When will the activity be finished?
9 months
10 months
11 months
1 year
When will activity CC end?
month 6
month 7
month 8
month 5
When will activity DD start?
month 6
month 7
month 8
month 5
What is the critical path?
ACDE
ABDE
ABCDE
ABCD
![Precedent Activity
Activity
AA
BB
Time
None
1 month
AA
3 months
СС
AA
BB,CC
5 months
DD
4 months
ЕЕ
DD
2 months](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F30daca3a-a33f-4fd5-87f7-3ac17fe31d8b%2Fc1c41a7e-cb61-45d5-ba19-23692eebc8d5%2Fsp8d6q_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Precedent Activity
Activity
AA
BB
Time
None
1 month
AA
3 months
СС
AA
BB,CC
5 months
DD
4 months
ЕЕ
DD
2 months
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 5 steps with 1 images