Suppose you are analyzing processing times for a machining operation. In your analysis, you found Cp = 2.1 and Cpk = 1.5. Given this information, which of the following sigma levels is the highest that you could claim your process is capable of meeting? 2 sigma 3 sigma 4 sigma 5 sigma 6 sigma

icon
Related questions
Question
Suppose you are analyzing processing times for a machining operation. In your analysis, you found Cp = 2.1 and Cpk = 1.5. Given this information, which of the following
sigma levels is the highest that you could claim your process is capable of meeting?
2 sigma
3 sigma
4 sigma
5 sigma
6 sigma
Transcribed Image Text:Suppose you are analyzing processing times for a machining operation. In your analysis, you found Cp = 2.1 and Cpk = 1.5. Given this information, which of the following sigma levels is the highest that you could claim your process is capable of meeting? 2 sigma 3 sigma 4 sigma 5 sigma 6 sigma
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer