Let us revisit the project data from Question 7 of Homework #2, where all times are in days (and it is understood that the duration of activity A can be no less than 3 days, in which case it costs $150 instead of $50, and so on and so forth). Normal Normal Crashed Crashed Activity Predecessors Cost $150 Time Cost Time A $50 3 В 4 40 2 200 7 70 6. 160 20 1 A,C A,C 50 E 30 | F В 8 80 5 290 G 50 4 100 H E,F 60 3 180 The project has been sold at a fixed price to the client provided the project is completed on time, but in case of delays, there is a penalty of $100 for each day in excess of the normal completion time. Work on the project started on time, and the project manager scheduled a meeting with the supervisors in the morning of day 9 in order to monitor progress by the end of day 9 (time now). a) According to the normal project schedule, indicate what percentage of each activity should be completed by the end day 9. b) Suppose the progress reports indicate that activity A was completed on time but activity B will actually take 5 days longer than planned. Indicate what percentage of each activity will actually be completed by the end of day 9. c) Using the crash data, find the optimal way of rescheduling the remainder of the project. What is the revised expected project duration? And revised cost?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Let us revisit the project data from Question 7 of Homework #2, where all times
are in days (and it is understood that the duration of activity A can be no less than
3 days, in which case it costs $150 instead of $50, and so on and so forth).
Normal
Normal
Crashed
Crashed
Activity
Predecessors
Time
Cost
Time
Cost
$50
40
$150
200
А
В
4
2
C
В
70
160
A,C
2
20
1
50
E
А, С
30
-
-
F
В
8
80
290
100
180
G
5
50
4
H
E,F
60
3
The project has been sold at a fixed price to the client provided the project is
completed on time, but in case of delays, there is a penalty of $100 for each day in
excess of the normal completion time. Work on the project started on time, and the
project manager scheduled a meeting with the supervisors in the morning of day 9
in order to monitor progress by the end of day 9 (time now).
a) According to the normal project schedule, indicate what percentage of each
activity should be completed by the end day 9.
b) Suppose the progress reports indicate that activity A was completed on time
but activity B will actually take 5 days longer than planned. Indicate what
percentage of each activity will actually be completed by the end of day 9.
c) Using the crash data, find the optimal way of rescheduling the remainder of
the project. What is the revised expected project duration? And revised cost?
Transcribed Image Text:Let us revisit the project data from Question 7 of Homework #2, where all times are in days (and it is understood that the duration of activity A can be no less than 3 days, in which case it costs $150 instead of $50, and so on and so forth). Normal Normal Crashed Crashed Activity Predecessors Time Cost Time Cost $50 40 $150 200 А В 4 2 C В 70 160 A,C 2 20 1 50 E А, С 30 - - F В 8 80 290 100 180 G 5 50 4 H E,F 60 3 The project has been sold at a fixed price to the client provided the project is completed on time, but in case of delays, there is a penalty of $100 for each day in excess of the normal completion time. Work on the project started on time, and the project manager scheduled a meeting with the supervisors in the morning of day 9 in order to monitor progress by the end of day 9 (time now). a) According to the normal project schedule, indicate what percentage of each activity should be completed by the end day 9. b) Suppose the progress reports indicate that activity A was completed on time but activity B will actually take 5 days longer than planned. Indicate what percentage of each activity will actually be completed by the end of day 9. c) Using the crash data, find the optimal way of rescheduling the remainder of the project. What is the revised expected project duration? And revised cost?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 6 steps with 5 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.