Customers are served in a process with two sequential resources. The processing times for the resources are 8.1 and 5.5 minutes, respectively. The first resource has 1 worker and the second resource has 1 worker. Demand occurs at the rate 4.7 customers per hour. What is the utilization (%) of the second resource?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section12.5: Analytic Steady-state Queueing Models
Problem 9P
Question

Customers are served in a process with two sequential resources. The processing times for the resources are 8.1 and 5.5 minutes, respectively. The first resource has 1 worker and the second resource has 1 worker. Demand occurs at the rate 4.7 customers per hour.

What is the utilization (%) of the second resource?

Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,