The manager of the Oak Hills Svimming Club is planning the club's swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follovs. Time (Weeks) Immediate Predecessor Activity Description Optimistic Most Probable Pessimistic A Meet with board 2 B Hire coaches A 4 6 8 Reserve pool A 2 4 6 D Announce program В, с 1 E Meet with coaches B 2 3 4 F Order team suits A 1 2 Register swimmers D 1 2 H Collect fees 1 2 3 Plan first practice E, H, F 1 1 (a) Draw a project netvork. (Submit a file vith a maximum size of 1 MB.) Browse. No file selected. (b) Develop an activity schedule. (Round your answers to tvo decimal places.) Earliest Start Latest Start Earliest Finish Latest Activity Slack Finish A B D E F G H I (c) What are the critical activities? (Enter your answers as a comma-separated list.) What is the expected project completion time (in veeks)? (Round your answer to tvo decimal places.) | weeks (d) If the club manager plans to start the project on February 1, calculate the probability the svimming program vill be ready by the scheduled May 1 date (13 weeks) based solely on the critical path. (You may need to use the appropriate technology to answer this question. Round your answer to four decimal places.) Should the manager begin planning the svimming program before February 1? (The probability for finishing on schedule should be at least 0.9.) Since the probability that the svimming program will be ready by May 1 is -Select-- v than 0.9, the manager -Select- v begin planning before February 1.
The manager of the Oak Hills Svimming Club is planning the club's swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follovs. Time (Weeks) Immediate Predecessor Activity Description Optimistic Most Probable Pessimistic A Meet with board 2 B Hire coaches A 4 6 8 Reserve pool A 2 4 6 D Announce program В, с 1 E Meet with coaches B 2 3 4 F Order team suits A 1 2 Register swimmers D 1 2 H Collect fees 1 2 3 Plan first practice E, H, F 1 1 (a) Draw a project netvork. (Submit a file vith a maximum size of 1 MB.) Browse. No file selected. (b) Develop an activity schedule. (Round your answers to tvo decimal places.) Earliest Start Latest Start Earliest Finish Latest Activity Slack Finish A B D E F G H I (c) What are the critical activities? (Enter your answers as a comma-separated list.) What is the expected project completion time (in veeks)? (Round your answer to tvo decimal places.) | weeks (d) If the club manager plans to start the project on February 1, calculate the probability the svimming program vill be ready by the scheduled May 1 date (13 weeks) based solely on the critical path. (You may need to use the appropriate technology to answer this question. Round your answer to four decimal places.) Should the manager begin planning the svimming program before February 1? (The probability for finishing on schedule should be at least 0.9.) Since the probability that the svimming program will be ready by May 1 is -Select-- v than 0.9, the manager -Select- v begin planning before February 1.
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
![The manager of the Oak Hills Swimming Club is planning the club's swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in
weeks) are as follows.
Time (Weeks)
Immediate
Predecessor
Activity
Description
Optimistic Most Probable
Pessimistic
A
Meet with board
1
1
2
B
Hire coaches
A
4
8
Reserve pool
A
4.
6
D
Announce program
В, с
3
E
Meet with coaches
B
4
F
Order team suits
A
1
2
3
G
Register swimmers
D
2
3
H
Collect fees
G
1
I
Plan first practice
Е, Н, F
1
1
1
(a) Draw a project network. (Submit a file with a maximum size of 1 MB.)
Browse. No file selected.
(b) Develop an activity schedule. (Round your answers to two decimal places.)
Earliest
Start
Earliest
Finish
Latest
Latest
Activity
Slack
Start
Finish
A
B
D
E
F
G
H
I
(c) What are the critical activities? (Enter your answers as a comma-separated list.)
What is the expected project completion time (in weeks)? (Round your answer to two decimal places.)
weeks
(d) If the club manager plans to start the project on February 1, calculate the probability the swimming program will be ready by the scheduled May 1 date (13 weeks) based solely on the critical path. (You may need to
use the appropriate technology to answer this question. Round your answer to four decimal places.)
Should the manager begin planning the swimming program before February 1? (The probability for finishing on schedule should be at least 0.9.)
Since the probability that the swimming program will be ready by May 1 is -Select- v than 0.9, the manager -Select- v begin planning before February 1.](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F845cc991-f9af-4030-ab65-04dc56a6a991%2F371f8333-0d7e-4dd2-b383-0c334e459046%2Foeglhhf_processed.png&w=3840&q=75)
Transcribed Image Text:The manager of the Oak Hills Swimming Club is planning the club's swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in
weeks) are as follows.
Time (Weeks)
Immediate
Predecessor
Activity
Description
Optimistic Most Probable
Pessimistic
A
Meet with board
1
1
2
B
Hire coaches
A
4
8
Reserve pool
A
4.
6
D
Announce program
В, с
3
E
Meet with coaches
B
4
F
Order team suits
A
1
2
3
G
Register swimmers
D
2
3
H
Collect fees
G
1
I
Plan first practice
Е, Н, F
1
1
1
(a) Draw a project network. (Submit a file with a maximum size of 1 MB.)
Browse. No file selected.
(b) Develop an activity schedule. (Round your answers to two decimal places.)
Earliest
Start
Earliest
Finish
Latest
Latest
Activity
Slack
Start
Finish
A
B
D
E
F
G
H
I
(c) What are the critical activities? (Enter your answers as a comma-separated list.)
What is the expected project completion time (in weeks)? (Round your answer to two decimal places.)
weeks
(d) If the club manager plans to start the project on February 1, calculate the probability the swimming program will be ready by the scheduled May 1 date (13 weeks) based solely on the critical path. (You may need to
use the appropriate technology to answer this question. Round your answer to four decimal places.)
Should the manager begin planning the swimming program before February 1? (The probability for finishing on schedule should be at least 0.9.)
Since the probability that the swimming program will be ready by May 1 is -Select- v than 0.9, the manager -Select- v begin planning before February 1.
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 6 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.