 Prepare a graph of the monthly...Ch. 13 - Prob. 2PCh. 13 - The president of Hill Enterprises, Terri Hill,...Ch. 13 - Prob. 4PCh. 13 - Prob. 5PCh. 13 - Prob. 6PCh. 13 - Prob. 7PCh. 13 - Prob. 8PCh. 13 - Prob. 9PCh. 13 - Question: 13.10 The SOP team (see Problem 13.9)...Ch. 13 - Prob. 11PCh. 13 - Prob. 12PCh. 13 - Prob. 13PCh. 13 - Question: 13.14 Jerusalem Medical Ltd., an...Ch. 13 - Prob. 15PCh. 13 - Prob. 16PCh. 13 - Prob. 17PCh. 13 - Question: 13.18 Jose Martinez of El Paso has...Ch. 13 - Prob. 19PCh. 13 - Prob. 23PCh. 13 - Prob. 24PCh. 13 - Prob. 25PCh. 13 - Prob. 26PCh. 13 - Prob. 1CSCh. 13 - Prob. 2CSCh. 13 - Prob. 1.1VCCh. 13 - Prob. 1.2VCCh. 13 - Question: 3. What are some concerns the team needs...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Question 3 List any five (5) costs prevalent in aggregate planning in the motor car industry.arrow_forwardQuestion 4 An alternative will have fixed costs of $10,000 per month, variable costs of $50 per unit, and revenue of $70 per unit. The break-even point volume is:arrow_forwardQUESTION 2 ID11 What is an information system for identifying and planning the enterprise-wide resources needed to take, make, ship, and account for customer orders? BOM MRP CIM ⒸERParrow_forward
- question 1 Terminator, Inc., manufactures a motorcycle part in lots of 250 units. The raw materials cost for the part is $150, and the value added in manufacturing 1 unit from its components is $280, for a total cost per completed unit of $430. The lead time to make the part is 3 weeks, and the annual demand is 4,200 units. Assume 50 working weeks per year. a. How many units of the part are held, on average, as cycle inventory? nothing units. (Enter your response as an integer.) What is its value? $_______.(Enter your response as an integer.) b. How many units of the part are held, on average, as pipeline inventory? nothing units. (Enter your response as an integer.) What is its value? $________________ (Enter your response as an integer.)arrow_forwardQuestion 5 Terminator, Inc., manufactures a motorcycle part in lots of 150 units. The raw materials cost for the part is $150, and the value added in manufacturing 1 unit from its components is $320, for a total cost per completed unit of $470. The lead time to make the part is 2 weeks, and the annual demand is 3,800 units. Assume 50 working weeks per year. a. How many units of the part are held, on average, as cycle inventory? __________________ units. (Enter your response as an integer.) What is its value? $___________________ (Enter your response as an integer.) b. How many units of the part are held, on average, as pipeline inventory? ________________ units. (Enter your response as an integer.) What is its value? $__________________________ (Enter your response as an integer.)arrow_forwardProblem 1 The following information applies to the City View Restaurant. May 1 Food inventory value: $73,480 bnl de May 31 Food inventory value: $77,550 bonen Cost of food used during May $386,410 1. What is the inventory turnover rate for food products for the City View Restaurant? 2. What does the answer (inventory turnover ratio) in question 1 mean?arrow_forward
- QUESTION 9 Consider a SKU with 276 picks forecasted during the planning horizon and an annual flow of 2000 ft. Suppose that: • the cost of picking from the forward fast-pick area is 1 minute per pick • the cost of picking from the reserve area is 4 minutes per pick • the cost of restocking the fast-pick area from reserve is 5 minutes per restock What is the labor efficiency of this SKU? Provide your answer to the nearest single decimal point.arrow_forwardQUESTION 2 NAK Consult Ltd is a construction company with many contracts being executed concurrently. A large number of workers are on various construction sites. NAK Consult Ltd has an internal audit department and the team is currently reviewing cash wages systems within the company. The following information is available concerning the wages systems: • Workers on each site are controlled by a foreman. The foreman has a record of all employee numbers and can issue temporary numbers for new employees. • Any overtime is calculated by the computerized wages system and added to the standard pay. • The two staff in the wages department make amendments to the computerized wages system in respect of employee leave, illness, as well as setting up and maintaining all employee records. • The computerized wages system calculates deductions from gross pay, such as employee taxes (PAYE), and other statutory deductions. • Finally, a list of net cash payments for each employee is produced. Cash is…arrow_forwardQUESTION THREEa) Zambia Breweries has a backlog of 250 crates of Fanta drinks at the end of December. The demand of Fanta drinks is expected to be 400 crates in January, 500 crates in February and 550 crates in March. Each worker can produce 50 crates of drinks per month with regular wage costing the company K10 000 per worker per month. Hiring cost has been calculated to be K25 000 per. Hiring cost has also been calculated to be K50 000 per worker. Backlog cost have been determined to cost the company K250 per worker. There are no cost associated with carrying the inventory. Develop a level of production plan (aggregate plan) and determine the cost. b) Explain why aggregate planning is necessary in production and operation management.c) Define the meaning and what happens at each of these aggregate capacity planning;i) Matching Demand approachii) Level Capacity approach.arrow_forward
- Question 3 Gajah Sdn Bhd makes two products (Alpha and Beta) that require direct materials, direct labour and overhead. The operations for next month are: Alpha RM Beta Revenue Direct material Direct labour Overhead: Direct material related Direct labour related RM 300,000 60,000 95,000 Total RM 400,000 90,000 135,000 100,000 30,000 40,000 13,500 40,500 Required : a) Gajah uses a two-stage cost allocation system. It uses direct material costs to allocate direct materials related overhead and direct labour costs to allocate direct labour related overhead costs: i. Calculate the direct material related overhead rate for next month. ii. Calculate the direct labour related overhead rate for next month iii. What is the total overhead allocated to product Alpha next month? iv. What is the total overhead allocated to product Beta next month?arrow_forwardQuestion 6 Table below is a time-phased net requirements for Widgets over the next six weeks. Week 1 Requirements 335 The setup cost is $200 and the holding cost is $0.30 per unit per week. Using the Silver-Meal heuristics, indicate the number of units to produce for each of the following period. Enter your answer as integer. Week 1 2 3 4 5 6 2 200 Production Quantity 3 140 4 440 5 300 The total holding and setup cost for the Silver-Meal lot sizing method is $ Note: Enter your value with exactly 2 decimal places, as in 12345.67 6 200arrow_forwardQuestion R .Create a BPMN diagram to represent the supply chain management process for BMW. The solution should include the following Actors. • Buyer • BMW dealership • BMW parts manufacturer • Raw material manufacturer Full explain this question and text typing work only We should answer our question within 2 hours takes more time then we will reduce Rating Dont ignore this linearrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.