Question
Book Icon
Chapter 10, Problem 2CS
Summary Introduction

Case summary:

Person K is the vice-president of operations at Company J, which received a request for quote of supplying 400 units per week. Employee must be permitted to perform the task for 17 times. The actual times observed were given below:

Number Actual time (minutes)
1 2.05
2 1.92
3 2.01
4 1.89
5 1.77
6 1.8
7 1.86
8 1.83
9 1.93
10 1.96
11 1.95
12 2.05
13 1.79
14 1.82
15 1.85
16 1.85
17 1.99

Performance rating is 115%, fatigue allowance is given as 8%, personal allowance is 6%, and delay allowance is 2%. Workday hour is 7.5 hours and the operators would be paid $12.50 per hour for 8 hours.

To determine: Whether the sample size is adequate.

Blurred answer
Students have asked these similar questions
Please use the following information to answer the following questions Alpha=0.05, Beta=D0.01, LTPD=0.3 , AQL=0.05 Question 8. What is the cut off point? 66
Question 1 This Test: 60 pts possible Submit Test Daily high temperatures in St. Louis for the last week were as follows: 92, 92, 94, 94, 95, 88, 95 (yesterday). a) The high temperature for today using a 3-day moving average = degrees (round your response to one decimal place). b) The high temperature for today using a 2-day moving average = degrees (round your response to one decimal place). c) The mean absolute deviation based on a 2-day moving average = degrees (round your response to one decimal place). %3D d) The mean squared error for the 2-day moving average = degrees (round your response to one decimal place). e) The mean absolute percent error (MAPE) for the 2-day moving average = % (round your response to one decimal place).
QUESTION 2   South Africa Airways would like to monitor its airline's performance. Each week for the past 20 weeks, they checked each week a random sample of 100 flight arrivals for "one-time" performance. The table that follows contains the number of flights that did not meet South Africa Airways definition of "one time":   Week   Late flights   10   9   11 39103422822   10   11   12   13   14   15 16 17 18 19 20   19   2.1 Which control chart is appropriate to analyze the above data? Justify your answer.   2.2 Calculate the upper and lower control limits for this chart @ 99.73% confidence level.   2.3 Draw the chart and interpret it.   (3)   (10)   (9)   QUESTION 3   Two machines are currently in use in a process at a local manufacturing plant. The standards for this process are LSL 400 and USL .403. Machine One is currently producing with mean .401 and a standard deviation 0004. Machine Two is currently producing with mean = 4015 and a standard deviation = .0005.   3.1 Which of the…
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.