Managerial Accounting: The Cornerstone of Business Decision-Making
7th Edition
ISBN: 9781337115773
Author: Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher: Cengage Learning
expand_more
expand_more
format_list_bulleted
Textbook Question
Chapter 11, Problem 38E
(Appendix 11A) Manufacturing Cycle Efficiency
Ventris Company found that one of its manufacturing cells had actual cycle time of 15 minutes per unit. The theoretical cycle time for this cell was 9 minutes per unit.
Required:
- 1. Calculate the amount of processing time per unit and the amount of nonprocessing time per unit.
- 2. Calculate the MCE.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
Schurz Corporation's management reports that its average delivery cycle time is 29 days, its average throughput time is 13.0 days, its
manufacturing cycle efficiency (MCE) is 0.20, its average move time is 0.6 day, and its average queue time is 3.0 days.
Required:
a. What is the wait time? (Round your answer to 1 decimal place.)
b. What is the process time? (Round your answer to 1 decimal place.)
c. What is the inspection time? (Round your intermediate calculations and final answer to 1 decimal place.)
a
b
C
Wait time
Process time
Inspection time
days
days
days
SanaMolp management reports that its average delivery cycle time is 20.0 days; its average throughput time is 7.5 days; its manufacturing cycle efficiency is 0.32; its average move time is 0.2 day; and its average queue time is 4.0 days: a. What is the wait time? b. What is the process time? c. What is the inspection time?
Answer with solution pls
(Chapter 4: Process Improvement) Consider a process consisting of three resources. Assume the
demand rate is 8 units/hour.
The process activities are always performed in the following sequence.
Resource 1 has a processing time of 5 minutes per unit.
Resource 2 has a processing time of 4 minutes per unit.
Resource 3 has a processing time of 6 minutes per unit.
Resource 1 is staffed by worker A and A's wage rate is $13 per hour.
Resource 2 is staffed by worker B and B's wage rate is $13 per hour.
Resource 3 is staffed by worker C and C's wage rate is $20 per hour.
If one additional worker could be hired, to which resource should this worker be assigned?
Calculate the new process capacity in units/hr.
O Assign the new worker to Resource 3. The process capacity is 12 units per hour.
O Assign the new worker to Resource 3. The process capacity is 10 units per hour.
O Assign the new worker to Resource 1. The process capacity is 20 units per hour.
O Assign the new worker to Resource 2. The…
Chapter 11 Solutions
Managerial Accounting: The Cornerstone of Business Decision-Making
Ch. 11 - Discuss the differences between centralized and...Ch. 11 - Prob. 2DQCh. 11 - Explain why firms choose to decentralize.Ch. 11 - What are margin and turnover? Explain how these...Ch. 11 - What are the three benefits of ROI? Explain how...Ch. 11 - What is residual income? What is EVA? How does EVA...Ch. 11 - Can residual income or EVA ever be negative? What...Ch. 11 - What is transfer price?Ch. 11 - Prob. 9DQCh. 11 - (Appendix 11A) What is the Balanced Scorecard?
Ch. 11 - (Appendix 11A) Describe the four perspectives of...Ch. 11 - The practice of delegating authority to...Ch. 11 - Which of the following is not a reason for...Ch. 11 - A responsibility center in which a manager is...Ch. 11 - A responsibility center in which a manager is...Ch. 11 - If sales and average operating assets for Year 2...Ch. 11 - If sales and average operating assets for Year 2...Ch. 11 - The key difference between residual income and EVA...Ch. 11 - It ROI for a division is 15% and the company's...Ch. 11 - Prob. 9MCQCh. 11 - Prob. 10MCQCh. 11 - (Appendix 11A) Which of the following is a...Ch. 11 - (Appendix 11A) The length of time it takes to...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Prob. 16BEACh. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Prob. 21BEBCh. 11 - Calculating Transfer Price Teslum Inc. has a...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Types of Responsibility Centers Consider each of...Ch. 11 - Margin, Turnover, Return on Investment Pelak...Ch. 11 - Margin, Turnover, Return on Investment, Average...Ch. 11 - Return on Investment, Margin, Turnover Data follow...Ch. 11 - Residual Income The Avila Division of Maldonado...Ch. 11 - Economic Value Added Falconer Company had net...Ch. 11 - Use the following information for Exercises 11-31...Ch. 11 - Use the following information for Exercises 11-31...Ch. 11 - Prob. 33ECh. 11 - Use the following information for Exercises 11-33...Ch. 11 - Prob. 35ECh. 11 - (Appendix 11A) Cycle Time and Velocity Prakesh...Ch. 11 - (Appendix 11A) Cycle Time and Velocity Lasker...Ch. 11 - (Appendix 11A) Manufacturing Cycle Efficiency...Ch. 11 - (Appendix 11A) Manufacturing Cycle Efficiency...Ch. 11 - Return on Investment and Investment Decisions...Ch. 11 - Return on Investment, Margin, Turnover Ready...Ch. 11 - Return on Investment for Multiple Investments,...Ch. 11 - Return on Investment and Economic Value Added...Ch. 11 - Transfer Pricing GreenWorld Inc. is a nursery...Ch. 11 - Prob. 45PCh. 11 - Prob. 46PCh. 11 - (Appendix 11A) Cycle Time, Velocity, Conversion...Ch. 11 - (Appendix 11A) Balanced Scorecard The following...Ch. 11 - (Appendix 11A) Cycle Time and Velocity,...Ch. 11 - Prob. 50C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Compute (a) cycle time, (b) value-added time, (c) non-value-added time, and (d) cycle efficiency using the following information for a manufacturer. Process time. 2.10 days Move time. 0.75 days Inspection time. 0.50 days Wait time. 0.15 daysarrow_forward1. Compute the throughput time. (Round your answer to 1 decimal place.) 2. Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your perce 3. What percentage of the throughput time was spent in non-value-added activities? (R whole percent.) 4. Compute the delivery cycle time. (Round your intermediate calculations and final ar 5. If by using Lean Production all queue time during production is eliminated, what will b answer to 1 decimal place.)arrow_forwardProduct A has a contribution margin per unit of $500 and required 2 hours of machine times. Product B has a contribution margin per unit of $1,000 and requires 5 hours of machine time. How much of each product should be produced given there are 100 hours of variable machine time?arrow_forward
- Hernandez Corp. wants to compute its throughput for August. The following production data are available: Good units produced and sold 2,923,200 Total units produced 4,844,000 Total processing (in hours) 201,600 Value-added time (in hours) 50,300 a. Determine the manufacturing cycle efficiency. ______% b. Determine the process productivity. ______ units per hour c. Determine the process quality yield. ______% d. Determine the throughput using only good units and total time. ______ units per hourarrow_forwardPlease explain each anwer with formula. Regarding the following information, how many machines would be needed to handle the required volume? Processing time per unit (minute) product demand A B C 1 16000 3 4 2 2 12000 4 4 3 3 6000 5 6 4 4 30000 2 2 1 In order to meet annual demand for all products, how many machines in each type are needed? Based on fixed annual cost (Alternative A with $40,000, B with $30,000 and C with $80,000), which type of machine and how many will cost least to satisfy the demand? Consider the operation of machines 10 hours per day and 200 days a year.arrow_forwardThe assembly-line activities are given as follows for the manufacturing of a product: Performance Time (mins) Performance Time (mins) 6 4 5 3 Task A B с D Predecessors A B B Task E F G H 524 2 Predecessors C с D, E, F G For a given 7-minute cycle time after allowances, the theoretical minimum number of workstations = (round your response to the immediate higher whole number).arrow_forward
- A manager must decide between two machines. The manager will take into account each machine's operating costs and initial costs, and its breakdown and repair times. Machine A has a projected average operating time of 131 hours and a projected average repair time of 4 hours. Projected times for machine B are an average operating time of 61 hours and a repair time of 5 hours. What are the projected availabilities of each machine? (Round your answers to 3 decimal places.) Answer is complete but not entirely correct. Availability 0.952 0.945 Machine A Machine Barrow_forwardBest Ink produces printers for personal computers. The following information is available for production of a recent order of 500 printers. Process time 16.0 hours Inspection time 3.5 hours Move time 9.0 hours Wait time 21.5 hours 1. Compute the company’s manufacturing cycle time. 2. Compute the company’s manufacturing cycle efficiency. 3. Assume the company wishes to increase its manufacturing cycle efficiency to 0.80. If process time is unchanged, what is the maximum number of hours of non-value-added time the company can have and meet this goal?arrow_forward4. What if the units actually produced were 10,000 for Printer A and 18,000 for Printer B. Using DBC, calculate the cost of unused capacity. can you give me the formulaarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Managerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Inspection and Quality control in Manufacturing. What is quality inspection?; Author: Educationleaves;https://www.youtube.com/watch?v=Ey4MqC7Kp7g;License: Standard youtube license