b. Identify the critical path. The critical path is -Select- C. What is the total project completion time? Round your answer to the nearest whole number. weeks d. What is the lowest cost solution if the state wants to complete the project three weeks early? Round your answer for the project duration to the nearest whole number and the answer for the total cost to the nearest dollar. The total cost of a(an) -week project-completion schedule is $

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
**Project Crash Analysis for Environment Recycling, Inc.**

Environment Recycling, Inc. must clean up a large automobile tire dump under a state environmental cleanup contract. Suppose that some of the activities in the Environment Recycling, Inc. project can be crashed. The table below shows the crash times and costs associated with performing the activities at their original (normal) times and also for the crash times (all times are in weeks).

| Activity | Predecessor(s) | Normal Time | Crash Time | Normal Cost | Crash Cost |
|----------|----------------|-------------|------------|-------------|------------|
| A        | —              | 5           | 4          | $430        | $780       |
| B        | A              | 8           | 6          | 1,950       | 2,350      |
| C        | A              | 7           | 6          | 900         | 1,200      |
| D        | —              | 6           | 5          | 620         | 1,020      |
| E        | B, C, D        | 8           | 5          | 1,900       | 2,400      |
| F        | D              | 3           | 2          | 900         | 1,100      |
| G        | D              | 3           | 2          | 500         | 650        |
| H        | E              | 4           | 3          | 580         | 780        |
| I        | F, G, H        | 6           | 5          | 850         | 1,250      |

**Explanation:**

- **Normal Time**: The original time planned to complete each activity.
- **Crash Time**: The reduced time to complete each activity when additional resources are applied.
- **Normal Cost**: The cost associated with completing an activity in the normal time.
- **Crash Cost**: The increased cost when an activity is expedited to be completed in the crash time.

The table provides essential data for project managers to consider the financial and time implications of accelerating project activities. This allows for strategic decision-making to minimize the project timeline while managing increased costs.
Transcribed Image Text:**Project Crash Analysis for Environment Recycling, Inc.** Environment Recycling, Inc. must clean up a large automobile tire dump under a state environmental cleanup contract. Suppose that some of the activities in the Environment Recycling, Inc. project can be crashed. The table below shows the crash times and costs associated with performing the activities at their original (normal) times and also for the crash times (all times are in weeks). | Activity | Predecessor(s) | Normal Time | Crash Time | Normal Cost | Crash Cost | |----------|----------------|-------------|------------|-------------|------------| | A | — | 5 | 4 | $430 | $780 | | B | A | 8 | 6 | 1,950 | 2,350 | | C | A | 7 | 6 | 900 | 1,200 | | D | — | 6 | 5 | 620 | 1,020 | | E | B, C, D | 8 | 5 | 1,900 | 2,400 | | F | D | 3 | 2 | 900 | 1,100 | | G | D | 3 | 2 | 500 | 650 | | H | E | 4 | 3 | 580 | 780 | | I | F, G, H | 6 | 5 | 850 | 1,250 | **Explanation:** - **Normal Time**: The original time planned to complete each activity. - **Crash Time**: The reduced time to complete each activity when additional resources are applied. - **Normal Cost**: The cost associated with completing an activity in the normal time. - **Crash Cost**: The increased cost when an activity is expedited to be completed in the crash time. The table provides essential data for project managers to consider the financial and time implications of accelerating project activities. This allows for strategic decision-making to minimize the project timeline while managing increased costs.
The content displayed in the image involves questions related to project management. Below is the transcription suitable for an educational website:

---

**Project Management Exercise**

b. Identify the critical path.

- **The critical path is** [Dropdown Selection].

c. What is the total project completion time? Round your answer to the nearest whole number.

- **[Text Box]** weeks

d. What is the lowest cost solution if the state wants to complete the project three weeks early? Round your answer for the project duration to the nearest whole number and the answer for the total cost to the nearest dollar.

- **The total cost of a(an) [Text Box] -week project-completion schedule is $ [Text Box].**

---

This exercise guides the learners in calculating and understanding essential elements in project management through identifying the critical path, determining project duration, and estimating costs for project acceleration.
Transcribed Image Text:The content displayed in the image involves questions related to project management. Below is the transcription suitable for an educational website: --- **Project Management Exercise** b. Identify the critical path. - **The critical path is** [Dropdown Selection]. c. What is the total project completion time? Round your answer to the nearest whole number. - **[Text Box]** weeks d. What is the lowest cost solution if the state wants to complete the project three weeks early? Round your answer for the project duration to the nearest whole number and the answer for the total cost to the nearest dollar. - **The total cost of a(an) [Text Box] -week project-completion schedule is $ [Text Box].** --- This exercise guides the learners in calculating and understanding essential elements in project management through identifying the critical path, determining project duration, and estimating costs for project acceleration.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 6 steps with 7 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.