The project manager for a construction project discovers that the local city council will vote on a zoning change that would open up a new neighborhood to commercial building. She contacts other construction companies in the area that would benefit from the change to ask them to attend the council meeting in order to convince the city council to vote for the change. A “Yes” vote will benefit all of the companies. This is an example of which risk response strategy? A. Share B. Mitigate C. Exploit D. Enhance You are interviewing new project managers for your company. One of the candidates claims to be a PMP Certified project manager, but you discover that she has never taken the PMP exam. What is the BEST way to handle this situation? A. Do nothing B. Report the person to your manager C. Report the person to PMI D. Call the police
The project manager for a construction project discovers that the local city
council will vote on a zoning change that would open up a new neighborhood
to commercial building. She contacts other construction companies in the
area that would benefit from the change to ask them to attend the council
meeting in order to convince the city council to vote for the change. A
“Yes” vote will benefit all of the companies. This is an example of which risk
response strategy?
A. Share
B. Mitigate
C. Exploit
D. Enhance
You are interviewing new project managers for your company. One of the
candidates claims to be a PMP Certified project manager, but you discover
that she has never taken the PMP exam. What is the BEST way to handle this
situation?
A. Do nothing
B. Report the person to your manager
C. Report the person to PMI
D. Call the police