Concept explainers
(a)
Calculate the total consolidation settlement under the action of fill load.
(a)
Answer to Problem 11.1CTP
The total consolidation settlement
Explanation of Solution
Given information:
The thickness of fill material
The compacted unit weight of fill material
The length of the foundation
The breadth of the foundation
The depth of fill
The height of the layer silty sand
The height of the clay layer
The height of the peat layer
The dry unit weight of sand
The saturated unit weight of sand
The saturated unit weight of clay
The saturated unit weight of peat
The time
The properties of clay and organic layers are given in the Table.
Calculation:
Consider the unit weight of water
Calculate the distributed load
Substitute
Calculate the increase in vertical stress
Here,
For clay layer:
For the depth
Calculate the width
Substitute
Calculate the ratio
Substitute
Calculate the ratio
Substitute
Similarly calculate the remaining values and tabulate as in Table 1.
Refer Table 10.11 “Variation of
Take the value of
Take the value of
Calculate the value of
Similarly calculate the remaining values and tabulate as in Table 1.
Calculate the increase in vertical stress
Substitute
Similarly calculate the increase in vertical stress values and tabulate as in Table 1.
Show the increase in vertical stress for each depth below the center of the loaded area as in Table 1.
Depth, | |||||
1 | 4 | 3 | 0.75 | 0.823 | 28.82 |
1 | 4 | 5 | 1.25 | 0.599 | 20.98 |
1 | 4 | 7 | 1.75 | 0.403 | 14.11 |
Table 1
Refer to table 1.
Calculate the stress increase in the clay layer
Here,
Substitute
Calculate the average effective stress at the middle of the clay layer
Substitute
Calculate the primary consolidation settlement
Substitute
For peat layer:
For the depth
Calculate the ratio
Substitute
Similarly calculate the remaining values and tabulate as in Table 2.
Refer Table 10.11 “Variation of
Take the value of
Take the value of
Calculate the value of
Similarly calculate the remaining values and tabulate as in Table 2.
Calculate the increase in vertical stress
Substitute
Similarly calculate the increase in vertical stress values and tabulate as in Table 2.
Show the increase in vertical stress for each depth below the center of the loaded area as in Table 2.
Depth, | |||||
1 | 4 | 7 | 1.75 | 0.403 | 14.11 |
1 | 4 | 7.9 | 1.975 | 0.342 | 11.98 |
1 | 4 | 8.8 | 2.2 | 0.302 | 10.58 |
Table 2
Refer to table 2.
Calculate the stress increase in the peat layer
Substitute
Calculate the average effective stress at the middle of the clay layer
Substitute
Calculate the primary consolidation settlement
Substitute
Calculate the total consolidation settlement under the action of fill load
Substitute
Hence, the total consolidation settlement
(b)
Calculate the time for
(b)
Answer to Problem 11.1CTP
The time for
The time for
Explanation of Solution
Given information:
The thickness of fill material
The compacted unit weight of fill material
The length of the foundation
The breadth of the foundation
The depth of fill
The height of the layer silty sand
The height of the clay layer
The height of the peat layer
The dry unit weight of sand
The saturated unit weight of sand
The saturated unit weight of clay
The saturated unit weight of peat
The time
The properties of clay and organic layers are given in the Table.
Calculation:
The degree of consolidation
The clay layer is permeable and having less void ratio compared to peat layer. Hence, double drainage condition is assumed for the clay layer.
Calculate the time factor
Refer Table 11.7 “Variation of
Take the value of
Calculate the length of maximum drainage path
Substitute
Calculate the time for
Substitute
Hence, the time for
The peat layer is low permeable and having high void ratio compared to clay layer. Hence, single drainage condition is assumed for the peat layer.
Calculate the length of maximum drainage path
Substitute
Calculate the time for
Substitute
Hence, the time for
(c)
Calculate the secondary compression in each layer up to end of
(c)
Answer to Problem 11.1CTP
The secondary compression for clay
The secondary compression for peat
Explanation of Solution
Given information:
The thickness of fill material
The compacted unit weight of fill material
The length of the foundation
The breadth of the foundation
The depth of fill
The height of the layer silty sand
The height of the clay layer
The height of the peat layer
The dry unit weight of sand
The saturated unit weight of sand
The saturated unit weight of clay
The saturated unit weight of peat
The time
The properties of clay and organic layers are given in the Table.
Calculation:
Refer to part (b).
The time for
The time for
For clay:
Calculate the primary void ratio
Substitute
Calculate the void ratio at the end of primary consolidation
Substitute
Calculate the magnitude of secondary compression index
Here,
Substitute
Calculate the secondary compression
Substitute
Hence, the secondary compression for clay
For peat:
Calculate the primary void ratio
Substitute
Calculate the void ratio at the end of primary consolidation
Substitute
Calculate the magnitude of secondary compression index
Substitute
Calculate the secondary compression
Substitute
Hence, the secondary compression for peat
(d)
Calculate the total settlement after 18 months.
(d)
Answer to Problem 11.1CTP
The total settlement after 18 months is
Explanation of Solution
Given information:
The thickness of fill material
The compacted unit weight of fill material
The length of the foundation
The breadth of the foundation
The depth of fill
The height of the layer silty sand
The height of the clay layer
The height of the peat layer
The dry unit weight of sand
The saturated unit weight of sand
The saturated unit weight of clay
The saturated unit weight of peat
The time
The properties of clay and organic layers are given in the Table.
Calculation:
Refer to part (a).
The total consolidation settlement
Refer to part (c).
The secondary compression for clay
The secondary compression for peat
Calculate the total settlement after 18 months as shown below.
Substitute
Hence, the total settlement after 18 months is
(e)
Calculate the excess pore water pressure at point A two months after the application of the fill load.
(e)
Answer to Problem 11.1CTP
The excess pore water pressure at point A
Explanation of Solution
Given information:
The thickness of fill material
The compacted unit weight of fill material
The length of the foundation
The breadth of the foundation
The depth of fill
The height of the layer silty sand
The height of the clay layer
The height of the peat layer
The dry unit weight of sand
The saturated unit weight of sand
The saturated unit weight of clay
The saturated unit weight of peat
The time
The properties of clay and organic layers are given in the Table.
The depth
Calculation:
Refer to part (a).
The pore water pressure
Calculate the length of maximum drainage path
Substitute
Calculate the time factor
Substitute
Calculate the ratio
Substitute
Calculate the degree of consolidation
Refer Figure 11.29 “Variation of
Take the value of U as
Calculate the excess pore water pressure after 2 months
Substitute
Hence, the excess pore water pressure at point A
(f)
Calculate the effective stress at point A two months after the application of the fill load.
(f)
Answer to Problem 11.1CTP
The effective stress at point A is
Explanation of Solution
Given information:
The thickness of fill material
The compacted unit weight of fill material
The length of the foundation
The breadth of the foundation
The depth of fill
The height of the layer silty sand
The height of the clay layer
The height of the peat layer
The dry unit weight of sand
The saturated unit weight of sand
The saturated unit weight of clay
The saturated unit weight of peat
The time
The properties of clay and organic layers are given in the Table.
The depth
Calculation:
Refer to part (a).
The pore water pressure
Refer to part (e)
The excess pore water pressure at point A
Calculate the increase in effective stress
Substitute
Calculate the average effective stress at the point A
Substitute
Calculate the final effective stress at point A as shown below.
Substitute
Hence, the effective stress at point A is
(g)
Calculate the piezometer reading at point A two months after the application of the fill load.
(g)
Answer to Problem 11.1CTP
The piezometer reading at point A is
Explanation of Solution
Given information:
The thickness of fill material
The compacted unit weight of fill material
The length of the foundation
The breadth of the foundation
The depth of fill
The height of the layer silty sand
The height of the clay layer
The height of the peat layer
The dry unit weight of sand
The saturated unit weight of sand
The saturated unit weight of clay
The saturated unit weight of peat
The time
The properties of clay and organic layers are given in the Table.
The depth
Calculation:
Refer to part (e)
The excess pore water pressure at point A
The piezometer reading is the total pore water pressure.
Calculate the piezometer reading
Substitute
Hence, the piezometer reading at point A is
Want to see more full solutions like this?
Chapter 11 Solutions
Principles of Geotechnical Engineering (MindTap Course List)
- Find the maximum distributed load can be applied to the two fixed ends beam shown below. Use Virtual work method Wu L=6marrow_forwardCalculate the collapse load (P) for the two fixed ended beam shown below. Use virtual work method P 2 m 4 m L=6marrow_forwardQuestion 1 (Approximate Method - Superposition). Using Superposition determine the displacement at C of this beam. El is constant. (Note - you must use the PE Handbook Shears, Moments and Deflection Tables. The FE handbook does not have one of these conditions) (On an exam I will make sure it is found in both the FE and the PE handbook). 60 kN 30 kN/m A C 3 m 3 m B Question 2 (Slope and Deflection - virtual work - statically determinate beam) Using virtual work determine the slope at A and the displacement at C of this beam. El is constant. Same beam as question #1arrow_forward
- Question 4 (Force Method). Determine the reaction at the supports. Assume A is a pin and B and C are rollers. El is constant. 1.5 k A A 10 ft 10 ft B C - 20 ftarrow_forwardFind the maximum load (collapse load) that can be carried by the simply supported beam shown below. P ↓ 3 m 3 marrow_forwardFind the maximum distributed load can be applied to the two fixed ends beam shown below. Wu L=6marrow_forward
- In excavation for a wall footing, the water table level was lowered from a depth of 1.0 m to a depth of 3.0 m in a clayey soil deposit. Considering that the soil has a water content of 28% when it is fully saturated, and above the water table the (dry) unit weight of the soil is 17 kN/m³. Assuming initially that all of the soil above the water table is dry, then compute the following: 1. The effective stress at a depth of 4.0 m after the lowering of the water table. Take Gs = 2.68. (Hints: w*Gs=Sr*e) 2. The increase in effective stress at a depth of 5 m. (You also need to plot the values of total vertical stress and effective vertical stress against depth before and after lowering the water table.)arrow_forwardCalculate the collapse load (P) for the two fixed ended beam shown below. P 2 m 4 m L=6marrow_forwardThe vertical stress at a point in soil is σx =400 kN/m², Txz = 50kN/m² while the horizontal stress at the same point is σ =100 kN/m², Tzx = -50kN/m². (a) Draw the Mohr circle that describes the 2D stress state at the point. (b) Find the maximum shear stress that acts at the point and its orientation angle from the horizontal plane. (c) Find the principal stress (σ₁ and σ3) that acts at the point and locate the major principal stress plane and its orientation angle from the horizontal plane (Use the pole method). (d) Determine both the normal and shear stress at a plane that orientates from the major principal stress plane with an angle of 30° (counterclockwise direction) and verify your results with the stress transformation equations.arrow_forward
- 2: A billboard 2 m high x 4 m wide is supported on each end by a pin jointed assembly (bracing not shown for simplification). Total weight of billboard is 32 kN. Given: H = 1m; Angle φ = 60⁰; q = 2.4 kPa.1. Determine the normal stress (MPa) in strut AB with crosssectional dimension 6 mm x 50 mm.2. Determine the normal stress (MPa) in strut BC with crosssectional dimension 8 mm x 40 mm.3. Determine the required diameter (mm) of pin (under double shear) to be used in A or C if the allowable shear stress of the pin is 120 MPa.arrow_forwardA total load of 900 kN is uniformly distributed over a rectangular footing of size 2 mx3 m. Find the vertical stress at a depth of 1.0 m below the footing at point C, under one corner, and D, under the center. If another footing of size 1 m × 3 m with a total load of 450 kN is constructed adjoining the previous footing, what is the vertical stress at the corner point E at the same depth due to the construction of these two footings. k 3 m 1m 2m E 3 marrow_forwardA soil profile is shown below. If a uniformly distributed load Aσ is applied at the ground surface, what is the settlement of the clay layer caused by primary consolidation if a. The clay is normally consolidated b. The clay is over-consolidated with σzc=200 kPa c. The clay is over-consolidated with σzc=150 kPa (Take Cr 0.03 and Cc = 0.15) Ao 100 kN/m² 2 m 4 m 3.5 m Sand Clay Xtry 14 kN/m³ Groundwater table Yat 18 kN/m³ Yat 19 kN/m³ Void ratio, e 0.8arrow_forward
- Principles of Foundation Engineering (MindTap Cou...Civil EngineeringISBN:9781305081550Author:Braja M. DasPublisher:Cengage LearningPrinciples of Geotechnical Engineering (MindTap C...Civil EngineeringISBN:9781305970939Author:Braja M. Das, Khaled SobhanPublisher:Cengage LearningPrinciples of Foundation Engineering (MindTap Cou...Civil EngineeringISBN:9781337705028Author:Braja M. Das, Nagaratnam SivakuganPublisher:Cengage Learning
- Fundamentals of Geotechnical Engineering (MindTap...Civil EngineeringISBN:9781305635180Author:Braja M. Das, Nagaratnam SivakuganPublisher:Cengage Learning