EBK OPERATIONS MANAGEMENT
14th Edition
ISBN: 9781260718447
Author: Stevenson
Publisher: MCG COURSE
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 11, Problem 19P
Prepare a master production
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A initially assume that Phi wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using a lot-for-lot (L4L).
Gear box requirements
Week 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipt
Planned order release
Input shaft requirements
Week 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipt
Planned order release
Hand written out please step by step
For a given store demand in Week 5 is 375 and onhand inventory at the end of Week 4 is 450 If the manufacturing lead time for this particular item is two weeks then what will be the Store demand
Chapter 11 Solutions
EBK OPERATIONS MANAGEMENT
Ch. 11 - What three levels of planning involve operations...Ch. 11 - What are the three phases of intermediate...Ch. 11 - Prob. 3DRQCh. 11 - Why is there a need for aggregate planning?Ch. 11 - What are the most common decision variables for...Ch. 11 - Prob. 6DRQCh. 11 - Briefly discuss the advantages and disadvantages...Ch. 11 - What are the primary advantages and limitations of...Ch. 11 - Briefly describe the planning techniques listed as...Ch. 11 - What are the inputs to master scheduling? What are...
Ch. 11 - Prob. 11DRQCh. 11 - What general trade-offs are involved in master...Ch. 11 - Who needs to interface with the master schedule...Ch. 11 - How has technology had an impact on master...Ch. 11 - Service operations often face more difficulty in...Ch. 11 - Name several behaviors related to aggregate...Ch. 11 - Compute the total cost for each aggregate plan...Ch. 11 - A manager would like to know the total cost of a...Ch. 11 - Determine the total cost for this plan given the...Ch. 11 - a. Given the following forecast and steady regular...Ch. 11 - Manager T. C. Downs of Plum Engines, a producer of...Ch. 11 - Manager Chris Channing of Fabric Mills, Inc., has...Ch. 11 - SummerFun. Inc., produces a variety of recreation...Ch. 11 - Nowjuice, Inc., produces Shakewell fruit juice. A...Ch. 11 - Wormwood, Ltd., produces a variety of furniture...Ch. 11 - Refer to Solved Problem 1. Prepare two additional...Ch. 11 - Refer to Solved Problem 1. Suppose another option...Ch. 11 - Prob. 12PCh. 11 - Prob. 13PCh. 11 - Prob. 14PCh. 11 - Prob. 15PCh. 11 - Refer to Example 3. Suppose that regular-time...Ch. 11 - Prob. 17PCh. 11 - Prob. 18PCh. 11 - Prepare a master production schedule for...Ch. 11 - Update the master schedule shown in Figure 11.11...Ch. 11 - Prepare a master schedule like that shown in...Ch. 11 - Determine the available-to-promise (ATP)...Ch. 11 - Prepare a schedule like that shown in Figure 11.12...Ch. 11 - The objective is to choose the plan that has the...Ch. 11 - Prob. 2CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Semans is a manufacturer that produces bracket assemblies. Demand for bracket assemblies (X) is 131 units. The following is in indented form: ITEM DESCRIPTION Bracket assembly Wall board USAGE 1 A 4 Hanger subassembly Hanger casting Ceramic knob Rivet head screw Metal tong Plastic cap E G 2 Below is a table indicating current inventory levels: Item Inventory A B E G 23 18 55 25 200 170 1,100 90 b. What are the net requirements of each item in the MPS? (Leave no cells blank be certain to enter "0" wherever requirec Item Net Requirements A F Nevtarrow_forward. Worldwide Can-Openers, Inc., makes a family of two hand-operated can openers. The production plan is based on months. There are 4 weeks in this month. Opening inventory is 2000 dozen, and it is planned to increase that to 4000 dozen by the end of the month. The MPS is made using weekly periods. The forecast and projected available balance for the two models follow. The lot size for both models is 1000 dozen. Calculate the production plan and the MPS for each item.arrow_forwardThe Alpha Beta Company produces two products; A and B, that are made from components C and D. Given the follow-ing product structures, master scheduling requirements, and inventory information, determine when orders shouldbe released for A, B, C, and D and the size of those orders.arrow_forward
- ITEMS 18 to 20 ARE BASED ON THE FOLLOWING INFORMATION: The following information pertains to Emy Manufacturing Corporation's Product X: Annual demand 33,750 units Annual cost to hold one unit of inventory P15 Setup cost (or the cost to initiate a production run) P500 Beginning inventory of product X 0 At present, the Company produces 2,250 units of Product X per production runt for a total of 15 production runs per year. The company is considering to use the EOQ model to determine the economic lot size and the number of production runs that will minimize the total inventory carrying cost and setup cost for Product X. At present, the company's total annual inventory costs is P 7,500. c. P24,375. P16,875. d. P22,500.arrow_forwardA’s lead time is 1 week; B’s lead time is 2 weeks; and C’s lead time is 2 weeks. This is true regardless of order size. Currently you have the following amounts in on-hand inventory; A = 50. a) How many units of B and C will I need to produce for A if I have an order for 100 units of A? b) Give me a time-phased assembly plan for A, B, and C such that I will receive 100 units of A at the beginning of Week 5. Assume that I can work on B and C at the same time (overlap).arrow_forwardEconomic order quantity (Q*) is 6,000 units. Annual demand (D) is 12,000 units. Find number of orders per year (N*) and time between orders (T*) in weeks. N*=2 times per year, T*= 0.5 years N*=0.33 times per year, T*= 13 years N*=4 times per year, T*= 0.33 years N*=0.25 times per year, T*= 4 years N*=2 times per year, T*= 26 weeks OO Oarrow_forward
- Historical demands observed for the last 5 months are 1000, 2300, 3200, 1750, and 1200. To match the demand, the company placed respective orders of 1100, 2500, 4000, 1000, and 900 units. (a) Compute the variance of demand. (b) Compute the variance of orders. (c) Compute the bullwhip measure. Is there an amplifying or smoothing effect?arrow_forwardThe annual demand of ABC Inc. sole product totaled 450,000 units. Due to uncertainty in supply of items, the maximum possible lead time for the orders is 2 weeks and 1 day. A safety stock of 6,250 units is determined. What is the normal lead time? (Use 360 days) Choices: 1 week and 5 days 1 week 9 days 10 daysarrow_forwardi was reading this answer and the way its calculated is a longer process then what someone else wrote can you check if ishould use this one that bartleby has given me or the other one: Step 1: Basic Information The question is related to Economic order quantiy Economic Order Quantity is that level of inventory at which ordering cost and handling cost are minimum. It is calculated with the help of following formula Economic Order Quantity = √2RO ÷ C R = Annual Requirment C = Carrying or Holding cost O = Ordering Cost Step 2: Solution Economic Order Quantity = √2RO ÷ C Economic Order Quantity = √2 × 3000 × 20 ÷ 4.25 Economic Order Quantity = √28,235.294117647 Economic Order Quantity = 168.0336100834 pounds R = Annual Requirment i.e.250 × 12 = 3000 pounds per annum. C = Carrying or Holding cost i.e. £4.25 O = Ordering Cost i.e. £20 Quantity to be ordered = 168.03 pounds. Supplier = Vendor 1 should be used as the cost per pound for 168 pounds is £32.25 (as per table…arrow_forward
- Caltex uses overtime, inventory, and subcontracting to ab-sorb fluctuations in demand. An annual production plan isdevised and updated quarterly. Expected demand, availablecapacities, and costs for the next four quarters are givenbelow. Design a production plan that will satisfy demand atminimum cost.Regular production cost per unit $10Overtime production cost per unit $15Subcontracting cost per unit $20Inventory holding cost per unit per period $ 2 Regular Overtime SubcontractingPeriod Demand Capacity Capacity Capacity1 1500 1000 200 5002 1900 1000 200 5003 500 1000 200 5004 2000 1000 200 500arrow_forwardPlease donot provide solution in image format and fast solution and step by steparrow_forwardAjax Manufacturing produces a single product, which takes 8.0 pounds of direct materials per unitproduced. Assume that it is currently at the end of the first quarter of the year, and there are 50,000pounds of material on hand. The company’s policy is to maintain an end-of-quarter inventoryof materials equal to 25 percent of the following quarter’s material requirements for production.How many units of product were produced in the first quarter of the year? Under the assumptionthat production will increase by 10 percent in the second quarter, what are the direct materialsrequirements (in pounds) for planned production in the second quarter?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY