Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move, record which activity was crashed, the total direct cost, total indirect cost, and total project cost. Assume the total indirect cost for the project is $1,000 and there is a savings of $60 per time unit reduced. a) What is the optimum cost-time schedule for the project? b) What is the total direct cost, total indirect cost, and total project cost at the optimum cost-time schedule for the project? c) Plot the project cost-duration graph for the project showing the three different types of costs. Note: The correct normal project duration and total direct cost are provided. WORK MUST BE DONE IN MICROSOFT EXCEL (WITH FORMULAS AND EXPLANATION, NOT BY HAND

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move, record which activity was crashed, the total direct cost, total indirect cost, and total project cost. Assume the total indirect cost for the project is $1,000 and there is a savings of $60 per time unit reduced.

a) What is the optimum cost-time schedule for the project?

b) What is the total direct cost, total indirect cost, and total project cost at the optimum cost-time schedule for the project?

c) Plot the project cost-duration graph for the project showing the three different types of costs.

Note: The correct normal project duration and total direct cost are provided.

WORK MUST BE DONE IN MICROSOFT EXCEL (WITH FORMULAS AND EXPLANATION, NOT BY HAND

A
2x
Act.
A
B
с
D
E
F
G
Crash Cost
(Slope)
B
3
C
5
100
40
60
20
40
Maximum
Crash Time
3
E5
F
4
0
1
1
2
1
1
0
Normal Normal
Time
Cost
2
3
5
3
5
4
2
G
2x
100
200
200
200
200
150
150
Project duration 14
Total direct cost 1,200
Transcribed Image Text:A 2x Act. A B с D E F G Crash Cost (Slope) B 3 C 5 100 40 60 20 40 Maximum Crash Time 3 E5 F 4 0 1 1 2 1 1 0 Normal Normal Time Cost 2 3 5 3 5 4 2 G 2x 100 200 200 200 200 150 150 Project duration 14 Total direct cost 1,200
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 8 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.