2. Answer the following questions based on the chart. What is the critical path based on 0 float times? b. Which activities have float times? c. Can resource from activity B be used to help activity C? Why? d. Can resource from activity D be used to help activity F? Why?
2. Answer the following questions based on the chart. What is the critical path based on 0 float times? b. Which activities have float times? c. Can resource from activity B be used to help activity C? Why? d. Can resource from activity D be used to help activity F? Why?
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question

Transcribed Image Text:2. Answer the following questions based on the chart.
a. What is the critical path based on 0 float times?
b.
Which activities have float times?
c. Can resource from activity B be used to help activity
C? Why?
d. Can resource from activity D be used to help activity
F? Why?

Transcribed Image Text:Below is a project listed in a table with:
activity,
predecessor, and
duration.
Activity
A
B
с
D
E
F
G
H
Predecessor
none
A
A
с
B
B
D, E, F
G
Fill in the chart below by filling in:
early start (ES),
early finish (EF),
☐late start (LS),
A
late finish (LF),
duration (D), and
float (F).
Then, answer the questions based on the chart.
Hint: You can use the Word tools to fill in the chart, or you can draw the chart by hand,
then photograph or scan your graph to submit it.
1. Fill in the chart below.
B
Duration (weeks)
C
5
3
8
13
7
9
10
7
-
D
E
F
G
H
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.