Textbook Question
Chapter 11, Problem 49P
(Appendix 11A) Cycle Time and Velocity, Manufacturing Cycle Efficiency
A company like Kicker performs warranty repair work on speakers in a manufacturing cell. The typical warranty repair involves taking the defective speaker apart, testing the components, and replacing the defective components. The maximum capacity of the cell is 1,000 repairs per month. There are 500 production hours available per month.
Required:
- 1. Compute the theoretical velocity (per hour) and the theoretical cycle time (minutes per unit repaired).
- 2. Speaker repair uses 4 minutes of move time, 10 minutes of wait time, and 6 minutes of inspection time. Calculate the MCE.
- 3. Using the information from Requirement 2, calculate the actual cycle time and the actual velocity for speaker repair.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
Nash Corporation manufactures and sells custom snowmobiles. From the time an order is placed till
the time the snowmobile reaches the customer averages 50 days. This 50 days is spent as follows:
Wait time: 10 days
Move time: 5 days
Process time: 15 days
Queue time: 15 days
Inspection time: 5 days
What is Nash's manufacturing cycle efficiency (MCE) for its snowmobiles?
A. Find the reorder point (Complete steps of computation please)
B. What would be the ordering policy for this item?
Waiting times, manufacturing cycle times. The Sandstone Corporation uses an injection molding machine to make a plastic product, Z35, after receiving rm orders from its customers. Sandstone estimates that it will receive 60 orders for Z35 during the coming year. Each order of Z35 will take 100 hours of machine time. The annual machine capacity is 8,000 hours.
Chapter 11 Solutions
Managerial Accounting: The Cornerstone of Business Decision-Making
Ch. 11 - Discuss the differences between centralized and...Ch. 11 - Prob. 2DQCh. 11 - Explain why firms choose to decentralize.Ch. 11 - What are margin and turnover? Explain how these...Ch. 11 - What are the three benefits of ROI? Explain how...Ch. 11 - What is residual income? What is EVA? How does EVA...Ch. 11 - Can residual income or EVA ever be negative? What...Ch. 11 - What is transfer price?Ch. 11 - Prob. 9DQCh. 11 - (Appendix 11A) What is the Balanced Scorecard?
Ch. 11 - (Appendix 11A) Describe the four perspectives of...Ch. 11 - The practice of delegating authority to...Ch. 11 - Which of the following is not a reason for...Ch. 11 - A responsibility center in which a manager is...Ch. 11 - A responsibility center in which a manager is...Ch. 11 - If sales and average operating assets for Year 2...Ch. 11 - If sales and average operating assets for Year 2...Ch. 11 - The key difference between residual income and EVA...Ch. 11 - It ROI for a division is 15% and the company's...Ch. 11 - Prob. 9MCQCh. 11 - Prob. 10MCQCh. 11 - (Appendix 11A) Which of the following is a...Ch. 11 - (Appendix 11A) The length of time it takes to...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Prob. 16BEACh. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Prob. 21BEBCh. 11 - Calculating Transfer Price Teslum Inc. has a...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Use the following information for Brief Exercises...Ch. 11 - Types of Responsibility Centers Consider each of...Ch. 11 - Margin, Turnover, Return on Investment Pelak...Ch. 11 - Margin, Turnover, Return on Investment, Average...Ch. 11 - Return on Investment, Margin, Turnover Data follow...Ch. 11 - Residual Income The Avila Division of Maldonado...Ch. 11 - Economic Value Added Falconer Company had net...Ch. 11 - Use the following information for Exercises 11-31...Ch. 11 - Use the following information for Exercises 11-31...Ch. 11 - Prob. 33ECh. 11 - Use the following information for Exercises 11-33...Ch. 11 - Prob. 35ECh. 11 - (Appendix 11A) Cycle Time and Velocity Prakesh...Ch. 11 - (Appendix 11A) Cycle Time and Velocity Lasker...Ch. 11 - (Appendix 11A) Manufacturing Cycle Efficiency...Ch. 11 - (Appendix 11A) Manufacturing Cycle Efficiency...Ch. 11 - Return on Investment and Investment Decisions...Ch. 11 - Return on Investment, Margin, Turnover Ready...Ch. 11 - Return on Investment for Multiple Investments,...Ch. 11 - Return on Investment and Economic Value Added...Ch. 11 - Transfer Pricing GreenWorld Inc. is a nursery...Ch. 11 - Prob. 45PCh. 11 - Prob. 46PCh. 11 - (Appendix 11A) Cycle Time, Velocity, Conversion...Ch. 11 - (Appendix 11A) Balanced Scorecard The following...Ch. 11 - (Appendix 11A) Cycle Time and Velocity,...Ch. 11 - Prob. 50C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Answer all subparts a to f.if answered within 30mins,it would be helpful Accounting ETS manufactures a component for its computer products. The annual demand for thiscomponent is 2500 units. The annual cost of maintaining inventory is10% per unit and the cost of preparing an order and setting up productionfor the order is $ 50.The machine used to make this part has a production rate of 10,000units per year and the cost is $ 22 per unit.a. Find the EPQ(Economic Production Quantity)A. How long does it take to produce the batch?B. How many batches will be produced per year?C. What is the maximum inventory level?D. What is the total cost per year?E. A supplier offers to sell a similar component for $ 25 per unit with a charge$ 5 per service per order. Should the company accept the offer?F. Find the average inventory level for each situationarrow_forwardMCE Craig, Inc., has provided the following information for one of its products for each hour of production: Actual velocity: 200 units (per hour) Move time: 11 minutes Inspection time: 12 minutes Rework time: 12 minutes 1. MCE is 0.42 2. What is the theoretical cycle time? Calculate MCE using actual and theoretical cycle times. If required, round your answers to two decimal places. Theoretical cycle time fill in the blank minutes Actual cycle time 0.3 minutes MCE fill in the blankarrow_forwardA thermoplastic film manufacturer is trying to decide between 5 types of thermoforming molding processes to be added to its molding operation. The estimated costs and revenues are shown below. Compare them on the basis of the IRR method and determine which process should be selected if the company's MARR is 7% per year. Select the best alternative by performing an IRR incremental analysis. Justify your answer.arrow_forward
- A manual assembly line is being designed for a product with annual demand = 100,000 units. The line will operate 50 wks/year, 5 shifts/wk, and 7.5 hr/shift. Work units will be attached to a continuously moving conveyor. Work content time = 42.0 min. Assume line efficiency E = 0.97, balancing efficiency Eb = 0.92, and repositioning time Tr = 6 sec. Determine: (a) hourly production rate to meet demand, (b) number of workers required.arrow_forwardThe Sandstone Corporation uses an injection molding machine to make a plastic product, Z35, after receiving firm orders from its customers. Sandstone estimates that it will receive 60 orders for Z35 during the coming year. Each order of Z35 will take 100 hours of machine time. The annual machine capacity is 8,000 hours. Q. Calculate (a) the average amount of time that an order for Z35 will wait in line before it is processed and (b) the average manufacturing cycle time per order for Z35.arrow_forwardExplain the computation needed. We have been producing product A for several years and look forward to several more years of sales at 500,000 units per year or 2,000 units per day. The present method requires a standard time of 2.0 mins per unit or 30 pcs per hour. At this rate, it takes 33.33 hrs to make 1,000 units. All production will run on the day shift. Present Method and Costs- with a labor rate of $10.00/hr, the labor cost will be $333.30 to produce 1,000 units. The cost of 500,000 units per year would be $166,650.00 in direct labor. New Method and Cost- we have a reduction idea. If we buy this new machine attachment for $1000, the new time standard would be lowered to 1.5 minutes per unit. Will this investment be good for us?arrow_forward
- Navern Coporation manufactures and sells custom home elevators. From the time an order is placed until the time the elevator is installed in the customer's home averages 44 days. This 44 days is spent as follows: Wait time 12 days Inspection time Process time Move time Queue time 12 days 5 days 6 days 9 days What is Navern's manufacturing cycle efficiency (MCE) for its elevators? Multiple Cholce 38.6% 15.6% 61.4% 591% 65°F Cloudy search DELLarrow_forwardBest Ink produces printers for personal computers. The following information is available for production of a recent order of 500 printers. Process time 16.0 hours Inspection time 3.5 hours Move time 9.0 hours Wait time 21.5 hours 1. Compute the company’s manufacturing cycle time. 2. Compute the company’s manufacturing cycle efficiency. 3. Assume the company wishes to increase its manufacturing cycle efficiency to 0.80. If process time is unchanged, what is the maximum number of hours of non-value-added time the company can have and meet this goal?arrow_forwardPLEASE MAKE IT IN EXCEL AND SHOW THE FORMULAS Comercial El Suspiro, S.A., purchases 2'100,000 units per year of a component. The cost of each order is $25.00. The annual unit maintenance cost is 27% of its cost of $2.00. On a 360-day basis, calculate the reorder point, knowing that it takes 10.5 days for the supplier to put in the LAB company the goods, and the company sorts and stores them in 1.5 days, calculate the reorder point.arrow_forward
- please answer in 30 minutes.arrow_forwarda. What is the EOQ for this component?b. What is the reorder point?c. What is the cycle time?d. What are the total annual holding and ordering costs associated with your recommendedEOQ?arrow_forwardNavern Corporation manufactures and sells custom home elevators. From the time an order is placed until the time the elevator is installed in the customer's home averages 82 days. This 82 days is spent as follows: Wait time Inspection time Process time Move time Queue time What is Navern's manufacturing cycle efficiency (MCE) for its elevators? Multiple Choice 41.5% 33.3% 58.5% 16 days 12 days 22 days 21 days 11 days 54.9%arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Managerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage Learning
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
alue Chain Analysis EXPLAINED | B2U | Business To You; Author: Business To You;https://www.youtube.com/watch?v=SI5lYaZaUlg;License: Standard Youtube License