Using the below table calculate critical path for the project. Which tasks are on the critical path?
Q: b. How many weeks will it take to complete the project
A:
Q: The following represents a project that should be scheduled using CPM: TIMES (DAYS) ACTIVITY…
A: Forward Pass:Early Start (ES) = Max EF value from immediate Predecessor(s)Early Finish (EF)= ES +…
Q: Effort Task Deck Predecessors (Days) Plan A Design deck 40 Buy materials 24 A Construction Dig holes…
A: Given Information:
Q: Schedule the Following Activities using CPM: 15 Duration of the project is: ID A B C D E F G H None…
A: The critical path is a fundamental concept in project management, It refers to the longest sequence…
Q: Given the following Information about a project: List ALL Activities that are on the Critical Path…
A: ActivityEarly StartLate StartA04B24C56D46E1012G1820H610
Q: The following represents a project that should be scheduled using CPM: TIMES (DAYS) IMMEDIATE…
A: Find the Given details below: ActivityPredecessorOptimistic Time(To) a(Days)Pessimistic Time(Tp)…
Q: Identify the critical path in the project. b. Determine the length of the project. Using the data,…
A: The critical path method is a process that helps to identify tasks that are essential for project…
Q: Time Activity Predecessors (Weeks) 4 А 2 C A D В 6. E 2 F D,E 3 What is the duration of the critical…
A: The project network is the network that shows the visual form of the project activities and their…
Q: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine.…
A: ActivityPredecessorTime(in weeks)A7B8CA3DA1EB4FB5GC, E11HD, F6
Q: The "Early Finish" of activity "C" is * 15 9. 30 21 O O O O
A: Project management is the management in which different types of knowledge and skills are needed to…
Q: O A.2 B. 3 G. 2 C, 1 D. 3 H. 5 E, 4 F. 3 I, 3 C Given the diagram above, please answer the…
A: Note: - As we can answer up to three subparts, we will answer the first three (1, 2, and 3) here. If…
Q: The following activities are part of a project to be scheduled using CPM: IMMEDIATE PREDECESSOR TIME…
A: Activity Immediate predecessor Time (weeks)A-8BA4CA4DC8EB, D2FD6GE, F2
Q: a) The corect precedence diagram for the project is shown in t
A: A precedence diagram can be of two types: AOA and AON. Both diagrams show the interdependencies of…
Q: Please answer all parts Activity Preceding activity Activity duration A - 6 B - 3 C - 1…
A: Note: - Since we can answer only up to three subparts we will answer the first three subparts…
Q: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine.…
A: A network diagram shows the link between each task and the duration taken by each activity with…
Q: The activity details and their predecessors are given below along with their activity times.…
A: The construction of the network is very important to understand the flow of activities in the…
Q: A project has the following activities, with specified precedents and expected durations (in days).…
A: A network diagram is a graphical representation of a project that helps to identify the activity…
Q: (1) Find the Early Start / Early Finish Time of Each Activity (2) Find the Late Start / Late Finish…
A:
Q: Given the following sequence of activities, find the activities on critical path and length of…
A: Given- Activity Predecessor Time (days) A - 5 B A 2 C A 4 D B 5 E B 5 F C 5 G E, F…
Q: In reference to the attached image and data below: What are the final recommendations? Step A we…
A: In project management, critical path refers to the order of activities that must be carried out on…
Q: You are provided with the following information for a project, with activity durations given in…
A: Given that: Activity Immediate Predecessor Optimistic Time (a) Most Likely Time (m)…
Q: 1- Calculate the total project time and floats 2- Identify activities on the critical path
A: In this question table data, we have activity information, for each activity, we have been given…
Q: What is the project standard deviation
A: A network diagram shows the link of each task with the duration taken by each activity with respect…
Q: Activity A B с D E F G H Earliest Start C r r DIC DIC 1 Latest Start Earliest Finish Latest Finish…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: Solve the following project by hand and submit your notes: Activity Normal Time (weeks) Crash…
A: NOTE: AS PER GUIDELINES, WE ARE ONLY ALLOWED TO DO THREE SUB-PARTS AT A TIME. PLEASE POST THE REST…
Q: Using the diagram, find: The critical path. How long it will take to complete the project?
A: Activity Expected time A 10 B 7 C 5 D 7 E 11 F 3 G 5 Paths : A-C-F : 10 + 5 + 3 =…
Q: A) Draw Precedence diagram (PD). B) Calculate completion data, what is completion data. C) Identify…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: lease complete the ES, EF, LS, LF, and slack for the project below. Activity Description
A: Early start (ES) indicates the earliest time of the beginning of the activity. Early finish (EF)…
Q: Project Activity and Time (days) Data Activity Normal Time (days) Crash Time (days) Immediate…
A: Using the following format for the network diagram: Early Start(Es Duration Early Finish(EF)…
Q: The following table shows estimates of activity times (in weeks) for a project: Optimistic Most…
A: The critical path is the path in the project network that takes the highest time to complete the…
Q: Determine and state the critical path for this project. This must be based on your work in (c) and…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: Let us revisit the project data from Question 7 of Homework #2, where all times are in days (and it…
A: Given data is
Q: Draw the figure No. using the time clamp method, then find the total tolerance for each activity,…
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: The first question: The part of a construction project whose activities are shown in Table No. 1…
A:
Q: The information in the table below is available for a large fund-raising project. Activity…
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: The following table shows a data of a project. Answer the following questions, a) and b). Activity…
A: Project managers utilize critical path analysis to determine which tasks, if they are delayed, will…
Q: Choose the correct network diagram for this project.…
A: In a project, slack refers to the length of time that an activity can be postponed without delaying…
Q: b. What is the critical path? O A-C-F-H OB-E-G-H O A-D-G-H O A-D-F-H c. What is the expected project…
A: Here, I will determine the expected activity time for each activity, I am given the immediate…
Q: In the program evaluation and review technique below, how many activities are there for this 7 month…
A: Program Evaluation and Review Technique is referred to as PERT. This statistical tool is employed in…
Q: Development of Version 2.0 of a particular accounting software product is being considered by Jose…
A: The given problem isActivityImmediatePredecessorsNormalTimeNormalCostCrashTimeTotal Cost with…
Q: What is the critical path? A-B-E-F-H OA-B-D-F-H A-C-D-F-H None of the above
A: The Critical Path Method is a project management technique used to determine the most crucial…
Q: 1.) Draw the network using the table above. Make sure all 4 values (ES, EF, LS, LF) are listed on…
A: As per Bartleby guidelines, we can only solve the first three sub parts of one question at a…
Q: (a) Draw the network diagram. Please add drawing here (photo may be added if hand drawn) (b) Using…
A: A project network is the graphical representation of project activities and their duration to…
Q: The following table represents a plan for a project: TIMES (DAYS) JOB NO. L234567BSGL 1 8 9 10 11…
A: 11 jobs with time estimates are given below:
Q: Consider the Work Breakdown Structure of this project. Immediate Activity Duration (days)…
A: Project duration is the time that any project takes to fully complete and deliver the final product…
Q: The project will take The critical activities are The early start on Activity D is The late start on…
A: A network diagram shows the link between each task and the duration taken by each activity with…
Q: The Scott Corey accounting firm is installing a new computer system. Several things must be done to…
A: The method of analyzing the set of activities related to the project of the company is known as the…
Using the below table calculate critical path for the project. Which tasks are on the critical path?
Task | Predecessor | Duration (Weeks) |
A | - |
32 |
B | - | 11 |
C | - | 12 |
D | B,C | 16 |
E | A,B | 23 |
F | A | 23 |
G | D | 22 |
H | D | 33 |
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 1 images
- Table A Activity Predecessor Time(weeks) A 8 B A 6 4 -- 9 E A 11 В 3 G D, E, F Using Table A, what is the earliest completion time for this project? Multiple Cholce 18 weeks 19 weeks 20 weeks 21 weeksRoss Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Activity A B C D E F a Time (weeks) 4 1 8 5 1 6 m 9 8 14 7 2 9 b 12 23 18 10 4 20 Immediate Predecessor(s) A A A B C, E Activity G H I J K a 3 1 7 4 1 Time (weeks) m 3 1 7 8 1 b 5 1 7 12 4 Immediate Predecessor(s) C, E F F D, G, H I, JUsing the following table, calculate the Late Start for Task G Task Predecessor Duration (days) A - 50 B A 32 C - 53 D - 21 E B 26 F B,C 55 G E,F 52 H F 15
- Consider the following project schedule and respond to the requirements that follow (all times are in days). Activity Predecessors a m b A ---- 12 16 20 B ---- 18 28 32 C A 6 9 12 D B 7 16 19 E C, D 4 10 16 F D, E 18 30 36 G F 5 8 17 H F, G 15 25 35 I F, G 22 26 36 J G 15 19 29 K I, H 24 32 34 (a) Construct a project network diagram using the AON technique, i.e. Activity on Node technique (and NOT AOA or activity on arc technique). Be sure to have a start node and a finish node and include the expected activity times for each node. (b) Determine the critical path and expected project completion time using the “critical path method”. Show ES, EF, LS and LF times, as well as slack for all activities. (c) Determine the standard deviation of the project completion time T; what is the probability that the project will take more…There are five activities on a project's critical path and they have standard deviations of 1, 1, 3, 5, 5 days. The standard deviation (in days) of the critical path is: OA. 8.8 OB.9.8 OC.7.8 OD.4.6 O.E. 10.2 OF, 10.6 W F2 A Moving to another question will save this response. #3 20 E F3 D $ 4 DOD 000 F4 R F % 5 F5 T G MacBook Air ^ 6 .... F6 Y & 7 H ◄◄ F7 U * ► 11 8 J F8 1 9 K F9 O ) 0 F10 « Question 30 of 42 > >> 4) F11 + 11 F12 delete DEBThe accompanying table shows the activities, times, and sequences required: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B 2 C 4 4 6 6 DEFGHH I ✔A-C-F-G- ? A-B-E-I b. What is the critical path? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.) ? A-D-H- ? A-D-F-G- B ✓C c. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B. C, D. and G each one week. Which would you shorten? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.) ✔A-D-H- A A A B ? A-B-E-I C, D D, F D E, G, H d-1. What is the new critical path? (You may select more than one answer. Single click the box with the question mark to…
- Humber Web Design Co. is organizing a new project to increase efficiency and improve relations with their clients. The project manager for this initiative has broken the project up into several parts as follows: Activity Activity Description Immediate Predecessor Activity time (days) A Identify Client Base ― 33 B Develop Client Prospectus ― 21 C Perform Design Analysis ― 35 D Program Back End A, B, C 47 E Program Front End A 13 F Project Consolidation D, E 11 (a) For the given project, fill in the nodes of the network diagram below. A E 33 13 Start B D F Finish Time 21 47 11 Time C 35 (b) Using the network diagram, fill in the table. Make sure that you put the values in the appropriate columns. Activity Earliest Start (ES) Latest…An advertising project manager developed the network diagram shown in Figure 2.10 for a new advertising campaign. In addition, the manager gathered the time information for each activity, as shown in the accompanying table. a. Calculate the expected time and variance for each activity. b. Calculate the activity slacks and determine the critical path, using the expected activity times. c. What is the probability of completing the project within 23 weeks?Given the following data:ActivityPredecessorDuration (days)a-10b-15ca17db5eb4fc15gd7he8if12jg,h,i104.1 Draw the network (AON) and calculate and calculate the Critical Path. 4.2 Your organization has been appointed to co-ordinate the local government elections.Develop a Work Breakdown Structure (WBS) – graphical format for this project.
- The project described by: Activity ImmediatePredecessor Time(days) A -- 6 B A 2 C -- 8 D B, C 5 E D 7 has a critical path of length ofConsider a project that has the following tasks (with the duration measured in days): Task ID Duration Dependency A 3 14 C,F a) Draw the PERT chart for the above table. Be sure to include sequencing and identification for all tasks and events along with their time estimates. b) What is the critical path. c) What is the total expected duration time represented by the critical path. eThe following represents a project with known activity times. All times are in weeks.Activity ImmediatePredecessor TimeA - 4B - 3C - 1D B 2E A 3F C, E 5G D 3H F 2I G, H 3J I 6K I 4L J 21) Create a CPM Network. 2) What is the total project time? 3) What activities are on the critical path?4) Compute the slack time for all non-critical activities. 5) What is the latest possible start time for activity D? Please show all work in excel and how you did it, Thank you!