Project Sand Mandala Carrie meticulousiy calculated the eariy and late start and finish times for her latest project and recorded them using different colors of sand on a pristine slab of white marble. She used red for late start and late finish times and green for early start and early finish times. Activity durations and their identifiers were written with black sand. She finished her task and had an opportunity to admire her work only briefiy before a colleague came by and swept most of it away. Sadly, this was before Carrie could record the numbers on a more permanent medium, so now she turns to you to help. Activity Exly Start Early Finish Predecessar Duration Late Start Late Finish 10 B 11 A 15 14 E 11 19 10 DE 24 H F 24 28 K GHJ 36 What is the late start time for activity H? 23 24 17 21

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Project Sand Mandala
Carrie meticulously calculated the early and late start and finish times for her latest project and recorded them using different colors of sand on a pristine slab of white marble.
She used red for late start and late finish times and green for early start and early finish times. Activity durations and their identifiers were written with black sand. She finished
her task and had an opportunity to admire her work only briefiy before a colleague came by and swept most of it away. Sadly, this was before Carrie could record the numbers on
a more permanent medium, so now she turns to you to help.
Activity
Predecessar
Duration
Early Start
Early Finish
Late Start
Late Finish
10
B
7
11
A
15
14
E
B
11
19
B
10
DE
24
H.
F
24
28
K
GHJ
36
What is the late start time for activity H?
23
24
17
21
O0 O C
Transcribed Image Text:Project Sand Mandala Carrie meticulously calculated the early and late start and finish times for her latest project and recorded them using different colors of sand on a pristine slab of white marble. She used red for late start and late finish times and green for early start and early finish times. Activity durations and their identifiers were written with black sand. She finished her task and had an opportunity to admire her work only briefiy before a colleague came by and swept most of it away. Sadly, this was before Carrie could record the numbers on a more permanent medium, so now she turns to you to help. Activity Predecessar Duration Early Start Early Finish Late Start Late Finish 10 B 7 11 A 15 14 E B 11 19 B 10 DE 24 H. F 24 28 K GHJ 36 What is the late start time for activity H? 23 24 17 21 O0 O C
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.