Concept explainers
Demand for walnut fudge ice cream at the Sweet Cream Dairy can be approximated by a
a. If an ROP model is used, what ROP would be consistent with the desired service level? How many days of supply are on hand at the ROP, assuming average demand?
b. If a fixed-interval model is used instead of an ROP model, what order size would be needed for the 90 percent service level with an order interval of 10 days and a supply of 8 gallons on hand at the order time? What is the probability of experiencing a stockout before this order arrives?
c. Suppose the manager is using the ROP model described in part a. One day after placing an order with the supplier, the manager receives a call from the supplier that the order will be delayed because of problems at the supplier's plant. The supplier promises to have the order there in two days. After hanging up, the manager checks the supply of walnut fudge ice cream and finds that 2 gallons have been sold since the order was placed. Assuming the supplier's promise is valid, what is the probability that the dairy will run out of this flavor before the shipment arrives?
a)
To determine: The reorder point and days of supply on hand.
Introduction: Reorder point is the point at which the firm has to replenish its inventory in order to avoid shortages or any lag in production.
Answer to Problem 21P
Explanation of Solution
Given information:
Formula:
Calculation of Reorder point and number of days of supply:
Using z-factor table, the z value corresponds to 0.90. The closest value of probability is 0.8997 which corresponds to z = 1.28.
Reorder point is calculated by multiplying 21 with
Number of days of supply is calculated by dividing 9 with the ratio of 21 and 7 which yields 3 days of supply on hand at ROP.
Hence, the reorder point and days of supply on hand is 9 gallons and 3days.
b)
To determine: The probability of experiencing stock out before the order arrives.
Introduction: Safety stock refers to the quantity of additional or extra stock which are maintained to mitigate the risks and uncertainty which arises due to fluctuation in supply and demand.
Answer to Problem 21P
Explanation of Solution
Given information:
Formula:
Calculation to determine the probability of stock out before arriving of the order:
Using z-factor table, the lead service level is 0.8577.
The risk of stock out is calculated by finding the z-factor from using the ROP of 8, mean demand of 21 and standard deviation of 3.5 and lead time of
For z=1.07, the corresponding value from z-factor table is 0.8577. The probability to find the risk of stock out is difference between 1 and 0.8577 which gives 14.23%.
Hence, the probability of experiencing stock out before the order arrives is 14.23%.
c)
To determine: The probability of stock out situation.
Introduction: Safety stock refers to the quantity of additional or extra stock which are maintained to mitigate the risks and uncertainty which arises due to fluctuation in supply and demand.
Answer to Problem 21P
Explanation of Solution
Given information:
Calculation to determine the probability of stock out situation:
The ROP is 9 gallons (refer equation (1)) and 2 gallons had been sold after placing order. Stock after day 1 of placing order is the difference between 9 and 2 which is 7 gallons.
Using z-factor table, the lead service level is 0.7019.
The risk of stock out is calculated by finding the z-factor from using the ROP of 7, mean demand of 21 and standard deviation of 3.5 and lead time of
For z = 0.53, the corresponding value from z-factor table is 0.7019. The probability to find the risk of stock out is difference between 1 and 0.7019 which gives 29.81%.
Hence, the probability of experiencing stock out is 29.81%.
Want to see more full solutions like this?
Chapter 13 Solutions
OPERATIONS MANAGEMENT W/ CNCT+
- Scenario 3 Ben Gibson, the purchasing manager at Coastal Products, was reviewing purchasing expenditures for packaging materials with Jeff Joyner. Ben was particularly disturbed about the amount spent on corrugated boxes purchased from Southeastern Corrugated. Ben said, I dont like the salesman from that company. He comes around here acting like he owns the place. He loves to tell us about his fancy car, house, and vacations. It seems to me he must be making too much money off of us! Jeff responded that he heard Southeastern Corrugated was going to ask for a price increase to cover the rising costs of raw material paper stock. Jeff further stated that Southeastern would probably ask for more than what was justified simply from rising paper stock costs. After the meeting, Ben decided he had heard enough. After all, he prided himself on being a results-oriented manager. There was no way he was going to allow that salesman to keep taking advantage of Coastal Products. Ben called Jeff and told him it was time to rebid the corrugated contract before Southeastern came in with a price increase request. Who did Jeff know that might be interested in the business? Jeff replied he had several companies in mind to include in the bidding process. These companies would surely come in at a lower price, partly because they used lower-grade boxes that would probably work well enough in Coastal Products process. Jeff also explained that these suppliers were not serious contenders for the business. Their purpose was to create competition with the bids. Ben told Jeff to make sure that Southeastern was well aware that these new suppliers were bidding on the contract. He also said to make sure the suppliers knew that price was going to be the determining factor in this quote, because he considered corrugated boxes to be a standard industry item. Is Ben Gibson acting legally? Is he acting ethically? Why or why not?arrow_forwardScenario 3 Ben Gibson, the purchasing manager at Coastal Products, was reviewing purchasing expenditures for packaging materials with Jeff Joyner. Ben was particularly disturbed about the amount spent on corrugated boxes purchased from Southeastern Corrugated. Ben said, I dont like the salesman from that company. He comes around here acting like he owns the place. He loves to tell us about his fancy car, house, and vacations. It seems to me he must be making too much money off of us! Jeff responded that he heard Southeastern Corrugated was going to ask for a price increase to cover the rising costs of raw material paper stock. Jeff further stated that Southeastern would probably ask for more than what was justified simply from rising paper stock costs. After the meeting, Ben decided he had heard enough. After all, he prided himself on being a results-oriented manager. There was no way he was going to allow that salesman to keep taking advantage of Coastal Products. Ben called Jeff and told him it was time to rebid the corrugated contract before Southeastern came in with a price increase request. Who did Jeff know that might be interested in the business? Jeff replied he had several companies in mind to include in the bidding process. These companies would surely come in at a lower price, partly because they used lower-grade boxes that would probably work well enough in Coastal Products process. Jeff also explained that these suppliers were not serious contenders for the business. Their purpose was to create competition with the bids. Ben told Jeff to make sure that Southeastern was well aware that these new suppliers were bidding on the contract. He also said to make sure the suppliers knew that price was going to be the determining factor in this quote, because he considered corrugated boxes to be a standard industry item. As the Marketing Manager for Southeastern Corrugated, what would you do upon receiving the request for quotation from Coastal Products?arrow_forwardA firm uses a one-week periodic review inventory system. A two-day lead time is needed for any order, and the firm is willing to tolerate an average of one stock-out per year.a. Using the firm’s service guideline, what is the probability of a stock-out associated with each replenishment decision?b. What is the replenishment level if demand during the review period plus lead-time period is normally distributed with a mean of 60 units and a standard deviation of 12 units?c. What is the replenishment level if demand during the review period plus lead-time period is uniformly distributed between 35 and 85 units?arrow_forward
- 33) please please help me with this Next week, Super Discount Airlines has a flight from New York to Los Angeles that will be booked to capacity. The airline knows from history that an average of 28 customers (with a standard deviation of 14) cancel their reservation or do not show for the flight. Revenue from a ticket on the flight is $122. If the flight is overbooked, the airline has a policy of getting the customer on the next available flight and giving the person a free round-trip ticket on a future flight. The cost of this free round-trip ticket averages $228. Super Discount considers the cost of flying the plane from New York to Los Angeles a sunk cost. By how many seats should Super Discount overbook the flight? Note: Use Excel's NORM.S.INV function to find the z value. Round z value to 2 decimal places. Round your answer to the nearest whole number.arrow_forwardGreat Harvest bakery distributes an average of 1,000 breads per day to local stores and restaurants. This demand is normally distributed with a standard deviation of 95 breads per day. The baking firm who makes the bread requires a 3-day lead time. The manager of Great Harvest expects a 96% service level to satisfy high customer expectations. Refer to the standard normal table N 0.38 0.50 0.67 75 1.28 0.84 80 1.41 1.04 85 1.56 Pr(Z) 1.65 65 1.75 69 2.33 90 92 94 95 96 2.06 98 99 a) The reorder point = enter your response here breads (round your response to the nearest whole number). b) The safety stock = enter your response here breads (round your response to the nearest whole number).arrow_forwardDemand for portable music players for joggers has caused Nancy Industries (Nancy) to grow almost 50 percent over the past year. The number of joggers continues to expand, so Nancy expects demand for music player to also expand, because, as yet, no safety laws have been passed to prevent joggers from wearing them. Demands for the players for last year was as follows : Month Demand (units) Jan 4200 Feb 4300 Mar 4000 Apr 4400 May 5000 Jun 4700 Jul 5300 Aug 4900 Sep 5400 Oct 5700 Nov 6300 Dec 6000 Question : From the choice of simple moving average, weighted moving average, exponential smoothing, and linear regression analysis, which forecasting technique would you consider the most accurate to Nancy Industries? Why?arrow_forward
- Please do not give solution in image format thanku Ram Roy's firm has developed the following supply, demand, cost, and inventory data. Supply Available Period Regular Time Overtime Subcontract Demand Forecast 1 40 15 15 50 2 30 15 15 55 3 40 20 15 60 Initial inventory 30 unitsRegular-time cost per unit$100 Overtime cost per unit$160 Subcontract cost per unit$250 Carrying cost per unit per month$4 Assume that the initial inventory has no holding cost in the first period and backorders are not permitted. Part 2 Allocating production capacity to meet demand at a minimum cost using the transportation method, the total cost is $enter your response here (enter your response as a whole number).arrow_forward1. Safety stock and service levels are positively correlated. True Falsearrow_forwardOPERATION RESEARCHarrow_forward
- What is the distinction between simulated and anticipated average demand:arrow_forwardHistorical records on the use of spare parts for several large hydraulic presses are to serve asan estimate of usage for spares of a newly installed press. Stockout costs involve downtimeexpenses and special ordering costs. These average $4,200 per unit short. Spares cost $800each, and unused parts have zero salvage. Determine the optimal stocking level.Spares Used Relative Frequency Cumulative Frequency0 .20 .201 .40 .602 .30 .903 .10 1.004 or more .001.00arrow_forwarda)Determine the service level b) determine optimal stocking levelarrow_forward
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning