a)
To determine: The number of tires Company RMT should order each time it places an order.
Introduction: Inventory management is the process of ordering, storing and using inventory of the company such raw material, components and finished goods. It governs the flow of goods from manufacturers to warehouse and to the point of sale. The key function is to maintain record of flow of new or returned products which enters or leaves the company.
a)
Answer to Problem 25P
The number of tires Company RMT should order each time it places an order is 667.
Explanation of Solution
Given information:
Formula:
Where
Calculation of optimal order quantity:
Calculation of EOQ for orders less than 500 tires:
EOQ for order less than 500 tires is calculated by multiplying 2, 20,000 and 40 and dividing the resultant with the product of 0.2 and 20 and taking square root which gives 632.5 tires.
Calculation of EOQ for orders between 500 to 999 tires:
EOQ for order between 500 to 999 tires is calculated by multiplying 2, 20,000 and 40 and dividing the resultant with the product of 0.2 and 18 and taking square root which gives 667 tires.
Calculation of EOQ for orders more than 1,000 tires:
EOQ for order orders more than 1,000 tires is calculated by multiplying 2, 20,000 and 40 and dividing the resultant with the product of 0.2 and 17 and taking square root which gives 686 tires.
Based on the above calculations, EOQ of orders between 500 to 999 tires gives optimal order quantity as the EOQ lies within the quantities ordered. Therefore the optimal order quantity is 667 tires at $0.18.
Hence, the number of tires Company RMT should order each time it places an order is 667.
b)
To determine: The total annual cost of the policy.
b)
Answer to Problem 25P
The total annual cost of the policy is $342,500 per year.
Explanation of Solution
Given information:
Formula:
Calculation of total annual cost:
The total annual cost for ordering quantity 667 tires is compared with 1000 tires to find the optimal total cost and quantities to be ordered by the company.
Total annual cost for 667 tires:
Total annual cost is calculated by adding holding cost, ordering cost and unit cost and the values are substituted in the above formula which yields $362,400 as total cost per year.
The total annual cost for 667 ordering quantity is $362,400/year.
Total annual cost for 1000 tires:
Total annual cost is calculated by adding holding cost, ordering cost and unit cost and the values are substituted in the above formula which yields $342,500 as total cost per year.
The total annual cost for 1000 tires is $342,500/year.
The total annual cost for 1000 tires is lesser than total annual cost for 667 tires and so company RMT should order 1,000 tires each time.
Hence, the total annual cost of the policy is $342,500 per year.
Want to see more full solutions like this?
Chapter 12 Solutions
Principles Of Operations Management
- Solve the following Question 1. How do volume and variety affect the process selection and layout types? Discuss 2. How is the human resource aspect important to operation function? Discuss 3. Discuss the supply network design and its impact on the overall performance of the organization.arrow_forwardHelp with question?arrow_forwardWhat are some good examples of bullet points on a resume for a Christian Elementary School?arrow_forward
- What is an example of a cover letter for a Christian School Long-Term Substitute Teaching position?arrow_forwardThe supply chain is a conventional notion, but organizations are only really interested in making products that they can sell to customers. Provided they have reliable supplies of materials and reasonable transport for finished products, logistics is irrelevant. Do you think this is true? If yes, explain, and if no, clearly explain as well.arrow_forwardworking as a program operations managerarrow_forward
- 12 X1, X230 1 x =0x2 write the Following linear Programming model by 1- general Form Canonical Forms Canonical formY 2- Standard Form Max Z=35X+ 4 X 2 +6 X3 ST. X+2X2-5x3 = 40 3X, + 6X2 + 7x 3 = 30 7x, +lox2 x3 = 50 X3 X 2 X 3 <0arrow_forwarda/ a Minimum cost assign each worker for one job at Jobs J1 12 33 WI 2 4 6 W2 5 W3 5 33 6 7arrow_forwardوبة واضافة هذه القيمة الى القيم Ex: Assign each job for each worker at minimum total Cost عمل لكل عامل وبأقل كلفة ممكنة obs الأعمال Workors العمال J1 J2 J3 J4 W₁ 15 13 14 12 W2 11 12 15 13 W3 13 12 10 11 W4 15 17 14 16arrow_forward
- The average completion time (flow time) for the sequence developed using the FCFS rule = 11.75 days (round your response to two decimal places). The percentage utilization for the sequence developed using the FCFS rule = 42.55 % (enter your response as a percentage rounded to two decimal places). b) Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): An Alabama lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: Job Due Date A 212 B 209 C 208 D 210 Duration (days) 6 3 3 8 Sequence 1 Job B 2 3 4 A D The average tardiness (job lateness) for the sequence developed using the SPT rule = 5.00 days (round your response to two decimal places). The average completion time (flow time) for the sequence developed using the SPT rule = 10.25 days…arrow_forwardWith the aid of examples, fully discuss any five (5) political tactics used in organisations.arrow_forwarda. With the aid of examples, define discrimination. b. Fully discuss any four (4) types of discrimination in the workplacearrow_forward
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning