Warehouse CPM Schedule 2 4 Rough Electrical Insulate 2 5 7 4 2 5 2 Excavate Form & Pour Slab Frame Ext Walls Frame Roof Shingle Roof Inst. Drywall Paint Interior 3 Finish Electrical 1 Close Out ES DEF Activity LS F LF SF FF IF Legend Temp Power 5 Windows & Doors 6 Brick South Side 5 2 Paint Inst. Siding Exterior Task 1: Solve the above schedule and determine the FF, SF, IF.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter7: Nonlinear Optimization Models
Section: Chapter Questions
Problem 56P
icon
Related questions
Question
100%

Solve the above schedule and determine the FF, SF, IF.

Thank you!

Warehouse CPM Schedule
2
4
Rough
Electrical
Insulate
2
5
7
4
2
5
2
Excavate
Form & Pour
Slab
Frame Ext
Walls
Frame Roof
Shingle Roof
Inst. Drywall
Paint Interior
3
Finish
Electrical
1
Close Out
ES DEF
Activity
LS F LF
SF FF IF
Legend
Temp Power
5
Windows &
Doors
6
Brick South
Side
5
2
Paint
Inst. Siding
Exterior
Task 1: Solve the above schedule and determine the FF, SF, IF.
Transcribed Image Text:Warehouse CPM Schedule 2 4 Rough Electrical Insulate 2 5 7 4 2 5 2 Excavate Form & Pour Slab Frame Ext Walls Frame Roof Shingle Roof Inst. Drywall Paint Interior 3 Finish Electrical 1 Close Out ES DEF Activity LS F LF SF FF IF Legend Temp Power 5 Windows & Doors 6 Brick South Side 5 2 Paint Inst. Siding Exterior Task 1: Solve the above schedule and determine the FF, SF, IF.
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,