Case summary:

Person K is the vice-president of operations at Company J, which received a request for quote of supplying 400 units per week. Employee must be permitted to perform the task for 17 times. The actual times observed were given below:

Number Actual time (minutes)
1 2.05
2 1.92
3 2.01
4 1.89
5 1.77
6 1.8
7 1.86
8 1.83
9 1.93
10 1.96
11 1.95
12 2.05
13 1.79
14 1.82
15 1.85
16 1.85
17 1.99

Performance rating is 115%, fatigue allowance is given as 8%, personal allowance is 6%, and delay allowance is 2%. Workday hour is 7.5 hours and the operators would be paid $12.50 per hour for 8 hours.

To determine: The sample size for an accurate standard.

Blurred answer
Students have asked these similar questions
QUESTION 6 In a burger shop, a sample of 36 days, was taken to study the daily sales, It was found that the mean daily sales are (m) with a standard deviation is (d). The confidence interval for the population mean is computed, the upper confidence limit is 35, and the lower confidence limit is 18 Calculate the value of m? (Round answer to two decimal places ex. 2.09)
How big should the sample be for a statistically accurate standard(at, say, the 99.73% confidence level and accuracy of ±5%)?
Question : A process that is considered to be in control measures an ingredient in ounces. Below are the last ten samples (each of size n=5) taken.  The population standard deviation is 1.36.   SAMPLE   1   2   3   4   5   6   7   8   9     10     5 6 9 10 9 10 9 12 8 9   8 9 9 8 12 11 9 9 6 10   6 8 5 7 10 8 10 9 4 12   4 7 3 8 8 6 12 10 4 11   5 4 2 9 8 6 8 6 5 7   Using information from the above table: Calculate the standard deviation of the sample means, σ×. Determine the control limits for the mean chart, using A2 and σ× if z=3. Determine the control limits for the range chart. Construct mean (using A2) and range control charts by using information from (ii) and (iii).                                                                Comment on your results.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.