Managerial Accounting: The Cornerstone of Business Decision-Making
7th Edition
ISBN: 9781337115773
Author: Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher: Cengage Learning
expand_more
expand_more
format_list_bulleted
Textbook Question
Chapter 11, Problem 38E
(Appendix 11A) Manufacturing Cycle Efficiency
Ventris Company found that one of its manufacturing cells had actual cycle time of 15 minutes per unit. The theoretical cycle time for this cell was 9 minutes per unit.
Required:
- 1. Calculate the amount of processing time per unit and the amount of nonprocessing time per unit.
- 2. Calculate the MCE.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
During the most recent month at Schwab Corporation, queue time was 10.6 days, inspection time was 1.7 day, process time was 2.7
days, wait time was 12.5 days, and move time was 3.5 day.
Required:
a. Compute the throughput time.
b. Compute the manufacturing cycle efficiency (MCE).
c. What percentage of the production time is spent in non-value-added activities?
d. Compute the delivery cycle time.
a. Throughput time
b. MCE
c. Percentage of non-value-added activities
d. Delivery cycle time
days
%
%
days
Patagania Company reports that its average delivery cycle time is 20.0 days; its average throughput time is 7.5 days; its manufacturing cycle efficiency is 0.32; its average move time is 0.2 day; and its average queue time is 4.0 days: a. What is the wait time? b. What is the process time? c. What is the inspection time?
Answer with complete set solution pls
Prakesh Company has the following data for one of its manufacturing cells:
Maximum units produced in a month: 62,500 units
Actual units produced in a month: 56,250 units
Hours of production labor in one month: 10,000 hours
Required:
1. Compute the theoretical cycle time. Round your answer to the nearest whole minute.fill in the blank 1 minutes per unit
2. Compute the actual cycle time. Round your answer to the nearest whole minute.fill in the blank 2 minutes per unit
3. Compute the theoretical velocity. Round your answer to the nearest whole unit.fill in the blank 3 units per hour
4. Compute the actual velocity. Round your answer to the nearest whole unit.fill in the blank 4 units per hour
Chapter 11 Solutions
Managerial Accounting: The Cornerstone of Business Decision-Making
Ch. 11 - Discuss the differences between centralized and...Ch. 11 - Prob. 2DQCh. 11 - Explain why firms choose to decentralize.Ch. 11 - What are margin and turnover? Explain how these...Ch. 11 - What are the three benefits of ROI? Explain how...Ch. 11 - What is residual income? What is EVA? How does EVA...Ch. 11 - Can residual income or EVA ever be negative? What...Ch. 11 - What is transfer price?Ch. 11 - Prob. 9DQCh. 11 - (Appendix 11A) What is the Balanced Scorecard?
Ch. 11 - (Appendix 11A) Describe the four perspectives of...Ch. 11 - The practice of delegating authority to...Ch. 11 - Which of the following is not a reason for...Ch. 11 - A responsibility center in which a manager is...Ch. 11 - A responsibility center in which a manager is...Ch. 11 - If sales and average operating assets for Year 2...Ch. 11 - If sales and average operating assets for Year 2...Ch. 11 - The key difference between residual income and EVA...Ch. 11 - It ROI for a division is 15% and the company's...Ch. 11 - Prob. 9MCQCh. 11 - Prob. 10MCQCh. 11 - (Appendix 11A) Which of the following is a...Ch. 11 - (Appendix 11A) The length of time it takes to...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Prob. 16BEACh. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Prob. 21BEBCh. 11 - Calculating Transfer Price Teslum Inc. has a...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Types of Responsibility Centers Consider each of...Ch. 11 - Margin, Turnover, Return on Investment Pelak...Ch. 11 - Margin, Turnover, Return on Investment, Average...Ch. 11 - Return on Investment, Margin, Turnover Data follow...Ch. 11 - Residual Income The Avila Division of Maldonado...Ch. 11 - Economic Value Added Falconer Company had net...Ch. 11 - Use the following information for Exercises 11-31...Ch. 11 - Use the following information for Exercises 11-31...Ch. 11 - Prob. 33ECh. 11 - Use the following information for Exercises 11-33...Ch. 11 - Prob. 35ECh. 11 - (Appendix 11A) Cycle Time and Velocity Prakesh...Ch. 11 - (Appendix 11A) Cycle Time and Velocity Lasker...Ch. 11 - (Appendix 11A) Manufacturing Cycle Efficiency...Ch. 11 - (Appendix 11A) Manufacturing Cycle Efficiency...Ch. 11 - Return on Investment and Investment Decisions...Ch. 11 - Return on Investment, Margin, Turnover Ready...Ch. 11 - Return on Investment for Multiple Investments,...Ch. 11 - Return on Investment and Economic Value Added...Ch. 11 - Transfer Pricing GreenWorld Inc. is a nursery...Ch. 11 - Prob. 45PCh. 11 - Prob. 46PCh. 11 - (Appendix 11A) Cycle Time, Velocity, Conversion...Ch. 11 - (Appendix 11A) Balanced Scorecard The following...Ch. 11 - (Appendix 11A) Cycle Time and Velocity,...Ch. 11 - Prob. 50C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Compute (a) cycle time, (b) value-added time, (c) non-value-added time, and (d) cycle efficiency using the following information for a manufacturer. Process time. 2.10 days Move time. 0.75 days Inspection time. 0.50 days Wait time. 0.15 daysarrow_forwardDelko Company has the following data for one of its manufacturing plants: Maximum units produced in a quarter (3-month period): 250,000 units Actual units produced in a quarter (3-month period): 210,000 units Productive hours in one quarter: 25,000 hours The actual cycle time for Indy Company is 7.14 minutes, and the theoretical cycle time is 6 minutes. Required: 1. Calculate the amount of processing time and the amount of nonprocessing time. If required, round your answers to two decimal places. Processing time minutes Nonprocessing time minutes 2. Calculate the MCE. If required, round your answer to nearest whole number.arrow_forwardProduct A has a contribution margin per unit of $500 and required 2 hours of machine times. Product B has a contribution margin per unit of $1,000 and requires 5 hours of machine time. How much of each product should be produced given there are 100 hours of variable machine time?arrow_forward
- Hernandez Corp. wants to compute its throughput for August. The following production data are available: Good units produced and sold 2,923,200 Total units produced 4,844,000 Total processing (in hours) 201,600 Value-added time (in hours) 50,300 a. Determine the manufacturing cycle efficiency. ______% b. Determine the process productivity. ______ units per hour c. Determine the process quality yield. ______% d. Determine the throughput using only good units and total time. ______ units per hourarrow_forwardCraig, Inc., has provided the following information for one of its products for each hour of production: Actual velocity: 100 units (per hour) Move time: 20 minutes Inspection time: 18 minutes Rework time: 12 minutes Required: Calculate MCE. Comment on its significance.arrow_forwardThe assembly-line activities are given as follows for the manufacturing of a product: Performance Time (mins) Performance Time (mins) 6 4 5 3 Task A B с D Predecessors A B B Task E F G H 524 2 Predecessors C с D, E, F G For a given 7-minute cycle time after allowances, the theoretical minimum number of workstations = (round your response to the immediate higher whole number).arrow_forward
- A process costs $200 to set up. The run time is 5 minutes per piece and the run costis $30 per hour. Determine the following:a. The fixed cost.b. The variable cost.c. The total cost and unit cost for a lot of 600.d. The total cost and unit cost for a lot of 1200.arrow_forwardThe number of set ups is the cost driver for production scheduling and machine set ups. The number of set ups for three products are as follows: Number of set-ups is X=240, Y=260 and Z=300. If the cost of production scheduling is GH¢1.2 million and the cost of ordering is GH¢1.8 million, how much of the production scheduling should be charged to Y?A. GH¢390,000B. GH¢360,000C. GH¢702,000D. GH¢500,000arrow_forwardABC INC product is currently produced at 10 materials, 40 labor and 15 overhead. If automation is implemented, the product can be produced at 10 materials, 5 labor and 35 overhead. At a total of 10,000 units, what is the net incremental cost or benefit if the production decides to move into automation?arrow_forward
- Norton Company has the following data for one of its production departments: Theoretical velocity: 420 units per hour Productive minutes available per year: 77,000,000 Annual conversion costs: $616,000,000 Actual velocity: 210 units per hour Required: 1. Calculate the actual conversion cost per unit using actual cycle time and the standard cost per minute. Round your actual cycle time answer to three decimal places and your cost per unit answer to the nearest cent. Actual cycle time fill in the blank minutes per unit Standard cost per minute $fill in the blank per minute Conversion cost per unit $fill in the blank per unitarrow_forwardThe following computer printout was generated, using regression, for use in estimating maintenance costs. Intercept 8300 X Variable 1 37 Multiple R 0.9500 R Square 0.9025 Activity variable machine hours An estimate of maintenance costs at an activity level of 100 machine hours would be:arrow_forwardNorton Company has the following data for one of its production departments: Theoretical velocity: 300 units per hour Productive minutes available per year: 10,000,000 Annual conversion costs: $60,000,000 Actual velocity: 160 units per hour Based on the above information, the theoretical cycle time will be Select one: a. 4 minutes per unit b. .2 minutes per unit c. Right answer is not listed d. .3 minutes per unitarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Managerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Inspection and Quality control in Manufacturing. What is quality inspection?; Author: Educationleaves;https://www.youtube.com/watch?v=Ey4MqC7Kp7g;License: Standard youtube license