Question 1 Given the project information in the Table Q1 below. Table Q1 Duration (Weeks) Cost (Dollars) Task Follows Task(s) Normal Crash Normal Crash (Start) 3 $500 $600 (Start) 1 400 450 А, В 5 3 600 750 B 5 4. 550 640 С, D 4 400 550 (a) Draw an arrow network diagram (3 mar (b) Show all possible paths and identify the critical path and (5 mar duration (c) Identify the task(s) you would crash and the incremental cost to reduce project duration one week. a second week: and a third week (17 mar
Q: Toyota’s history goes back to 1897 when Sakichi Toyoda (Sakichi) diversified into the handloom…
A: As per the given case, the company is facing the problem of the mass departure of young male…
Q: Examine Food supply chain approaches and procurement strategies that can enhance organisational…
A: Food supply chains are as varied as the organizations that are involved in them, from multi-national…
Q: Below is data of lobster sales volume from a seafood company. We are using exponential smoothing (α…
A: Forecasting is the process of estimating future demands and sales using the previous years of…
Q: PDM stand for; O a. Product development methodology O b. Project development measure O c. Precedence…
A: As per our guidelines, we are supposed to answer only the first question when multiple questions are…
Q: When integrating suppliers, what are the best practices to follow?
A: Suppliers are very important and has a great role in firms sucess because they supply the scarce…
Q: Why is the police called as the initiator of the Criminal Justice System?
A: Police are the part of administration system which helps to maintain a specified decorum in the…
Q: Technology that may be utilised to enhance project communication can be described in detail. As…
A: Communication is the most important thing in any project because it connects each and every unit in…
Q: ther option is wrong. make sure both the questions are answered else i will give negative. please…
A: Through the implementation of change, the project provides excellent opportunities for businesses…
Q: To what extent do you feel it is critical that management and personnel challenges be included in…
A: Business plan refers to thinking in advance as what ,when and by whom what is to be done in future.
Q: Do you agree that over the years Cricket and other sports has transformed in to a global industry?…
A: Global industry refers to the industries which operate there activities in more that one country and…
Q: The following table shows estimates of activity times (in weeks) for a project: Optimistic Most…
A: The critical path is the path in the project network that takes the highest time to complete the…
Q: What is the number of customers waiting in the queue on average?
A: Arrival Rate (Lambda) = 12 per hour Average Service Rate (Mu) = 60/4 = 15 per hour
Q: 5. An operation has a 10 percent scrap rate. As a result, 72 pieces per hour are produced. What is…
A: An operation has a 10 percent scrap rate. As a result, 72 pieces per hour are produced. What is the…
Q: What is the significance of aligning the capabilities of the process to the needs of the product?
A: Aligning by capability provides a cooperative organization. It enables working as an ecosystem to…
Q: 1. The profit payoff table below showing profit for a decision problem with four states of nature…
A: Note: As you have posted a multipart question, the first question with 3 subparts is solved. Please…
Q: The use of milestones assists in the tracking of project progress. In many of the client…
A: A milestone is a pointer in a project that indicates a variation or stage in expansion. Milestones…
Q: Do you agree that over the years Cricket and other sports has transformed in to a global industry?…
A: Global industry refers to the industry which does not have any fixed place of its operations and it…
Q: What is the purpose of the Medium Term Scheduling tool?
A: Medium-term scheduling : Medium-term scheduling is a piece of swapping. It removes the processes…
Q: The "5 Why" technique is useful in identifying.. Six Sigma projects that should be prioritized.…
A: The 5 why technique is used to find out the root cause of a problem in order to remove it from its…
Q: What do you think? How do organizations manage customer service and product quality?
A: The product quality refers to the standard of products which a firm will deliver to its customers.…
Q: QUESTION 13 Before he died, Steve Jobs asked the employees to consider the demands of their fellow…
A: Internal stakeholders are the stakeholder which are present within the internal organisation and are…
Q: Tell us why it's so critical to integrate product requirements with production procedures.
A: Product requirement refers to the quality of a output which a firm wants from its production units…
Q: Time Task Precedence Tasks Task (sec (s ЕЗ D6 D7 D8 J2 D9 J3 C1 K4, K9 K9, J1 B3 B5 J2 B7 25
A: Calculate the cycle time based on the goal is to produce 1000 bicycles per standard 40hour week…
Q: Altug's Coffee Shop decides to install an automatic coffee vending machine outside one of its stores…
A: Given data; Cost 3.5 $/cup λ Arrival rate 30 per hr Service rate 1.5…
Q: Aggregate demand for a product family is given in the table below for the 4 quarters of 2021.…
A: Aggregate plan helps the company to procure in an optimal way while saving as much money as…
Q: 2. A project for improving a billing process has the following precedence relationships and activity…
A: The project network is the visual representation of the project activities and their duration to…
Q: Consider the following forecasting model: x^t,t+1=axt+(1-a)x^t-1,t If a decreases from 0.5 to 0.2,…
A: The given question is about exponential smoothing.
Q: Maggle Moylan Motorcycle Corp. uses kanbans to support its transmission assembly line. Determine the…
A: Note: - Since the exact question that has to be answered is not specified we will answer the first…
Q: pen-and-paper performance management system
A: Performance management system is a technique used for tracking the performance of the employees. It…
Q: 4. Evaluate the decision tree as shown in below figure. $30,000 60% $120,000 50% 40% $200,000 10%…
A: The expected pay off at node C= Sum of (probability*respective payoff)…
Q: What are the major causes of small-business failure? Do these causes also apply to larger…
A: It is becoming really competitive to setup a business in the present day scenario as lot of…
Q: what is the difference between raw materials and feedstock? give examples
A: Definitions: Raw materials: - Raw materials are the general component terms that consist of all the…
Q: The annual demand, ordering cost, and the inventory carrying cost rate for a certain item are D =…
A: Find the Given details below: Given details: Annual Demand (D) 960 Units Ordering cost (S)…
Q: Apple, Inc. launched its first iPhone on January 9, 2007. As of 2021, iPhone has accounted for more…
A: An innovation process allows to add value to a business to increase profit. International strategy…
Q: A certain piece of production equipment is used to produce various components for an assembled…
A: Given data: Batch size (EOQ) = 150 units Demand for each product (D)= 2500 units Production…
Q: . Describe the price–quality relationship of Food Network’s programming and its cookware products at…
A: Entrepreneurs have referred to purchaser demands for specific food sources that they have seen…
Q: a) The cycle time for the production of a PDA = seconds (round your response to two decimal places).…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: Using M-tech ni Lue
A: Linear programming is a mathematical technique that is also used in operations management…
Q: A paper factory produces 70,000 paper each week. The equipment used costs $10,000 and will remain…
A: Productivity is a measure of performance that compares the goods and services produced (output) with…
Q: of the following categories would most likely NOT use an employee labor dollars to determine its…
A: Attacking another person or organization's information system is known as a "cyberattack," and it is…
Q: The following table shows estimates of activity times (in weeks) for a project: Optimistic Most…
A: The critical path is the path that takes the longest time to complete the whole project…
Q: The company's sales history (in thousands of units) is shown in the table below. Use exponential…
A: Concept and formulas used: FIT = Forcast Including Trend FIT = Ft + Tt Ft = FITt-1 + a…
Q: If 25 units of the end item are to be assembled, how many units of component B are needed?
A: The data mentioned in the given question is shown below in the form of a chart for better…
Q: のinそ=5 Sito 2.
A: Linear programming is a mathematical technique that is also used in operations management…
Q: (a) What reorder point provides an 80 percent service level? (b) What reorder point provides a 90…
A: Reorder point is a level up to which the stock reaches, it needs to be replenished instantly. No…
Q: hat is production and management system in industrial engineering?
A: Production management : production management, likewise called operations management, planning and…
Q: Do you believe that breaking down projects into tiny, achievable tasks is an essential aspect of…
A: Project management refers to proper planning and controlling the project activities in an standard…
Q: What is the difference between Capitalist economy and Socialist economy? Give examples in this…
A: Socialist economy is an economy in which all decisions are taken by government as what to…
Q: Identify and critically discuss any THREE drawbacks/disadvantages of the smart factory (max 200).
A: A smart factory (also known as the industrial internet of things) refers to a production facility…
Q: All contemporary organisations operating in an uncertain economic climate, need to know how to…
A: given, All contemporary organisations operating in an uncertain economic climate, need to know how…
Step by step
Solved in 3 steps with 1 images
- Q1 ) Scenarios of a project activities (tables given below) and their required times to be completed in addition to their predecessors for developing a ‘Website’: Activity Description Duration (weeks) Preceding Activities A Determine user needs 8 -- B Review s/w and languages 4 -- C Purchase software 10 -- D Design format and style 10 B E Write programs 6 A F Review outcome product with user 12 C G Make revisions 4 C H Select server site 8 E I Install on server 14 D,F J Test 8 G,H,I Draw the path. Calculate the early finishing time (forwards calculations) Highlight the total time to complete the project (days) Calculate the late finishing time (backwards calculations) Calculate the slack time of the non-critical path activities Identify the critical path (highlight critical path activities) what would happen if activity D revised to take 14 instead of 10 days?Q6. Following are the activities of a Project, please consider them for answering the questions below: Duration Activity Predecessor(s) (days) 4 В A B 6 C, D С. D E, F E 5 G D 4 I 6. J Н. I 3 K J 3 a) Draw Gantt chart for the above table b) Draw Labeled Network Diagram and high light critical path. c) Calculate total duration of the project d) Make a list of all Critical Activities e) Make a list of all Non Critical Activities f) Find Float/ Slack for Each Activity.Question 2 Table 3 gives time estimates in weeks for each activity (Durations are Time Expected obtained using PERT) 1 Order review 2 Order vendor parts 3 Produce standard parts 4 Design custom parts 5 Software development 6 Manufacture custom Activity 7 8 parts Assemble Test Duration 5 15 20 13 18 10 10 5 Preceded 1 1 1 4 2,3,6 2,5 Assuming that you have been engaged to programme the project activities indicated in Table 3 and Figure A8.1B (Air Control Project: Time Plan without Resources), USE CCPM (Critical Chain Project Management) to ESTIMATE the project duration by showing each and every stage of your programming process (indicate technical dependency with resources imposed).
- Q4- For the activities shown in the table using PERT, draws the network diagram and determine the probability that the project is completed within 70 days. Activity T. 17 6. T, 47 A 29 B 12 24 C 16 19 28 D 13 16 19 E 5 14 F 81. Draw the bar (Gantt) chart 2. Determine the project total duration Activity Duration Predec. Description Excavate Stage I Order & Deliver Steel Work Formwork Stage I Excavate Stage II Concrete Stage I Formwork Stage II Backfill Stagel Concrete Stage II A 4 B 7 4 A D 5 A E 8 C F С, D G 3 E Е, F В, Н H 8 Erect Steel WWork 10 J Backfill Stage II G, HActivity Predecessor Activities Normal Crashed Duration (Days) Cost ($) Duration Cost ($) KA - 5 2000 3 5600 LB - 7 3000 4 7800 MC A 10 4000 7 6100 ND AB 11 5000 8 8000 PE B 6 2400 4 3600 RF C 8 3000 6 5100 QG C,D,E 4 4200 1 3000 SH E,G 5 5500 3 2500 What is the ES for Activity G and and LS for activity F?
- CASE - CAPACITY BUILDING PROJECT AIMS TO INCREASE YOUTH INVOLVEMENT IN SUSTAINABLE DEVELOPMENT Basseterre, St. Kitts, April 29, 2021 (SKNIS): St. Kitts and Nevis Youth Ambassador Corps officially launched a new project on Wednesday (April 28, 2021) designed to increase the contributions of young people to the sustainable development of the twin-island Federation. The initiative, dubbed the Youth Capacity Building Small Grants Project on Youth in Sustainable Development, will build the capacity and practical skills of young people to design, implement, and monitor interventions relevant to the social, economic, and sustainable development of youth and their communities. The project is geared towards members of youth groups specifically. It is spearheaded by the national youth ambassador corps in collaboration with the GEF Small Grants Programme (SGP), and the Departments of Youth in St. Kitts, and Nevis. The Small Grants Project is funding the initiative to the tune of US$49,970.00. SGP…CASE - CAPACITY BUILDING PROJECT AIMS TO INCREASE YOUTH INVOLVEMENT IN SUSTAINABLE DEVELOPMENT Basseterre, St. Kitts, April 29, 2021 (SKNIS): St. Kitts and Nevis Youth Ambassador Corps officially launched a new project on Wednesday (April 28, 2021) designed to increase the contributions of young people to the sustainable development of the twin-island Federation. The initiative, dubbed the Youth Capacity Building Small Grants Project on Youth in Sustainable Development, will build the capacity and practical skills of young people to design, implement, and monitor interventions relevant to the social, economic, and sustainable development of youth and their communities. The project is geared towards members of youth groups specifically. It is spearheaded by the national youth ambassador corps in collaboration with the GEF Small Grants Programme (SGP), and the Departments of Youth in St. Kitts, and Nevis. The Small Grants Project is funding the initiative to the tune of US$49,970.00. SGP…CASE - CAPACITY BUILDING PROJECT AIMS TO INCREASE YOUTH INVOLVEMENT IN SUSTAINABLE DEVELOPMENT Basseterre, St. Kitts, April 29, 2021 (SKNIS): St. Kitts and Nevis Youth Ambassador Corps officially launched a new project on Wednesday (April 28, 2021) designed to increase the contributions of young people to the sustainable development of the twin-island Federation. The initiative, dubbed the Youth Capacity Building Small Grants Project on Youth in Sustainable Development, will build the capacity and practical skills of young people to design, implement, and monitor interventions relevant to the social, economic, and sustainable development of youth and their communities. The project is geared towards members of youth groups specifically. It is spearheaded by the national youth ambassador corps in collaboration with the GEF Small Grants Programme (SGP), and the Departments of Youth in St. Kitts, and Nevis. The Small Grants Project is funding the initiative to the tune of US$49,970.00. SGP…
- CASE - CAPACITY BUILDING PROJECT AIMS TO INCREASE YOUTH INVOLVEMENT IN SUSTAINABLE DEVELOPMENT Basseterre, St. Kitts, April 29, 2021 (SKNIS): St. Kitts and Nevis Youth Ambassador Corps officially launched a new project on Wednesday (April 28, 2021) designed to increase the contributions of young people to the sustainable development of the twin-island Federation. The initiative, dubbed the Youth Capacity Building Small Grants Project on Youth in Sustainable Development, will build the capacity and practical skills of young people to design, implement, and monitor interventions relevant to the social, economic, and sustainable development of youth and their communities. The project is geared towards members of youth groups specifically. It is spearheaded by the national youth ambassador corps in collaboration with the GEF Small Grants Programme (SGP), and the Departments of Youth in St. Kitts, and Nevis. The Small Grants Project is funding the initiative to the tune of US$49,970.00. SGP…CASE - CAPACITY BUILDING PROJECT AIMS TO INCREASE YOUTH INVOLVEMENT IN SUSTAINABLE DEVELOPMENT Basseterre, St. Kitts, April 29, 2021 (SKNIS): St. Kitts and Nevis Youth Ambassador Corps officially launched a new project on Wednesday (April 28, 2021) designed to increase the contributions of young people to the sustainable development of the twin-island Federation. The initiative, dubbed the Youth Capacity Building Small Grants Project on Youth in Sustainable Development, will build the capacity and practical skills of young people to design, implement, and monitor interventions relevant to the social, economic, and sustainable development of youth and their communities. The project is geared towards members of youth groups specifically. It is spearheaded by the national youth ambassador corps in collaboration with the GEF Small Grants Programme (SGP), and the Departments of Youth in St. Kitts, and Nevis. The Small Grants Project is funding the initiative to the tune of US$49,970.00. SGP…CASE - CAPACITY BUILDING PROJECT AIMS TO INCREASE YOUTH INVOLVEMENT IN SUSTAINABLE DEVELOPMENT Basseterre, St. Kitts, April 29, 2021 (SKNIS): St. Kitts and Nevis Youth Ambassador Corps officially launched a new project on Wednesday (April 28, 2021) designed to increase the contributions of young people to the sustainable development of the twin-island Federation. The initiative, dubbed the Youth Capacity Building Small Grants Project on Youth in Sustainable Development, will build the capacity and practical skills of young people to design, implement, and monitor interventions relevant to the social, economic, and sustainable development of youth and their communities. The project is geared towards members of youth groups specifically. It is spearheaded by the national youth ambassador corps in collaboration with the GEF Small Grants Programme (SGP), and the Departments of Youth in St. Kitts, and Nevis. The Small Grants Project is funding the initiative to the tune of US$49,970.00. SGP…