Southeast Soda Pop, Inc., has a new fruit drink for which it has high hopes. John Mittenthal, the production planner, has assembled the following cost data and demand
John’s job is to develop an aggregate plan. The three initial options he wants to evaluate are:
♦ Plan A: a strategy that hires and fires personnel as necessary to meet the forecast.
♦ Plan B: a level strategy.
♦ Plan C: a level strategy that produces 1,200 cases per quarter and meets the forecast demand with inventory and sub-contracting.
a) Which strategy is the lowest-cost plan?
b) If you are John’s boss, the VP for operations, which plan do you implement and why?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
cpmpute for 4 quarters pls
w given info solve for all 4 quarters for production, hire, and layoff
help:) thank you!! two parts
Chapter 13 Solutions
PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
Ch. 13 - Make the case for, and then against, this pricing...Ch. 13 - Prob. 1DQCh. 13 - Why are SOP teams typically cross-functional?Ch. 13 - Prob. 3DQCh. 13 - Prob. 4DQCh. 13 - Prob. 5DQCh. 13 - Prob. 6DQCh. 13 - Prob. 7DQCh. 13 - Prob. 8DQCh. 13 - Prob. 9DQ
Ch. 13 - Prob. 10DQCh. 13 - Prob. 11DQCh. 13 - Prob. 12DQCh. 13 - Prob. 13DQCh. 13 - Prob. 14DQCh. 13 - Prob. 1PCh. 13 - Prob. 2PCh. 13 - The president of Hill Enterprises, Terri Hill,...Ch. 13 - Prob. 4PCh. 13 - Prob. 5PCh. 13 - Prob. 6PCh. 13 - Consuelo Chua, Inc., is a disk drive manufacturer...Ch. 13 - Prob. 8PCh. 13 - Prob. 9PCh. 13 - Prob. 10PCh. 13 - Prob. 11PCh. 13 - Southeast Soda Pop, Inc., has a new fruit drink...Ch. 13 - Ram Roys firm has developed the following supply,...Ch. 13 - Jerusalem Medical Ltd., an Israeli producer of...Ch. 13 - Prob. 15PCh. 13 - Prob. 16PCh. 13 - Prob. 17PCh. 13 - Prob. 18PCh. 13 - Dwayne Cole, owner of a Florida firm that...Ch. 13 - Prob. 20PCh. 13 - Prob. 21PCh. 13 - Prob. 22PCh. 13 - Prob. 23PCh. 13 - Prob. 24PCh. 13 - Prob. 25PCh. 13 - Prob. 26PCh. 13 - Evaluate the various configurations of operating...Ch. 13 - Prob. 2CSCh. 13 - After researching revenue (yield) management in...Ch. 13 - The Magic used its original pricing systems of...Ch. 13 - Prob. 1.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Southeast Soda Pop, Inc., has a new fruit drink forwhich it has high hopes. John Mitten thai, the production planner,has assembled the fo llowing cost data and demand forecast: John's job is to develop an aggregate plan. The three initialoptions he wants to evaluate are:• Plan A: a strategy that hires and fires personnel as necessaryto meet the forecast.• Plan B: a level strategy.• Plan C: a level strategy that produces 1,200 cases per quarterand meets the fo recast demand with inventory and subcontracting.a) Which strategy is the lowest-cost plan?b) If you are John's boss, the VP for operations, which p lan doyou implement and why?arrow_forwardSoutheast Soda Pop, Inc., has a new fruit drink for which it has high hopes. John Mittenthal, the production planner, has assembled the following cost data and demand forecast: Click the icon to view the demand forecast. E Click the icon to view the cost data. John's job is to develop an aggregate plan. The three initial options he wants to evaluate are: • Plan A: a strategy that hires and fires personnel as necessary to meet the forecast. • Plan B: a level strategy. • Plan C: a level strategy that produces 1,000 cases per quarter and meets the forecast demand with inventory and subcontracting. a) Which strategy is the lowest-cost plan? Try hiring and layoffs (to meet the forecast) as necessary (enter your responses as whole numbers). Hiring and Layoff Plan Layoff (Units) Hire Quarter Forecast Production Inits) 1,300 1 1,700 Costs/Other Data Previous quarter's output = 1,300 cases Beginning inventory = 0 cases Stockout cost of backorders = $140 per case Inventory holding cost = $45 per…arrow_forwardNowJuice, Inc. produces bottled pickle juice. A planner has developed an aggregate forecast for demand (in cases) for the next four months. Use the following information to develop an aggregate plan using the LEVEL strategy. Inventory holding cost is $1 per month per case and backlog cost is $5 per month per case. Beginning inventory is zero. Month May June July August Forecast 452 520 600 719 Cost Per Unit Monthly Capacity Regular Production 19.40 400 Overtime Production 1.5 x Regular Prod Cost 400 What is the TOTAL cost of the LEVEL plan over the planning horizon? Correct Answer 51,588.6 CAN SOMEONE SHOW ME HOW THEY GOT THE ANSWER 51588.6arrow_forward
- Forecast Data is given within problem. Cost Data is attached Southeast Soda Pop, Inc., has a new fruit drink for which it has high hopes. John Mittenthal, the production planner, has assembled the following cost data and demand forecast: LOADING... Click the icon to view the demand forecast. LOADING... Click the icon to view the cost data. John's job is to develop an aggregate plan. The three initial options he wants to evaluate are: • Plan A: a strategy that hires and fires personnel as necessary to meet the forecast. • Plan B: a level strategy. • Plan C: a level strategy that produces 1,000 cases per quarter and meets the forecast demand with inventory and subcontracting. Part 2 a) Which strategy is the lowest-cost plan? Try hiring and layoffs (to meet the forecast) as necessary (enter your responses as whole numbers). Hiring and Layoff Plan Quarter Forecast Production Hire (Units) Layoff (Units)…arrow_forward12arrow_forwardManager T. C. Downs of Plum Engines, a producer of lawn mowers and leaf blowers, must develop an aggregate plan given the forecast for engine demand shown in the table. The department has a regular output capacity of 135 engines per month. Regular output has a cost of $60 per engine. The beginning inventory is zero engines. Overtime has a cost of $100 per engine. a. Develop a chase plan that matches the forecast and compute the total cost of your plan. Regular production can be less than regular capacity. (Negative amounts should be indicated by a minus sign. Leave no cells blank - be certain to enter "0" wherever required.) b. Compare the costs to a level plan that uses inventory to absorb fluctuations. Inventory carrying cost is $2 per engine per month. Backlog cost is $120 per engine per month. There should not be a backlog in the last month. Set regular production equal to the monthly average of total forecasted demand. Assume that using overtime is not an option. (Negative amounts…arrow_forward
- 1. Develop an aggregate plan for the following forecast Period 3 4 5 6 7 Total 1 2 8 Forecast 190 230 260 280 210 170 160 260 180 1,940 There are 20 workers who can produce 10 units per period at a cost of P6.00 per unit. There is no beginning invetory and the cost of carrying inventory is P5.00 per unit per period. Backlog cost is P10.00 per unit per period. Will the present workforce able to produce the forecast? b. What is the total cost of the plan? a.arrow_forwardDevelop a chase aggregate plan for Draper using apermanent workforce of 12 employees supplemented by overtime.All demand must be met each period.(a) Show what would happen if this plan were implemented.(b) Calculate the costs associated with this plan.(c) Evaluate the plan in terms of cost, customer service,operations, and human resources.arrow_forward1.Describe the overall frameworks for resource planning in both goods-producing and service-providing organizations. 2.Explain options for aggregate planning 3.Explain the three basic strategies for aggregate planning.arrow_forward
- Southeast Soda Pop, Inc., has a new fruit drink for which it has high hopes. John Mittenthal, the production planner, has assembled the following cost data and demand forecast: demand forecast. Quarter Forecast 1 1,900 2 1,200 3 1,600 4 800 Costs/Other Data Previous quarter's output=1,200 cases Beginning inventory=0 cases Stockout cost of backorders=$160 per case Inventory holding cost=$40 per case at end of quarter Hiring employees=$35 per case Terminating employees=$80 per case Subcontracting cost=$65 per case Unit cost on regular time=$30 per case Overtime cost=$20 extra per case Capacity on regular time=1,900 cases per quarter John's job is to develop an aggregate plan. The three initial options he wants to evaluate are: • Plan A: a strategy that hires and fires personnel as necessary to meet the forecast. • Plan B: a level strategy. • Plan C: a level strategy that…arrow_forward7-3. Nowjuice, Inc., produces Shakewell fruit juice. A planner has developed an aggregate forecast for demand (in cases) for the next eight months. month Apr forecast 4500 May 4400 Jun 6200 Jul 6400 Aug 5800 Sep 6600 Oct 7200 Nov 6900 Use the following information to develop aggregate plans. Regular production cost: $10.00 per case Regular production capacity: 5,000 cases Overtime production cost: $16 per case Subcontracting cost: $20 per case Holding cost: $1 per case per month Beginning inventory: 0 Develop an aggregate plan using each of the following guidelines and compute the total cost for each plan. Which plan has the lowest total cost? (a) Use level production of 5,000 case per month. Supplement using overtime as needed (b) Use a combination of overtime (500 cases per month for the first five months), inventory, and subcontracting (500 cases per month from September to November, if necessary) to handle variations in demand. Note that suitable amounts of overtime for the last…arrow_forwardThe president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: alculator DEPREFERESSESES Cara be Her operations manager is considering a new plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is $65 per unit. Inventory holding cost is $20 per unit per month. Ignore any idle-time costs Evaluate the following plan. This exercise contains only Plan E. Plan E: Keep the current workforce, which is producing 1,600 units per month, and subcontract to meet the rest of the demand. Subcontract cost is $75 per unit. mummill M Pla $100433443 January February March April MESS Month 0 December 1 January 2 February 3 March 4 April 5 May 6 June 7 July 8 August Ask my instructor 1,400 1,600 1,800 1,800 Demand 1.400 1,600 1,800 1,800 2,200 2,100 1,800 1.400 May June July August Production (Units) 1,600 1,600 1,600 1,600 1,600 1,600 1,600 1,600 2,200 2.100 1.800 1,400 S Plan E Subcontract…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY