Operations Management
13th Edition
ISBN: 9780135173626
Author: HEIZER, Jay, RENDER, Barry, Munson, Chuck
Publisher: Pearson,
expand_more
expand_more
format_list_bulleted
Question
Chapter 10, Problem 15P
a)
Summary Introduction
To determine: To find the standard time for the operation
Introduction: Time study is the basis that helps to set the standard time; it would time a sample of the performance of the worker.
b)
Summary Introduction
To determine: Thestandard time for the operation
Introduction: Time study is the basis that helps to set the standard time; it would time a sample of the performance of the worker.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Jell Lee Beans is famous for its boxed candies, which are sold primarily to businesses. One operator had the following observed times for gift wrapping in minutes: 2.3, 2.7, 2.4, 2.4, 2.3. The operator has a performance rating of 110% and an
allowance factor of 10%.
The standard time for this gift-wrapping operation =
minutes (round your response to one decimal place).
help please
Under which perspective of the balanced scorecard would you classify on time delivery to customers?
Chapter 10 Solutions
Operations Management
Ch. 10 - Prob. 1DQCh. 10 - Prob. 2DQCh. 10 - Prob. 3DQCh. 10 - Prob. 4DQCh. 10 - Prob. 5DQCh. 10 - Prob. 6DQCh. 10 - Prob. 7DQCh. 10 - Prob. 8DQCh. 10 - Prob. 9DQCh. 10 - Prob. 10DQ
Ch. 10 - Prob. 11DQCh. 10 - Prob. 12DQCh. 10 - Prob. 13DQCh. 10 - Prob. 14DQCh. 10 - Prob. 2PCh. 10 - Draw an activity chart for a machine operator with...Ch. 10 - Prob. 4PCh. 10 - Prob. 5PCh. 10 - Prob. 6PCh. 10 - Prob. 1PCh. 10 - Prob. 7PCh. 10 - Prob. 8PCh. 10 - Prob. 9PCh. 10 - Prob. 10PCh. 10 - Prob. 11PCh. 10 - Prob. 12PCh. 10 - Prob. 13PCh. 10 - Prob. 14PCh. 10 - Prob. 15PCh. 10 - Prob. 16PCh. 10 - Prob. 17PCh. 10 - Prob. 18PCh. 10 - Prob. 19PCh. 10 - Prob. 20PCh. 10 - Prob. 21PCh. 10 - Prob. 22PCh. 10 - Prob. 23PCh. 10 - Prob. 24PCh. 10 - Prob. 25PCh. 10 - Prob. 26PCh. 10 - Prob. 27PCh. 10 - Prob. 28PCh. 10 - Prob. 29PCh. 10 - Prob. 30PCh. 10 - Prob. 31PCh. 10 - Prob. 32PCh. 10 - Prob. 34PCh. 10 - Prob. 35PCh. 10 - Prob. 36PCh. 10 - Prob. 37PCh. 10 - Prob. 33PCh. 10 - Prob. 39PCh. 10 - Prob. 40PCh. 10 - Prob. 41PCh. 10 - Prob. 42PCh. 10 - Prob. 44PCh. 10 - Prob. 1CSCh. 10 - Prob. 2CSCh. 10 - Prob. 3CSCh. 10 - Prob. 4CSCh. 10 - Prob. 2.1VCCh. 10 - Prob. 2.2VCCh. 10 - Prob. 2.3VCCh. 10 - Prob. 2.4VCCh. 10 - Prob. 1.1VCCh. 10 - Prob. 1.2VCCh. 10 - Prob. 1.3VC
Knowledge Booster
Similar questions
- Describe some of the limitations of time study method ?arrow_forwardplease answer within 30 minutes.arrow_forwardIdentify to which category of “personal”, “fatigue”, or “delay” the following job elements belong to a) The hair-dresser takes the phone to confirm a booking, in the middle of a client haircut. b) The doctor takes a cup of coffee and a quick rest in a short time between visiting two patients. c) In a long-distance drive, the coach driver stops in a service area every two to three hours to have some food.arrow_forward
- Please do not give solution in image format thankuarrow_forwardA time study of an employee assembling peanut valves resulted in the following set of observations. What is the standard time, given a performance rating of 97 percent and an allowance of 10 percent of the total normal time? LOADING... Average Time (seconds) Observations 10 15 11 10 15 19 Part 2 The standard time is enter your response here seconds. (Enter your response rounded to two decimal places.)arrow_forwardLatisha Simmons, a loan processor at Wentworth Bank, has been timed performing four work elements, with the results shown in the following table. Task Element 1 2 3 4 Performance Rating 110% 85% 90% 85% 1 0.6 0.6 0.5 1.4 Observation (minutes per cycle) 2 3 4 0.3 0.8 0.5 1.9 0.6 0.7 0.6 1.9 0.4 0.6 0.5 1.7 The allowances for tasks such as this are personal, 8%; fatigue, 12%; and delay, 3%. minutes (round your response to two a) The normal time for the complete operation : = decimal places). b) The standard time for this process = minutes (round your response to two decimal places). 0.5 0.8 0.5 1.4arrow_forward
- A worker-machine operation was found to involve 3.3 minutes of machine time per cycle in the course of 40 cycles of stopwatch study. The worker's time-averaged 1.9 minutes per cycle, and the worker was given a rating of 120% (machine rating is 100%). Midway through the study, the worker took a 10-minute rest break. Assuming an allowance factor of 12% of work time, determine the standard time for this job. Hints: you should consider both machine time and machine time together. Also, Allowance only applies to the man, not a machine.arrow_forwardNine observations from a work measurement study using continuous timing are shown below. Allowances are determined as: personal, five percent; fatigue, six percent; delay, five percent. Use the Work Measurement Excel template to determine the standard time for this operation. Work Observation Element 1 2 3 4 5 6 7 8 9 Performance Rating A 0.10 0.15 0.08 0.06 0.11 0.10 0.16 0.15 0.16 115% B 0.23 0.18 0.23 0.22 0.25 0.24 0.29 0.28 0.28 95% C 0.49 0.52 0.49 0.48 0.47 0.47 0.52 0.49 0.51 105% D 0.62 0.67 0.64 0.59 0.70 0.68 0.68 0.67 0.70 90% E 0.71 0.74 0.73 0.70 0.81 0.81 0.78 0.81 0.83 105% F 1.03 1.03 1.01 1.01 1.08 1.12 1.03 1.09 1.11 100% Round your answer to two decimal places. minutesarrow_forwardIOarrow_forward
- Nine observations from a work measurement study using continuous timing are shown below. Allowances are determined as: personal, five percent; fatigue, five percent; delay, seven percent. Use the Work Measurement Excel template to determine the standard time for this operation. Work Observation Element 1 2 3 4 5 6 7 8 9 Performance Rating A 0.11 0.14 0.10 0.09 0.12 0.11 0.15 0.14 0.15 105% B 0.24 0.20 0.21 0.22 0.24 0.23 0.28 0.26 0.26 85% C 0.46 0.48 0.46 0.44 0.48 0.48 0.48 0.46 0.49 100% D 0.64 0.66 0.65 0.59 0.71 0.69 0.69 0.66 0.71 115% E 0.70 0.74 0.74 0.68 0.79 0.83 0.77 0.80 0.84 100% F 1.01 1.05 1.01 1.00 1.09 1.12 1.05 1.06 1.12 95% Round your answer to two decimal places. minutesarrow_forwardNine observations from a work measurement study using continuous timing are shown below. Allowances are determined as: personal, five percent; fatigue, six percent; delay, six percent. Use the Work Measurement Excel template to determine the standard time for this operation. Work Observation Element 1 2 3 4 5 6 7 8 9 Performance Rating A 0.09 0.13 0.06 0.05 0.11 0.09 0.14 0.13 0.14 85% B 0.25 0.18 0.23 0.20 0.24 0.24 0.27 0.26 0.26 115% C 0.47 0.51 0.47 0.46 0.49 0.49 0.51 0.47 0.48 110% D 0.61 0.69 0.65 0.60 0.71 0.67 0.67 0.69 0.73 90% E 0.72 0.76 0.74 0.68 0.79 0.81 0.76 0.80 0.81 115% F 1.02 1.04 0.98 1.02 1.08 1.12 1.04 1.07 1.09 85% Round your answer to two decimal places. minutesarrow_forwardNine observations from a work measurement study using continuous timing are shown below. Allowances are determined as: personal, five percent; fatigue, eight percent; delay, five percent. Use the Work Measurement Excel template to determine the standard time for this operation. Work Observation Element 1 2 3 4 5 6 7 8 9 Performance Rating A 0.09 0.14 0.08 0.07 0.10 0.09 0.15 0.14 0.15 110% B 0.23 0.20 0.22 0.20 0.24 0.23 0.29 0.27 0.27 90% C 0.49 0.51 0.49 0.46 0.49 0.49 0.51 0.49 0.48 95% D 0.64 0.66 0.63 0.62 0.69 0.67 0.67 0.66 0.70 115% E 0.72 0.74 0.74 0.69 0.81 0.82 0.79 0.80 0.82 105% F 1.01 1.03 0.99 0.99 1.09 1.12 1.03 1.07 1.12 85% Round your answer to two decimal places. minutesarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.