Abey Kuruvilla, of Parkside Plumbing, uses 1,200 of a certain spare part that costs $25 for each order, with an annual holding cost of $24.
- a. Calculate the total cost for order sizes of 25, 40, 50, 60, and 100.
- b. Identify the economic order quantity and consider the implications for making an error in calculating economic order quantity.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Abey Kuruvilla, of Parkside Plumbing, uses 1,200 of a certain spare part that costs $25 for each order, with an annual holding cost of $24. a) Calculate the total cost for order sizes of 25, 40, 50, 60, and 100. b) Identify the economic order quantity and consider the implications for making an error in calculating economic order quantity.
Abey Kuruvilla, of Parkside Plumbing, uses 1,200 of a certain spare part that costs $25.00 for each order, with an annual holding cost of $24.00.
a) Calculate the total cost for order sizes of 25, 40, 50, 60, and 100 (round your response to the nearest whole number).
b) What is the economic order quantity? units (round your response to the nearest whole number).
Order Size
25
40
50
60
100
Total Cost ($)
Question 1
For supply item ABC, Andrews Company has been ordering 400 units per week. A new
purchasing agent has been hired by the company who wants to start using the economic-order-
quantity method and its supporting decision elements. She has gathered the following
information:
Annual demand in units
Lead time, in days
Ordering costs
Insurance and handling costs
Purchase price per unit
Return on cash investment
20,800
5
$22
$7
$15
15%
Required
Chapter 12 Solutions
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Ch. 12 - Question 1. Describe the four types of inventory.Ch. 12 - Question
2. With the advent of low-cost...Ch. 12 - Question
3. What is the purpose of the ABC...Ch. 12 - Question
4. Identify and explain the types of...Ch. 12 - Question 5. Explain the major assumptions of the...Ch. 12 - Question 6. What is the relationship of the...Ch. 12 - Question
7. Explain why it is not necessary to...Ch. 12 - Question 8. What are the advantages of cycle...Ch. 12 - What impact does a decrease in setup time have on...Ch. 12 - When quantity discounts are offered, why is it not...
Ch. 12 - What is meant by service level?Ch. 12 - Explain the following: All things being equal, the...Ch. 12 - Describe the difference between a fixed-quantity...Ch. 12 - Explain what is meant by the expression robust...Ch. 12 -
15. What is “safety stock”? What does safety...Ch. 12 - When demand is not constant, the reorder point is...Ch. 12 - How are inventory levels monitored in retail...Ch. 12 - State a major advantage, and a major disadvantage,...Ch. 12 - L. Houts Plastics is a large manufacturer of...Ch. 12 - Boreki Enterprises has the following 10 items in...Ch. 12 - Jean-Marie Bourjollys restaurant has the following...Ch. 12 - Lindsay Electronics, a small manufacturer of...Ch. 12 - William Bevilles computer training school, in...Ch. 12 - • 12.6 If D = 8,000 per month, S = $45 per order,...Ch. 12 - Henry Crouchs law office has traditionally ordered...Ch. 12 - Matthew Liotines Dream Store sells beds and...Ch. 12 - Southeastern Bell stocks a certain switch...Ch. 12 - Lead time for one of your fastest-moving products...Ch. 12 - Annual demand for the notebook binders at Duncans...Ch. 12 - Thomas Kratzer is the purchasing manager for the...Ch. 12 - Joe Henrys machine shop uses 2,500 brackets during...Ch. 12 - Abey Kuruvilla, of Parkside Plumbing, uses 1,200...Ch. 12 - ••• 12.15 M. Cotteleer Electronics supplies...Ch. 12 - •• 12.16 Race One Motors is an Indonesian car...Ch. 12 - Radovilsky Manufacturing Company, in Hayward,...Ch. 12 - Arthur Meiners is the production manager of...Ch. 12 - Cesar Rego Computers, a Mississippi chain of...Ch. 12 - Bell Computers purchases integrated chips at 350...Ch. 12 - Wang Distributors has an annual demand for an...Ch. 12 - Question 12.22 The catering manager of La Vista...Ch. 12 - Prob. 25PCh. 12 - Prob. 26PCh. 12 - Prob. 27PCh. 12 - Question 12.26 Emery Pharmaceutical uses an...Ch. 12 - Prob. 29PCh. 12 - Prob. 30PCh. 12 - Question 12.27 Barbara Flynn is in charge of...Ch. 12 - Question 12.28 Based on available information,...Ch. 12 - Question 12.29 Authentic Thai rattan chairs...Ch. 12 - Question 12.30 Tobacco is shipped from North...Ch. 12 - Prob. 45PCh. 12 - Question 12.32 Chicagos Hard Rock Hotel...Ch. 12 - Question 12.33 First Printing has contracts with...Ch. 12 - Prob. 48PCh. 12 - Question 12.40 A gourmet coffee shop in downtown...Ch. 12 - Question 12.36 Cynthia Knotts oyster bar buys...Ch. 12 - Question 12.37 Henrique Correas bakery prepares...Ch. 12 - Question 12.38 University of Florida football...Ch. 12 - Question Zhou Bicycle Company Zhou Bicycle...Ch. 12 - Question Zhou Bicycle Company Zhou Bicycle...Ch. 12 - Question Zhou Bicycle Company Zhou Bicycle...Ch. 12 - Parker Hi-Fi Systems Parker Hi-Fi Systems, located...Ch. 12 - Parker Hi-Fi Systems Parker Hi-Fi Systems, located...Ch. 12 - Parker Hi-Fi Systems Parker Hi-Fi Systems, located...Ch. 12 - Question Frito-Lay has flourished since its...Ch. 12 - Question Frito-Lay has flourished since its...Ch. 12 - Question Frito-Lay has flourished since its...Ch. 12 - Question Frito-Lay has flourished since its...Ch. 12 - Question Frito-Lay has flourished since its...Ch. 12 - Question Frito-Lay has flourished since its...Ch. 12 - Question Frito-Lay has flourished since its...Ch. 12 - Inventory Control at Wheeled Coach Video Case...Ch. 12 - Prob. 2.2VCCh. 12 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The chapter presented various approaches for the control of inventory investment. Discuss three additional approaches not included that might involve supply chain managers.arrow_forwardEpworth Co. predicts that it will use 360,000 gallons of material during the year. It anticipates that it will cost $72 to place each order. The annual carrying cost is $4 per gallon. a. Determine the most economical order quantity by using the EOQ formula. b. Determine the annual order and carrying costs at the EOQ point.arrow_forwardEOQ, reorder point, and safety stock Alexis Company uses 916 units of a product per year on a continuous basis. The product has a fixed cost of $60 per order, and its carrying cost is $3 per unit per year. It takes 5 days to receive a shipment after an order is placed, and the firm wishes to hold 10 days' usage in inventory as a safety stock. a. Calculate the EOQ. b. Determine the average level of inventory. (Note: Use a 365-day year to calculate daily usage.) c. Determine the reorder point. d. Indicate which of the following variables change if the firm does not hold the safety stock: (1) order cost, (2) carrying cost, (3) total inventory cost, (4) reorder point, (5) economic order quantity. a. Alexis' EOQ is units. (Round to the nearest whole number.)arrow_forward
- The materials manager for a billiard ball maker must periodically place orders for resin, one of the raw materials used in producing billiard balls. She knows that manufacturing uses resin at a rate of 50 kilograms each day, and that it costs $.04 per day to carry a kilogram of resin in inventory. She also knows that the order costs for resin are $100 per order, and that the lead time for delivery is four days. If the order size was 1,000 kilograms of resin, what would be the average inventory level?arrow_forward21. The expected annual usage of a particular material is 540,000 units, and the standard order size is 36,000 units The invoice cost of each unit is P900, and the ordering cost per order is P240. Assuming the company does not maintain safety stock. What is the ordering cost?arrow_forwardCorry Corporation purchases 1,200,000 unit per year of one component. The Fixed Cost per order is $25. The annual carrying cost of the item is 27% of its $2 cost. Show Computations and Explanations. Determine the EOQ under each of the following conditions: A. Using the same data above, compute the EOQ. (Format: 11,111) B. What if the order cost is zero, what is the EOQ? (Format: 11,111)arrow_forward
- 20. The expected annual usage of a particular material is 540,000 units, and the standard order size is 36,000 units The invoice cost of each unit is P900, and the ordering cost per order is P240. Assuming the company does not maintain safety stock. What is the average inventory?arrow_forwardWalrus Company has the following information available concerning one of its inventory items: Cost of placing an order $30.00 Unit carrying cost per year $3.00 Annual unit demand 6,625 Safety stock 125 Average daily demand 25 Normal lead time in days 10 If there is a delay in shipping the item, approximately how many days can be covered by the safety stock? a.5 days b.110 days c.26 days d.31 daysarrow_forwardDiscount-Mart, a major East Coast retailer, wants todetermine the economic order quantity (see Chapter 12 for EOQformulas) for its halogen lamps. It currently buys all halogenlamps from Specialty Lighting Manufacturers in Atlanta. Annualdemand is 2,000 lamps, ordering cost per order is $30, and annualcarrying cost per lamp is $12. a) What is the EOQ?b) What are the total annual costs of holding and ordering(managing) this inventory?c) How many orders should Discount-Mart place with SpecialtyLighting per year?arrow_forward
- EOQ, reorder point, and safety stock Alexis Company uses 937units of a product per year on a continuous basis. The product has a fixed cost of $44 per order, and its carrying cost is $4 per unit per year. It takes 5 days to receive a shipment after an order is placed, and the firm wishes to hold 10 days' usage in inventory as a safety stock. a. Calculate the EOQ. b. Determine the average level of inventory. (Note: Use a 365-day year to calculate daily usage.) c. Determine the reorder point. d. Indicate which of the following variables change if the firm does not hold the safety stock: (1) order cost, (2) carrying cost, (3) total inventory cost, (4) reorder point, (5) economic order quantity.arrow_forward2) A service garage operates 300 days and uses 120 boxes of cleaning cloths a year. The boxes cost RM6 each. Ordering cost is RM3, and the holding costs is 10% of purchase costs per unit on annual basis. i) The economic order quantity? ii) Compute total cost of managing inventory. iii) Determine the number of order cycles per year. iv) Expected time between orders.arrow_forwardA bey Kuru villa, of Parkside Plumbing, uses I ,200 ofa certain spare part that costs $25 for each order, with an annualholding cost of $24.a) Calculate the total cost for order sizes of25, 40, 50, 60, and 100.b) Identify the economic order quantity and consider the implicationsfor making an error in calculating economic orderquantity.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY