weeks. (Round your response to two decimal places.) weeks. (Round your response to two decimal places.) d) The estimated time for the critical path is e) The activity variance along the critical path is f) Using the standard normal table, the probability that Hopkins Hospitality will finish the project in 42 weeks or less is probability and round your response to three decimal places.) (Enter as a

Purchasing and Supply Chain Management
6th Edition
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
ChapterC: Cases
Section: Chapter Questions
Problem 5.1SD: Scenario 4 Sharon Gillespie, a new buyer at Visionex, Inc., was reviewing quotations for a tooling...
icon
Related questions
Question
Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for
building new motels.
Activity
A
B
C
D
E
F
a
Time (weeks)
4
1
8
5
1
6
m
9
8
14
7
2
9
b
12
23
18
10
4
20
Immediate
Predecessor(s)
A
A
A
B
C, E
Activity
G
H
I
J
K
a
3
1
7
4
1
Time (weeks)
m
3
1
7
8
1
b
5
1
7
12
4
Immediate
Predecessor(s)
C, E
F
F
D, G, H
I, J
Transcribed Image Text:Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Activity A B C D E F a Time (weeks) 4 1 8 5 1 6 m 9 8 14 7 2 9 b 12 23 18 10 4 20 Immediate Predecessor(s) A A A B C, E Activity G H I J K a 3 1 7 4 1 Time (weeks) m 3 1 7 8 1 b 5 1 7 12 4 Immediate Predecessor(s) C, E F F D, G, H I, J
a) The expected (estimated) time for activity C is 13.67 weeks. (Round your response to two decimal places.)
b) The variance for activity C is 2.78 weeks. (Round your response to two decimal places.)
c) Based on the calculation of the estimated times, the critical path is A-C-F-H-J-K
d) The estimated time for the critical path is
e) The activity variance along the critical path is
weeks. (Round your response to two decimal places.)
weeks. (Round your response to two decimal places.)
f) Using the standard normal table, the probability that Hopkins Hospitality will finish the project in 42 weeks or less is
probability and round your response to three decimal places.)
(Enter as a
Transcribed Image Text:a) The expected (estimated) time for activity C is 13.67 weeks. (Round your response to two decimal places.) b) The variance for activity C is 2.78 weeks. (Round your response to two decimal places.) c) Based on the calculation of the estimated times, the critical path is A-C-F-H-J-K d) The estimated time for the critical path is e) The activity variance along the critical path is weeks. (Round your response to two decimal places.) weeks. (Round your response to two decimal places.) f) Using the standard normal table, the probability that Hopkins Hospitality will finish the project in 42 weeks or less is probability and round your response to three decimal places.) (Enter as a
Expert Solution
Step 1

The critical path method (CPM) is a project management technique that identifies the sequence of tasks that must be accomplished to complete the project.

The tasks on the critical path are those that cannot be delayed without delaying the end date of the project.

steps

Step by step

Solved in 4 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning