Question 2: Mr. K’s is a very popular hair salon. It offers high-quality hairstyling and physical relaxation services at a reasonable price, so it always has unlimited demand. The service process includes five activities that are conducted in the sequence described next (the time required for each activity is shown in parentheses): ● Activity 1: Welcome a guest and offer homemade herb tea (13 minutes). ● Activity 2: Wash and condition hair (13 minutes). ● Activity 3: Neck, shoulder, and back stress-release massage (13 minutes). ● Activity 4: Design the hairstyle and do the hair (28 minutes). ● Activity 5: Check out the guest (12 minutes). Three servers (S1, S2, and S3) offer the services in a worker-paced line. The assignment of tasks to servers is the following: S1 does Activity 1, S2 does activities 2 and 3, and S3 does activities 4 and 5.
Question 2: Mr. K’s is a very popular hair salon. It offers high-quality hairstyling and physical relaxation services at a reasonable price, so it always has unlimited demand. The service process includes five activities that are conducted in the sequence described next (the time required for each activity is shown in parentheses):
● Activity 1: Welcome a guest and offer homemade herb tea (13 minutes).
● Activity 2: Wash and condition hair (13 minutes).
● Activity 3: Neck, shoulder, and back stress-release massage (13 minutes).
● Activity 4: Design the hairstyle and do the hair (28 minutes).
● Activity 5: Check out the guest (12 minutes).
Three servers (S1, S2, and S3) offer the services in a worker-paced line. The assignment of tasks to servers is the following: S1 does Activity 1, S2 does activities 2 and 3, and S3 does activities 4 and 5.