Southeastern Bell stocks a certain switch connector at its central warehouse for supplying field service offices. The yearly demand for these connectors is 15,000 units. Southeastern estimates its annual holding cost for this item to be $25 per unit. The cost to place and process an order from the supplier is $75. The company operates 300 days per year, and the lead time to receive an order from the supplier is 2 working days.
- a. Find the economic order quantity
- b. Find the annual holding costs.
- c. Find the annual ordering costs.
- d. What is the reorder point?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Southeastern Bell stocks a certain switch connector at its central warehouse for supplying field service offices. The
yearly demand for these connectors is 14,100 units. Southeastern estimates its annual holding cost for this item to be
$22 per unit. The cost to place and process an order from the supplier is $73. The company operates 300 days per year,
and the lead time to receive an order from the supplier is 3 working days.
a) What is the economic order quantity? 306 units (round your response to the nearest whole number).
b) What are the annual holding costs? $
(round your response to the nearest whole number).
Southeastern Bell stocks a certain switch connector at its central warehouse for supplying field service offices. The
yearly demand for these connectors is 14,100 units. Southeastern estimates its annual holding cost for this item to be
$22 per unit. The cost to place and process an order from the supplier is $73. The company operates 300 days per year,
and the lead time to receive an order from the supplier is 3 working days.
a) What is the economic order quantity? 306 units (round your response to the nearest whole number).
b) What are the annual holding costs? $ 3365 (round your response to the nearest whole number).
c) What are the annual ordering costs? $ 3364 (round your response to the nearest whole number).
d) What is the reorder point? units (round your response to the nearest whole number).
Southeastern Bell stocks a certain switch connector at its central warehouse for supplying field service offices. The yearly demand for these connectors is 15,500 units. Southeastern estimates its annual holding cost for this item to be
$23 per unit. The cost to place and process an order from the supplier is $78. The company operates 300 days per year, and the lead time to receive an order from the supplier is 3 working days.
a) What is the economic order quantity?
units (round your response to the nearest whole number).
(round your response to the nearest whole number).
b) What are the annual holding costs? $
c) What are the annual ordering costs? $
(round your response to the nearest whole number).
d) What is the reorder point? units (round your response to the nearest whole number).
Chapter 12 Solutions
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Ch. 12 - Question 1. Describe the four types of inventory.Ch. 12 - Question
2. With the advent of low-cost...Ch. 12 - Question
3. What is the purpose of the ABC...Ch. 12 - Question
4. Identify and explain the types of...Ch. 12 - Question 5. Explain the major assumptions of the...Ch. 12 - Question 6. What is the relationship of the...Ch. 12 - Question
7. Explain why it is not necessary to...Ch. 12 - Question 8. What are the advantages of cycle...Ch. 12 - What impact does a decrease in setup time have on...Ch. 12 - When quantity discounts are offered, why is it not...
Ch. 12 - What is meant by service level?Ch. 12 - Explain the following: All things being equal, the...Ch. 12 - Describe the difference between a fixed-quantity...Ch. 12 - Explain what is meant by the expression robust...Ch. 12 -
15. What is “safety stock”? What does safety...Ch. 12 - When demand is not constant, the reorder point is...Ch. 12 - How are inventory levels monitored in retail...Ch. 12 - State a major advantage, and a major disadvantage,...Ch. 12 - L. Houts Plastics is a large manufacturer of...Ch. 12 - Boreki Enterprises has the following 10 items in...Ch. 12 - Jean-Marie Bourjollys restaurant has the following...Ch. 12 - Lindsay Electronics, a small manufacturer of...Ch. 12 - William Bevilles computer training school, in...Ch. 12 - • 12.6 If D = 8,000 per month, S = $45 per order,...Ch. 12 - Henry Crouchs law office has traditionally ordered...Ch. 12 - Matthew Liotines Dream Store sells beds and...Ch. 12 - Southeastern Bell stocks a certain switch...Ch. 12 - Lead time for one of your fastest-moving products...Ch. 12 - Annual demand for the notebook binders at Duncans...Ch. 12 - Thomas Kratzer is the purchasing manager for the...Ch. 12 - Joe Henrys machine shop uses 2,500 brackets during...Ch. 12 - Abey Kuruvilla, of Parkside Plumbing, uses 1,200...Ch. 12 - ••• 12.15 M. Cotteleer Electronics supplies...Ch. 12 - •• 12.16 Race One Motors is an Indonesian car...Ch. 12 - Radovilsky Manufacturing Company, in Hayward,...Ch. 12 - Arthur Meiners is the production manager of...Ch. 12 - Cesar Rego Computers, a Mississippi chain of...Ch. 12 - Bell Computers purchases integrated chips at 350...Ch. 12 - Wang Distributors has an annual demand for an...Ch. 12 - Question 12.22 The catering manager of La Vista...Ch. 12 - Prob. 25PCh. 12 - Prob. 26PCh. 12 - Prob. 27PCh. 12 - Question 12.26 Emery Pharmaceutical uses an...Ch. 12 - Prob. 29PCh. 12 - Prob. 30PCh. 12 - Question 12.27 Barbara Flynn is in charge of...Ch. 12 - Question 12.28 Based on available information,...Ch. 12 - Question 12.29 Authentic Thai rattan chairs...Ch. 12 - Question 12.30 Tobacco is shipped from North...Ch. 12 - Prob. 45PCh. 12 - Question 12.32 Chicagos Hard Rock Hotel...Ch. 12 - Question 12.33 First Printing has contracts with...Ch. 12 - Prob. 48PCh. 12 - Question 12.40 A gourmet coffee shop in downtown...Ch. 12 - Question 12.36 Cynthia Knotts oyster bar buys...Ch. 12 - Question 12.37 Henrique Correas bakery prepares...Ch. 12 - Question 12.38 University of Florida football...Ch. 12 - Question Zhou Bicycle Company Zhou Bicycle...Ch. 12 - Question Zhou Bicycle Company Zhou Bicycle...Ch. 12 - Question Zhou Bicycle Company Zhou Bicycle...Ch. 12 - Parker Hi-Fi Systems Parker Hi-Fi Systems, located...Ch. 12 - Parker Hi-Fi Systems Parker Hi-Fi Systems, located...Ch. 12 - Parker Hi-Fi Systems Parker Hi-Fi Systems, located...Ch. 12 - Question Frito-Lay has flourished since its...Ch. 12 - Question Frito-Lay has flourished since its...Ch. 12 - Question Frito-Lay has flourished since its...Ch. 12 - Question Frito-Lay has flourished since its...Ch. 12 - Question Frito-Lay has flourished since its...Ch. 12 - Question Frito-Lay has flourished since its...Ch. 12 - Question Frito-Lay has flourished since its...Ch. 12 - Inventory Control at Wheeled Coach Video Case...Ch. 12 - Prob. 2.2VCCh. 12 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Southeastern Bell stocks a certain switch connector at its central warehouse for supplying field service offices. The yearly demand for these connectors is 15,900 units. Southeastern estimates its annual holding cost for this item to be $25 per unit. The cost to place and process an order from the supplier is $78. The company operates 300 days per year, and the lead time to receive an order from the supplier is 2 working days. a) What is the economic order quantity? units (round your response to the nearest whole number).arrow_forwardSoutheastern Bell stocks a certain switch connector at its central warehouse for supplying field service offices. The yearly demand for these connectors is 14,100 units. Southeastern estimates its annual holding cost for this item to be $25 per unit. The cost to place and process an order from the supplier is $76. The company operates 300 days per year, and the lead time to receive an order from the supplier is 3 working days. a) What is the economic order quantity? units (round your response to the nearest whole number).arrow_forwardSoutheastern Bell stocks a certain switch connectorvat its central warehouse for supplying field service offices. The yearly demand for these connectors is 15,000 units. Southeastern estimates its annual holding cost for this item to be $25 per unit. The cost to place and process an order from the supplier is $75. The company operates 300 days per year, and the lead time to receive an order from the supplier is 2 working days. a) Find the economic order quantity. b) Find the annual holding costs. c) Find the annual ordering costs. d) What is the reorder point?arrow_forward
- Southeastern Bell stocks a certain switch connector at its central warehouse for supplying field service offices. The yearly demand for these connectors is 15,200 units. Southeastern estimates its annual holding cost for this item to be $26 per unit. The cost to place and process an order from the supplier is $73. The company operates 300 days per year, and the lead time to receive an order from the supplier is 2 working days. Part 2 a) What is the economic order quantity? enter your response here units (round your response to the nearest whole number). Part 3 b) What are the annual holding costs? $enter your response here (round your response to the nearest whole number). Part 4 c) What are the annual ordering costs? $enter your response here (round your response to the nearest whole number). Part 5 d) What is the reorder point? enter your response here units (round your response to the nearest whole number).arrow_forwardEOQ, reorder point, and safety stock Alexis Company uses 937units of a product per year on a continuous basis. The product has a fixed cost of $44 per order, and its carrying cost is $4 per unit per year. It takes 5 days to receive a shipment after an order is placed, and the firm wishes to hold 10 days' usage in inventory as a safety stock. a. Calculate the EOQ. b. Determine the average level of inventory. (Note: Use a 365-day year to calculate daily usage.) c. Determine the reorder point. d. Indicate which of the following variables change if the firm does not hold the safety stock: (1) order cost, (2) carrying cost, (3) total inventory cost, (4) reorder point, (5) economic order quantity.arrow_forwardK Southeastern Bell stocks a certain switch connector at its central warehouse for supplying field service offices. The yearly demand for these connectors is 14,100 units. Southeastern estimates its annual holding cost for this item to be $22 per unit. The cost to place and process an order from the supplier is $73. The company operates 300 days per year, and the lead time to receive an order from the supplier is 3 working days. a) What is the economic order quantity? 306 units (round your response to the nearest whole number). b) What are the annual holding costs? $ 3365 (round your response to the nearest whole number). c) What are the annual ordering costs? $ (round your response to the nearest whole number).arrow_forward
- Alina Limited is a manufacturer of widgets orders components for use in manufacturing. The estimated demand for the components during the coming year is 15,000. Order costs are $100 per order; carrying costs are $12 per component. Using the economic order quantity model What is Alina Ltd’s optimum order quantity? If the supplier guarantees a three (3) day delivery on any order that is placed, What is the re-order point?arrow_forwardSoutheastern Bell stocks a certain switch connector at its central warehouse for supplying field service offices. The yearly demand for these connectors is 14,800 units. Southeastern estimates its annual holding cost for this item to be $26 per unit. The cost to place and process an order from the supplier is $74. The company operates 300 days per year, and the lead time to receive an order from the supplier is 3 working days. a) What is the economic order quantity? [ units (round your response to the nearest whole number). b) What are the annual holding costs? $☐ (round your response to the nearest whole number). c) What are the annual ordering costs? $☐ (round your response to the nearest whole number). d) What is the reorder point? ☐ units (round your response to the nearest whole number).arrow_forwardEOQ, reorder point, and safety stock Alexis Company uses 916 units of a product per year on a continuous basis. The product has a fixed cost of $60 per order, and its carrying cost is $3 per unit per year. It takes 5 days to receive a shipment after an order is placed, and the firm wishes to hold 10 days' usage in inventory as a safety stock. a. Calculate the EOQ. b. Determine the average level of inventory. (Note: Use a 365-day year to calculate daily usage.) c. Determine the reorder point. d. Indicate which of the following variables change if the firm does not hold the safety stock: (1) order cost, (2) carrying cost, (3) total inventory cost, (4) reorder point, (5) economic order quantity. a. Alexis' EOQ is units. (Round to the nearest whole number.)arrow_forward
- K Southeastern Bell stocks a certain switch connector at its central warehouse for supplying field service offices. The yearly demand for these connectors is 14,100 units. Southeastern estimates its annual holding cost for this item to be $22 per unit. The cost to place and process an order from the supplier is $73. The company operates 300 days per year, and the lead time to receive an order from the supplier is 3 working days. a) What is the economic order quantity? units (round your response to the nearest whole number). ncorrearrow_forwardThe Universal Computer Company uses a newly developed A1 chip in the manufacturer of their tablet computers. The estimated annual demand for this chip is 12,000 units. It is estimated that the cost to place an order is $75, and the holding cost for each chip is $20 per year. The company operates 320 days per year. a. What is the economic order quantity for the A1 chip? b. What is the total cost if the Universal Computer Company orders using the EOQ quantity?arrow_forwardThe annual demand for the Super Thrive brand plant food manufactured by Cumberbatch and Dunst Indoor Plants Company is 120,000 pounds. The annual holding cost (also known as carrying charge) is $0.05 per pound, and Operations Manager Kirsten Benedict has calculated the cost of setting up machinery for making the plant food to be $20. What is the economic order quantity (EOQ) based on the information provided? (Round the EOQ to the next whole number).arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY