The demand for subassembly S is 120 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T requires 1 unit of V, 2 units of W, and 2 units of X. Finally, each unit of U requires 1 unit of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 1 week to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 2 weeks to make Z. Click the icon to view the product structure and the time-phased product structure. In addition to 120 units of S, there is also a demand for 30 units of U, which is a component of S. The 30 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used). Week Item S 1 2 3 4 5 6 7 Lead Time (weeks) Gross req 0 0 0 0 0 0 120 Order release 0 0 0 0 120 0 0 2 T Gross req 0 0 0 0 120 0 0 Order release 0 0 0 120 0 0 0 1 U Gross req Order release 2

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question
The demand for subassembly S is 120 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T requires 1 unit of V, 2 units of W, and 2 units of X. Finally, each unit
of U requires 1 unit of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 1 week to make V, 3 weeks to make W, 1
week to make X, 2 weeks to make Y, and 2 weeks to make Z.
Click the icon to view the product structure and the time-phased product structure.
In addition to 120 units of S, there is also a demand for 30 units of U, which is a component of S. The 30 units of U are needed for maintenance purposes. These units are needed in week
6. Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used).
Week
Item
S
1
2
3
4
5
6
7
Lead Time
(weeks)
Gross req
0
0
0
0
0
0
120
Order release
0
0
0
0
120
0
0
2
T
Gross req
0
0
0
0
120
0
0
Order release
0
0
0
120
0
0
0
1
U
Gross req
Order release
2
Transcribed Image Text:The demand for subassembly S is 120 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T requires 1 unit of V, 2 units of W, and 2 units of X. Finally, each unit of U requires 1 unit of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 1 week to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 2 weeks to make Z. Click the icon to view the product structure and the time-phased product structure. In addition to 120 units of S, there is also a demand for 30 units of U, which is a component of S. The 30 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used). Week Item S 1 2 3 4 5 6 7 Lead Time (weeks) Gross req 0 0 0 0 0 0 120 Order release 0 0 0 0 120 0 0 2 T Gross req 0 0 0 0 120 0 0 Order release 0 0 0 120 0 0 0 1 U Gross req Order release 2
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,