PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
11th Edition
ISBN: 9780135226742
Author: HEIZER
Publisher: PEARSON
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 13, Problem 19P

Dwayne Cole, owner of a Florida firm that manufactures display cabinets, develops an 8-month aggregate plan. Demand and capacity (in units) are forecast as follows:

Chapter 13, Problem 19P, Dwayne Cole, owner of a Florida firm that manufactures display cabinets, develops an 8-month

The cost of producing each unit is $1,000 on regular time, $1,300 on overtime, and $1,800 on a subcontract. Inventory carrying cost is $200 per unit per month. There is no beginning or ending inventory in stock, and no backorders are permitted from period to period.

Let the production (workforce) vary by using regular time first, then overtime, and then subcontracting.

a) Set up a production plan that minimizes cost by producing exactly what the demand is each month. This plan allows no backorders or inventory. What is this plan’s cost?

b) Through better planning, regular time production can be set at exactly the same amount, 275 units, per month. If demand cannot be met there is no cost assigned to shortages and they will not be filled. Does this alter the solution?

c) If overtime costs per unit rise from $1,300 to $1,400, will your answer to (a) change? What if overtime costs then fall to $1,200?

a)

Expert Solution
Check Mark
Summary Introduction

To determine: The total cost of the plan.

Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.

Answer to Problem 19P

The total cost of the plan is $2,608,300.

Explanation of Solution

Given information:

Regular time cost per unit is given as $1,000, overtime cost is $1,300, and subcontract cost is $1,800 per unit. The capacity and demand are given as follows:

Month Demand Regular time capacity Overtime capacity Subcontract capacity
Initial 0 0 0 0
January 255 235 20 12
February 294 255 24 16
March 321 290 26 15
April 301 300 24 17
May 330 300 30 17
June 320 290 28 19
July 345 300 30 19
August 340 290 30 20

Calculate the total cost:

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 13, Problem 19P , additional homework tip  1

Table 1

Working note:

Demand, regular time capacity, overtime capacity, and subcontract capacity are given.

Determine regular time, overtime, and subcontract units for the month of January:

It is given that the demand for the month of January is 255 units. 235 units would be produced in the regular time (as the regular time capacity is 235). Remaining 20 units would be produced in the overtime (as the overtime capacity is 20). Hence, regular time unit is 235 units and overtime unit is 20 units.

Determine regular time, overtime, and subcontract units for the month of February:

It is given that the demand for the month of February is 294 units. 255 units would be produced in the regular time (as the regular time capacity is 255). From the remaining 39 units, 24 units would be produced in the overtime (as the overtime capacity is 24) and 15 units would be produced using subcontract (as the subcontract capacity is 16). Hence, regular time unit is 255 units, overtime unit is 24 units, and subcontract unit is 15 units.

Determine regular time, overtime, and subcontract units for the month of March:

It is given that the demand for the month of March is 321 units. 290 units would be produced in the regular time (as the regular time capacity is 290). From the remaining 31 units, 26 units would be produced in the overtime (as the overtime capacity is 26) and 5 units would be produced using subcontract (as the subcontract capacity is 15). Hence, regular time unit is 290 units, overtime unit is 26 units, and subcontract unit is 5 units.

Note: The procedure continues for all months.

Increase or decrease for the month of January:

There would be no increase or decrease for the month of January as there is no period compare.

Increase or decrease for the month of February:

Production in the month of January is 235 units and production in the month of February is 255 units. There is an increase of 20 units. Hence, there would be 20 units increase in February.

Increase or decrease for the month of March:

Production in the month of February is 255 units and production in the month of March is 290 units. There is an increase of 35 units. Hence, there would be 35 units increase in March.

Increase or decrease for the month of April:

Production in the month of March is 290 units and production in the month of April is 300 units. There is an increase of 10 units. Hence, there would be 10 units increase in April.

Increase or decrease for the month of May:

Production in the month of April is 300 units and production in the month of May is 300 units. As there is no change in the production units, there would not be any increase or decrease.

Increase or decrease for the month of June:

Production in the month of May is 300 units and production in the month of June is 290 units. There is a decrease of 10 units. Hence, there would be 10 units decrease in June.

Increase or decrease for the month of July:

Production in the month of June is 290 units and production in the month of July is 300 units. There is an increase of 10 units. Hence, there would be 10 units increase in July.

Increase or decrease for the month of August:

Production in the month of July is 300 units and production in the month of August is 290 units. There is a decrease of 10 units. Hence, there would be 10 units decrease in August.

Summary of the table:

Type Units Cost
Regular time 2,260 $2,260,000
Overtime 189 $245,700
Subcontract 57 $102,600
Holding 0 0
Shortage 0 0
Increase 75 0
Decrease 20 0
$2,608,300

Table 2

Working note:

Total units of regular time, overtime, subcontract, shortage, holding, increase, and decrease were calculated in theTable 1.

Calculate the regular time cost:

Regular time cost is calculated by multiplying regular time unit and the given regular time cost per unit. Hence, the regular time cost is $2,260,000.

Regular time cost=Regular time units×Regular time cost per unit=2,260 units×$1,000=$2,260,000

Calculate the overtime cost:

Overtime cost is calculated by multiplying overtime unit and the given overtime cost per unit. Hence, the overtime cost is $245,700.

Overtime cost=Overtime units×Overtime cost per unit=189 units×$1,300=$245,700

Calculate the subcontract cost:

Subcontract cost is calculated by multiplying subcontract unit and the given subcontract cost per unit. Hence, the subcontract cost is $102,600.

Subcontract cost=Subcontract units×Subcontract cost per unit=57 units×$1,800=$102,600

Calculate the increase and decrease cost:

As there is no increase or decrease cost per unit, it would remain 0.

Calculate the total cost:

Total cost is calculated by adding regular time cost, overtime cost, subcontract cost, holding cost, shortage cost, increase cost, and decrease cost.

Total cost={Regular time cost+Overtime cost+Subcontract cost+Holding cost+Shortage cost+Increase cost+Decrease cost}=$2,260,000+$245,700+$102,600+$0+$0+$0+$0=$2,608,300

Hence, the total cost of the plan is $2,608,300.

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The total cost of the plan.

Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.

Answer to Problem 19P

The total cost of the plan is $2,585,100.

Explanation of Solution

Given information:

Regular time cost per unit is given as $1,000, overtime cost is $1,300, and subcontract cost is $1,800 per unit. The capacity and demand are given as follows:

Month Demand Regular time capacity Overtime capacity Subcontract capacity
Initial 0 0 0 0
January 255 275 20 12
February 294 275 24 16
March 321 275 26 15
April 301 275 24 17
May 330 275 30 17
June 320 275 28 19
July 345 275 30 19
August 340 275 30 20

Calculate the total cost:

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 13, Problem 19P , additional homework tip  2

Table 3

Working note:

Demand, regular time capacity, overtime capacity, and subcontract capacity are given.

Determine regular time, overtime, and subcontract units for the month of January:

It is given that the demand for the month of January is 255 units. Whole 255 units would be produced in the regular time (as the regular time capacity is 275). Hence, regular time unit is 255 units.

Determine regular time, overtime, and subcontract units for the month of February:

It is given that the demand for the month of February is 294 units. 275 units would be produced in the regular time (as the regular time capacity is 275). Remaining 19 units would be produced in the overtime (as the overtime capacity is 24). Hence, regular time unit is 275 units and overtime unit is 19 units.

Determine regular time, overtime, and subcontract units for the month of March:

It is given that the demand for the month of March is 321 units. 275 units would be produced in the regular time (as the regular time capacity is 290). From the remaining 46 units, 26 units would be produced in the overtime (as the overtime capacity is 26) and 15 units would be produced using subcontract (as the subcontract capacity is 15). Hence, regular time unit is 275 units, overtime unit is 26 units, and subcontract unit is 15 units. Remaining 5 units is a shortage.

Note: The procedure continues for all months.

Increase or decrease for the month of January:

There would be no increase or decrease for the month of January as there is no period compare.

Increase or decrease for the month of February:

Production in the month of January is 255 units and production in the month of February is 275 units. There is an increase of 20 units. Hence, there would be 20 units increase in February.

Increase or decrease from the month of March to August:

As the production for regular time remains the same, there would be no increase or decrease from the month of March to August.

Summary of the table:

Type Units Cost
Regular time 2,180 $2,180,000
Overtime 187 $243,100
Subcontract 90 $162,000
Holding 0 0
Shortage 49 0
Increase 20 0
Decrease 0
$2,585,100

Table 4

Working note:

Total units of regular time, overtime, subcontract, shortage, holding, increase, and decrease were calculated in theTable 3.

Calculate the regular time cost:

Regular time cost is calculated by multiplying regular time unit and the given regular time cost per unit. Hence, the regular time cost is $2,180,000.

Regular time cost=Regular time units×Regular time cost per unit=2,180 units×$1,000=$2,180,000

Calculate the overtime cost:

Overtime cost is calculated by multiplying overtime unit and the given overtime cost per unit. Hence, the overtime cost is $243,100.

Overtime cost=Overtime units×Overtime cost per unit=187 units×$1,300=$243,100

Calculate the subcontract cost:

Subcontract cost is calculated by multiplying subcontract unit and the given subcontract cost per unit. Hence, the subcontract cost is $162,000.

Subcontract cost=Subcontract units×Subcontract cost per unit=90 units×$1,800=$162,000

Calculate the increase and decrease cost:

As there is no increase or decrease cost per unit, it would remain 0.

Calculate the total cost:

Total cost is calculated by adding regular time cost, overtime cost, subcontract cost, holding cost, shortage cost, increase cost, and decrease cost.

Total cost={Regular time cost+Overtime cost+Subcontract cost+Holding cost+Shortage cost+Increase cost+Decrease cost}=$2,180,000+$243,100+$162,000+$0+$0+$0+$0=$2,585,100

Hence, the total cost of the plan is $2,585,100.

c)

Expert Solution
Check Mark
Summary Introduction

To determine: The total cost of the plan, if the overtime increased to $1,400.

Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.

Answer to Problem 19P

The total cost of the plan is $2,627,200.

Explanation of Solution

Given information:

Regular time cost per unit is given as $1,000, overtime cost is $1,400, and subcontract cost is $1,800 per unit. The capacity and demand are given as follows:

Month Demand Regular time capacity Overtime capacity Subcontract capacity
Initial 0 0 0 0
January 255 235 20 12
February 294 255 24 16
March 321 290 26 15
April 301 300 24 17
May 330 300 30 17
June 320 290 28 19
July 345 300 30 19
August 340 290 30 20

Calculate the total cost:

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 13, Problem 19P , additional homework tip  3

Table 5

Working note:

Demand, regular time capacity, overtime capacity, and subcontract capacity are given.

Determine regular time, overtime, and subcontract units for the month of January:

It is given that the demand for the month of January is 255 units. 235 units would be produced in the regular time (as the regular time capacity is 235). Remaining 20 units would be produced in the overtime (as the overtime capacity is 20). Hence, regular time unit is 235 units and overtime unit is 20 units.

Determine regular time, overtime, and subcontract units for the month of February:

It is given that the demand for the month of February is 294 units. 255 units would be produced in the regular time (as the regular time capacity is 255). From the remaining 39 units, 24 units would be produced in the overtime (as the overtime capacity is 24) and 15 units would be produced using subcontract (as the subcontract capacity is 16). Hence, regular time unit is 255 units, overtime unit is 24 units, and subcontract unit is 15 units.

Determine regular time, overtime, and subcontract units for the month of March:

It is given that the demand for the month of March is 321 units. 290 units would be produced in the regular time (as the regular time capacity is 290). From the remaining 31 units, 26 units would be produced in the overtime (as the overtime capacity is 26) and 5 units would be produced using subcontract (as the subcontract capacity is 15). Hence, regular time unit is 290 units, overtime unit is 26 units, and subcontract unit is 5 units.

Note: The procedure continues for all months.

Increase or decrease for the month of January:

There would be no increase or decrease for the month of January as there is no period compare.

Increase or decrease for the month of February:

Production in the month of January is 235 units and production in the month of February is 255 units. There is an increase of 20 units. Hence, there would be 20 units increase in February.

Increase or decrease for the month of March:

Production in the month of February is 255 units and production in the month of March is 290 units. There is an increase of 35 units. Hence, there would be 35 units increase in March.

Increase or decrease for the month of April:

Production in the month of March is 290 units and production in the month of April is 300 units. There is an increase of 10 units. Hence, there would be 10 units increase in April.

Increase or decrease for the month of May:

Production in the month of April is 300 units and production in the month of May is 300 units. As there is no change in the production units, there would not be any increase or decrease.

Increase or decrease for the month of June:

Production in the month of May is 300 units and production in the month of June is 290 units. There is a decrease of 10 units. Hence, there would be 10 units decrease in June.

Increase or decrease for the month of July:

Production in the month of June is 290 units and production in the month of July is 300 units. There is an increase of 10 units. Hence, there would be 10 units increase in July.

Increase or decrease for the month of August:

Production in the month of July is 300 units and production in the month of August is 290 units. There is a decrease of 10 units. Hence, there would be 10 units decrease in August.

Calculate the total cost if the overtime cost per unit increased to $1,400:

Type Units Cost
Regular time 2,260 $2,260,000
Overtime 189 $264,600
Subcontract 57 $102,600
Holding 0 0
Shortage 0 0
Increase 75 0
Decrease 20 0
$2,627,200

Table 6

Working note:

Total units of regular time, overtime, subcontract, shortage, holding, increase, and decrease were calculated in theTable 5.

Calculate the regular time cost:

Regular time cost is calculated by multiplying regular time unit and the given regular time cost per unit. Hence, the regular time cost is $2,260,000.

Regular time cost=Regular time units×Regular time cost per unit=2,260 units×$1,000=$2,260,000

Calculate the overtime cost:

Overtime cost is calculated by multiplying overtime unit and the given overtime cost per unit. Hence, the overtime cost is $264,600.

Overtime cost=Overtime units×Overtime cost per unit=189 units×$1,400=$264,600

Calculate the subcontract cost:

Subcontract cost is calculated by multiplying subcontract unit and the given subcontract cost per unit. Hence, the subcontract cost is $102,600.

Subcontract cost=Subcontract units×Subcontract cost per unit=57 units×$1,800=$102,600

Calculate the increase and decrease cost:

As there is no increase or decrease cost per unit, it would remain 0.

Calculate the total cost:

Total cost is calculated by adding regular time cost, overtime cost, subcontract cost, holding cost, shortage cost, increase cost, and decrease cost.

Total cost={Regular time cost+Overtime cost+Subcontract cost+Holding cost+Shortage cost+Increase cost+Decrease cost}=$2,260,000+$245,700+$264,600+$0+$0+$0+$0=$2,627,200

Hence, the total cost of the plan is $2,627,200.

Calculate the total cost if the overtime cost per unit increased to $1,200:

Type Units Cost
Regular time 2,260 $2,260,000
Overtime 189 $226,800
Subcontract 57 $102,600
Holding 0 0
Shortage 0 0
Increase 75 0
Decrease 20 0
$2,589,400

Table 7

Working note:

Total units of regular time, overtime, subcontract, shortage, holding, increase, and decrease were calculated in theTable 6.

Calculate the regular time cost:

Regular time cost is calculated by multiplying regular time unit and the given regular time cost per unit. Hence, the regular time cost is $2,260,000.

Regular time cost=Regular time units×Regular time cost per unit=2,260 units×$1,000=$2,260,000

Calculate the overtime cost:

Overtime cost is calculated by multiplying overtime unit and the given overtime cost per unit. Hence, the overtime cost is $264,600.

Overtime cost=Overtime units×Overtime cost per unit=189 units×$1,200=$226,800

Calculate the subcontract cost:

Subcontract cost is calculated by multiplying subcontract unit and the given subcontract cost per unit. Hence, the subcontract cost is $102,600.

Subcontract cost=Subcontract units×Subcontract cost per unit=57 units×$1,800=$102,600

Calculate the increase and decrease cost:

As there is no increase or decrease cost per unit, it would remain 0.

Calculate the total cost:

Total cost is calculated by adding regular time cost, overtime cost, subcontract cost, holding cost, shortage cost, increase cost, and decrease cost.

Total cost={Regular time cost+Overtime cost+Subcontract cost+Holding cost+Shortage cost+Increase cost+Decrease cost}=$2,260,000+$245,700+$226,800+$0+$0+$0+$0=$2,589,400

Hence, the total cost of the plan is $2,589,400.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
The president of Hill​ Enterprises, Terri​ Hill, projects the​ firm's aggregate demand requirements over the next 8 months as​ follows:   January 1,400 May 2,100 February 1,700 June 2,100 March 1,600 July 1,700 April 1,900 August 1,500      Her operations manager is considering a new​ plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is ​$60 per unit. Inventory holding cost is ​$20 per unit per month. Ignore any​ idle-time costs. Evaluate the following plans D and E. Plan D​: Keep the current workforce stable at producing 1,600 units per month. In addition to the regular​ production, another 20​% of the normal production units can be produced in overtime at an additional cost of ​$50 per unit. A warehouse now constrains the maximum allowable inventory on hand to 600 units or less. ​Note: Do not produce in overtime if production or inventory are adequate to cover demand.…
The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: May 2,100 January February 1,450 1,700 1,700 June 2,300 July 1,900 March April 1,700 August 1,300 Her operations manager is considering a new plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is $65 per unit. Inventory holding cost is $25 per unit per month. Ignore any idle-time costs. Evaluate the following plan. This exercise contains only Plan E. Plan E: Keep the current workforce, which is producing 1,600 units per month, and subcontract to meet the rest of the demand. Subcontract cost is $75 per unit. Month 10 December 1 January 2 February 3 March 4 April 5 May 6 June 7 July 8 August Demand 1,450 1,700 1,700 1,700 2,100 2,300 1,900 1,300 Production (Units) 1,600 1,600 1,600 1,600 1,600 1,600 1,600 1,600 Plan E Ending Subcontract (Units) Inventory 200 The total subcontracting cost = $ (Enter your response as…
The president of Hill​ Enterprises, Terri​ Hill, projects the​ firm's aggregate demand requirements over the next 8 months as​ follows:     January 1,500 May 2,300 February 1,700 June 2,100 March 1,700 July 1,900 April 1,700 August 1,500   Her operations manager is considering a new​ plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is ​$125 per unit. Inventory holding cost is ​$20 per unit per month. Ignore any​ idle-time costs. The plan is called plan C.   Plan​ C: Keep a stable workforce by maintaining a constant production rate equal to the average gross requirements excluding initial inventory and allow varying inventory levels.   Conduct your analysis for January through August. The average monthly demand requirement=18001800 units. ​(Enter your response as a whole​ number.) In order to arrive at the​ costs, first compute the ending inventory and stockout units for each month by filling in…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY