Engineering Economy
Engineering Economy
16th Edition
ISBN: 9780133582819
Author: Sullivan
Publisher: DGTL BNCOM
bartleby

Videos

Textbook Question
Book Icon
Chapter 11, Problem 20P

A bridge is to be constructed now as part of a new road. Engineers have determined that traffic density on the new road will justify a two-lane road and a bridge at the present time. Because of uncertainty regarding future use of the road, the time at which an extra two lanes will be required is currently being studied.

The two-lane bridge will cost $200,000 and the four- lane bridge, if built initially, will cost $350,000. The future cost of widening a two-lane bridge to four lanes will be an extra $200,000 plus $25,000 for every year that widening is delayed. The MARR used by the highway department is 12% per year. The following estimates have been made of the times at which the four-lane bridge will be required:

Chapter 11, Problem 20P, A bridge is to be constructed now as part of a new road. Engineers have determined that traffic

In view of these estimates, what would you recommend? What difficulty, if any, do you have in interpreting your results? List some advantages and disadvantages of this method of preparing estimates.

Blurred answer
Students have asked these similar questions
A bridge is to be constructed now as part of a new road. Engineers have determined that traffic density on the new road will justify a two-lane road and a bridge at the present time. Because of uncertainty regarding future use of the road, the time at which an extra two lanes will be required is currently being studied. The two-lane bridge will cost $220,000 and the four-lane bridge, if built initially, will cost $440,000. The future cost of widening a two-lane bridge to four lanes will be an extra $220,000 plus $23,000 for every year that widening is delayed. The MARR used by the highway department is 12% per year. The following estimates have been made of the times at which the four-lane bridge will be required: Pessimistic estimate Most likely estimate Optimistic estimate In view of these estimates, what would you recommend? List some advantages and disadvantages of this method of preparing estimates. 4 years 6 years 7 years A Click the icon to view the interest and annuity table…
A bridge is to be constructed now as part of a new road. Engineers have determined that traffic density on the new road will justify a two-lane road and a bridge at the present time. Because of uncerta. regarding future use of the road, the time at which an extra two lanes will be required is currently being studied. The two-lane bridge will cost $210,000 and the four-lane bridge, it built initially, will cost $400,000. The future cost of widering a two-lane bridge to four lanes will be an extra $210,000 plus $23,000 for year that widening is delayed The MARR used by the highway department is 15% per year. The following estimates have been made of the times at which the four-lane bridge will be required: 4 years Pessimistic estimate Most likely estimate 5 years 9 years Optimistic estimate In view of these estimates, what would you recommend? List some advantages and disadvantages of this method of preparing estimates Click the icon to view the interest and annuity table for discrete…
*12
Knowledge Booster
Background pattern image
Economics
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:9780190931919
Author:NEWNAN
Publisher:Oxford University Press
Text book image
Principles of Economics (12th Edition)
Economics
ISBN:9780134078779
Author:Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:PEARSON
Text book image
Engineering Economy (17th Edition)
Economics
ISBN:9780134870069
Author:William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:PEARSON
Text book image
Principles of Economics (MindTap Course List)
Economics
ISBN:9781305585126
Author:N. Gregory Mankiw
Publisher:Cengage Learning
Text book image
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Text book image
Managerial Economics & Business Strategy (Mcgraw-...
Economics
ISBN:9781259290619
Author:Michael Baye, Jeff Prince
Publisher:McGraw-Hill Education
Difference between Renewable and Nonrenewable Resources; Author: MooMooMath and Science;https://www.youtube.com/watch?v=PLBK1ux5b7U;License: Standard Youtube License