a. How many different paths are there through the network? b. What is the number of the last node in the network? c. What is the difference in hours taken for the two paths when they connect at node 10.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
### Network Analysis Exercise

This exercise requires an examination of a network diagram composed of various nodes and paths. We'll address several questions to understand the network's configuration and workflow.

**Questions:**

a. **How many different paths are there through the network?**  
b. **What is the number of the last node in the network?**  
c. **What is the difference in hours taken for the two paths when they connect at node 10?**  
d. **What is the difference in hours taken for the two paths when they connect at node 12?**  
e. **What is the expected duration of the entire project?**  
f. **What is the critical path?** Separate each node with a dash (–).  
g. **Which is the longest path?** Separate each node with a dash (–).  

---

### Diagram Description

The provided network diagram consists of a series of nodes connected by paths with associated time values. These nodes range numerically, starting from node 1 and ending at node 12. Each path connecting these nodes is marked with a number representing the time (in hours) required to traverse the path.

- **Node 1 connects to Node 2** with a path labeled 4 hours.
- **Node 1 connects to Node 5** with a path labeled 10 hours.
- **Node 2 connects to Node 4** with a path labeled 9 hours.
- **Node 2 connects to Node 5** with a path labeled 8 hours.
- **Node 4 connects to Node 7** with a path labeled 5 hours.
- **Node 5 connects to Node 8** with a path labeled 7 hours.
- **Node 6 connects to Node 9** with a path labeled 4 hours.
- **Node 7 connects to Node 10** with a path labeled 2 hours.
- **Node 8 connects to Node 10** with a path labeled 2 hours.
- **Node 9 connects to Node 11** with a path labeled 6 hours.
- **Node 9 connects to Node 12** with a path labeled 5 hours.
- **Node 10 connects to Node 12** with a path labeled 3 hours.
- **Node 11 connects to Node 12** with a path labeled 6 hours.

This setup allows identification of paths, critical paths, and other network-specific queries relevant
Transcribed Image Text:### Network Analysis Exercise This exercise requires an examination of a network diagram composed of various nodes and paths. We'll address several questions to understand the network's configuration and workflow. **Questions:** a. **How many different paths are there through the network?** b. **What is the number of the last node in the network?** c. **What is the difference in hours taken for the two paths when they connect at node 10?** d. **What is the difference in hours taken for the two paths when they connect at node 12?** e. **What is the expected duration of the entire project?** f. **What is the critical path?** Separate each node with a dash (–). g. **Which is the longest path?** Separate each node with a dash (–). --- ### Diagram Description The provided network diagram consists of a series of nodes connected by paths with associated time values. These nodes range numerically, starting from node 1 and ending at node 12. Each path connecting these nodes is marked with a number representing the time (in hours) required to traverse the path. - **Node 1 connects to Node 2** with a path labeled 4 hours. - **Node 1 connects to Node 5** with a path labeled 10 hours. - **Node 2 connects to Node 4** with a path labeled 9 hours. - **Node 2 connects to Node 5** with a path labeled 8 hours. - **Node 4 connects to Node 7** with a path labeled 5 hours. - **Node 5 connects to Node 8** with a path labeled 7 hours. - **Node 6 connects to Node 9** with a path labeled 4 hours. - **Node 7 connects to Node 10** with a path labeled 2 hours. - **Node 8 connects to Node 10** with a path labeled 2 hours. - **Node 9 connects to Node 11** with a path labeled 6 hours. - **Node 9 connects to Node 12** with a path labeled 5 hours. - **Node 10 connects to Node 12** with a path labeled 3 hours. - **Node 11 connects to Node 12** with a path labeled 6 hours. This setup allows identification of paths, critical paths, and other network-specific queries relevant
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 3 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.