Draw the following project schedule (See textbook section 8.8 and exhibits 8.11-8.15) Task A duration 12 days Task B duration 4 days, the predecessor is task A Task C duration 6 days, the predecessor is task A Task D duration 8 days, the predecessor is task C Task E duration 6 days, the predecessor is task B Task F duration 4 days, the predecessor is task C Task G duration 8 days, predecessors are tasks D, E, and F Indicate the ES, EF, LS, LF and slack time (format as displayed in examples) and provide a legend with the diagram. Highlight/Identify the critical path on the diagram. Show the enumeration method to determine the critical path. Be sure that both methods indicate the same critical path.
Draw the following project
Task A duration 12 days
Task B duration 4 days, the predecessor is task A
Task C duration 6 days, the predecessor is task A
Task D duration 8 days, the predecessor is task C
Task E duration 6 days, the predecessor is task B
Task F duration 4 days, the predecessor is task C
Task G duration 8 days, predecessors are tasks D, E, and F
Indicate the ES, EF, LS, LF and slack time (format as displayed in examples) and provide a legend with the diagram.
Highlight/Identify the critical path on the diagram.
Show the enumeration method to determine the critical path.
Be sure that both methods indicate the same critical path.

Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 3 images









