Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table. a. Draw the precedence diagram. b. What is the probability that the project can be completed in 24 days or less? c. Suppose it is now the end of the seventh day and that activities A and B have been completed while activity D is 50 percent completed. Time estimates for the completion of activity D are 5, 6, and 7. Activities C and H are ready to begin. Determine the probability of finishing the project by day 24.     TIME IN DAYS Activity Precedes Optimistic Most Likely Pessimistic A — 5 6 7 B — 8 8 11 C A 6 8 11 D - 9 12 15 E C 5 6 9 F D 5 6 7 G F 2 3 7 H B 4 4 5 I H 5 7 8 End E,G,I           d. The partners have decided that shortening the project by two days would be beneficial, as long as it doesn't cost more than about $20,000. They have estimated the daily crashing costs for each activity in thousands, as shown in the following table. Which activities should be crashed, and what further analysis would they probably want to do? Activity First Crash Second Crash C $8 $10 D 10 11 E 9 10 F 7 9 G 8 9 H 7 8 I 6 8

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question

Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table.

a.

Draw the precedence diagram.

b.

What is the probability that the project can be completed in 24 days or less?

c.

Suppose it is now the end of the seventh day and that activities A and B have been completed while activity D is 50 percent completed. Time estimates for the completion of activity D are 5, 6, and 7. Activities C and H are ready to begin. Determine the probability of finishing the project by day 24.

 

 

TIME IN DAYS

Activity

Precedes

Optimistic

Most Likely

Pessimistic

A

5

6

7

B

8

8

11

C

A

6

8

11

D

-

9

12

15

E

C

5

6

9

F

D

5

6

7

G

F

2

3

7

H

B

4

4

5

I

H

5

7

8

End

E,G,I

 

 

 

 

 

d.

The partners have decided that shortening the project by two days would be beneficial, as long as it doesn't cost more than about $20,000. They have estimated the daily crashing costs for each activity in thousands, as shown in the following table. Which activities should be crashed, and what further analysis would they probably want to do?

Activity

First Crash

Second Crash

C

$8

$10

D

10

11

E

9

10

F

7

9

G

8

9

H

7

8

I

6

8

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 4 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.