Concept explainers
(a)
Calculate the average stress increase in the clay layer due to the applied load.
(a)
Answer to Problem 11.21P
The average stress increase in the clay layer
Explanation of Solution
Given information:
The foundation load
The length of the foundation
The breadth of the foundation
The depth of foundation
The height of the clay layer 1
The height of the clay layer 2
The dry unit weight of sand
The saturated unit weight
The liquid limit
Calculation:
Consider the unit weight of water
Calculate the distributed load
Substitute
Calculate the increase in vertical stress
Here,
For the depth
Calculate the width
Substitute
Calculate the ratio
Substitute
Calculate the ratio
Substitute
Similarly calculate the remaining values and tabulate as in Table 1.
Refer Table 10.11 “Variation of
Take the value of
Similarly calculate the remaining values and tabulate as in Table 1.
Calculate the increase in vertical stress
Substitute
Similarly calculate the increase in vertical stress values and tabulate as in Table 1.
Show the increase in vertical stress for each depth below the center of the loaded area as in Table 1.
Depth, | |||||
1 | 1.25 | 1.75 | 1.4 | 0.522 | 39.92 |
1 | 1.25 | 3.5 | 2.8 | 0.210 | 16.06 |
1 | 1.25 | 5.25 | 4.2 | 0.10 | 7.65 |
Table 1
Refer to table 1.
Calculate the stress increase in the clay layer
Here,
Substitute
Hence, the average stress increase in the clay layer
(b)
Calculate the primary consolidation settlement.
(b)
Answer to Problem 11.21P
The primary consolidation settlement
Explanation of Solution
Given information:
The foundation load
The length of the foundation
The breadth of the foundation
The depth of foundation
The height of the clay layer 1
The height of the clay layer 2
The dry unit weight of sand
The saturated unit weight of sand
The liquid limit
The moisture content
The specific gravity of soil solids
The preconsolidation pressure
The swell index
Calculation:
Consider the unit weight of water
The stress at the middle of the clay layer
Calculate the compression index
Substitute
Calculate the swell index
Substitute
Calculate the saturated unit weight of clay layer
Substitute
Calculate the void ratio
Substitute
Calculate the average effective stress at the middle of the clay layer
Substitute
The effective stress
Check for the condition
Substitute
Calculate the primary consolidation settlement
Substitute
Therefore, the primary consolidation settlement
(c)
Calculate the degree of consolidation after 2 years.
(c)
Answer to Problem 11.21P
The degree of consolidation after 2 years
Explanation of Solution
Given information:
The settlement after 2 years
The foundation load
The length of the foundation
The breadth of the foundation
The depth of foundation
The height of the clay layer 1
The height of the clay layer 2
Calculation:
Refer to part (b).
The primary consolidation settlement
Calculate the degree of consolidation after 2 years
Substitute
Hence, the degree of consolidation
(d)
Calculate the coefficient of consolidation for the pressure range.
(d)
Answer to Problem 11.21P
The coefficient of consolidation of the clay
Explanation of Solution
Given information:
The settlement after 2 years
The foundation load
The length of the foundation
The breadth of the foundation
The depth of foundation
The height of the clay layer 1
The height of the clay layer 2
Calculation:
Refer to part (c).
The degree of consolidation
Calculate the time factor
Refer Table 11.7 “Variation of
Take the value of
Calculate the length of maximum drainage path
Substitute
Calculate the coefficient of consolidation
Substitute
Hence, the coefficient of consolidation of the clay
(e)
Calculate the settlement in 3 years.
(e)
Answer to Problem 11.21P
The time settlement in 3 years
Explanation of Solution
Given information:
The foundation load
The length of the foundation
The breadth of the foundation
The depth of foundation
The height of the clay layer 1
The height of the clay layer 2
The time
Calculation:
Refer to part (b).
The primary consolidation settlement
Refer to part (d).
The coefficient of consolidation of the clay
Calculate the time factor
Substitute
Calculate the degree of consolidation
Refer Table 11.7 “Variation of
Take the value of
Calculate the settlement in 3 years
Substitute
Therefore, the time settlement in 3 years
Want to see more full solutions like this?
Chapter 11 Solutions
Principles of Geotechnical Engineering (MindTap Course List)
- Refer to Figure 11.41. Given that B =1 m, L = 3 m, and Q = 110 kN, the soil characteristics given in the figure are Cs = 1/5 Cc, Ꝺ’c= 40 kN/m2. Field monitoring indicated that the foundation settlement was 19 mm during the first 12 months. Estimate the average stress increase in the clay layer due to the applied load. Estimate the primary consolidation settlement. What is the degree of consolidation after 12 months? Estimate the coefficient of consolidation for the pressure range. Estimate the settlement in 24 months.arrow_forwardKINDLY OBTAIN THE RIGHT ANSWER AND EXPLAIN Refer to Figure. Given that B =1 m, L = 3 m, and Q = 110 kN, the soil characteristics given in the figure are Cs = 1/5 Cc, Ꝺ’c= 40 kN/m2. Field monitoring indicated that the foundation settlement was 19 mm during the first 12 months. Estimate the average stress increase in the clay layer due to the applied load. Estimate the primary consolidation settlement. What is the degree of consolidation after 12 months? Estimate the coefficient of consolidation for the pressure range. Estimate the settlement in 24 months.arrow_forwardA foundation with dimensions BxL supporting a column load, P. The foundation rests on a sandy soil underlain by a clay layer (consolidation test result in Problem 2). • Estimate the primary consolidation settlement of the clay due to the foundation load. • What is the void ratio at the end of primary consolidation? • Calculate the secondary Consolidation settlement after 6 years knowing that the primary consolidation settlement took 2.5 years. Given: P = 350 kN, B =L=2.5 m, Df= 2 m, H1= 3 m, and H2=4.5 m. The soil properties are as follows: Sand: ya = 16.4 kN/m³; ysat = 18.8 kN/m³ Clay: Ysat = 17.6 kN/m²; eo = 0.82, Ca=0.02 Sand D Yd H GWT BxL Ysat Clay Ysat Sandy gravelarrow_forward
- answer in 3 decimal places ty :)arrow_forwardRefer to Figure 11.41. Given that B =1 m, L = 3 m, and Q = 110 kN, the soil characteristics given in the figure are Cs = 1/5 Cc, Ꝺ’c= 40 kN/m2. Field monitoring indicated that the foundation settlement was 19 mm during the first 12 months. a. Estimate the average stress increase in the clay layer due to the applied load. b. Estimate the primary consolidation settlement. c. What is the degree of consolidation after 12 months? d. Estimate the coefficient of consolidation for the pressure range. e. Estimate the settlement in 24 months. Answer must be: A. 6.33 B. 32.82 C. 57.89 D. 0.0013 E. 25.66arrow_forwardA CD triaxial compression test conducted on a clay specimen revealed that c'=5 kPa and o'=22°. What is the major principal stress at failure if the confining pressure is 35 kPa? Solve the problem graphically and then analytically.arrow_forward
- Given that B =1 m, L = 3 m, and Q = 110 kN, the soil characteristics given in the figure are Cs = 1/5 Cc, Ꝺ’c= 40 kN/m2. Field monitoring indicated that the foundation settlement was 19 mm during the first 12 months. Estimate the average stress increase in the clay layer due to the applied load. Estimate the primary consolidation settlement. What is the degree of consolidation after 12 months? Estimate the coefficient of consolidation for the pressure range. Estimate the settlement in 24 months.arrow_forwardfinal answer in 3 decimal placesarrow_forwardplease solve.arrow_forward
- Estimate the ultimate consolidation settlement under the centerline of a 15 X 15 m mat foundation. The mat is 1 m thick reinforced concrete and the average stress on the surface of the slab is 75 kPa. The soil profile is shown below. Oedometer tests on samples of the clay provide these average values. ’p = 130 kPa, Cc = 0.40, Cr = Cs = 0.03 Neglect any settlements due to the sand layer. Please and thank you!! :)arrow_forwardA plan of a foundation 1 m x 2 m is shown in Figure 4-2. a. Estimate the consolidation settlement of the foundation. b. Refer to part a. Given for the clay layer: Ca=0.02. Estimate the total consolidation settlement eight years after the completion of the primary consolidation settlement. (Note: Time for completion of primary consolidation settlement is 1.5 years). 15m 0.5 m 9=170 kN/m²(net stress increase) BXL 1m x 2m Sand Y = 16.5 kN/m Groundwater table Sand 25m Figure 4-2 = You 17.5 kN/m³ Normally consolidated clay y = 16 kN/m³ ea 0.78 E = 6,000 kN/m² C, = 0.32 C₁ = 0.09 A. = 0.5arrow_forwardindicate the final answer in 3 decimal places.arrow_forward
- Principles of Foundation Engineering (MindTap Cou...Civil EngineeringISBN:9781337705028Author:Braja M. Das, Nagaratnam SivakuganPublisher:Cengage LearningPrinciples of Foundation Engineering (MindTap Cou...Civil EngineeringISBN:9781305081550Author:Braja M. DasPublisher:Cengage Learning