Q2: For the activities shown in the table below, it is required to reduce the total duration of the project four days by using crash program and network diagram, If you knew that indirect costs is 150 S/day and the delay fine is 100 $/day after the 14th day. Find new cost after crashing the project four days? Activity Preceding Normal Program Crash Program activity Duration (days) Direct Cost (S) Duration (days) Direct Cost (S) A 5 600 3 950 B - 4 200 3 500 C A 5 300 4 500 D A 2 600 1 615 E B 6 900 5 1025 800 3 F C 4 700 450 G D 4 400 3 700 3 700 1400 3 H E 2 600 I F,G,H 4 5000 Σ (40 px) good luck) Q1: By using the PERT technique, the durations of the activities were calculated as shown in the table below, Draw an activity network for project by using Activity On Node (AON) method and find: 1. The project's total duration and date of completion and CP (assume the project start date is the 1st of June 2025)? 2. The overall variance of the project? 3. The probability of completing the project in 30 days? 4. The probability of completing the project in 22th of June 2025? 5. With a probability of 75%, what is the expected duration and date for completing the project? Activity Preceding activity K Optimistic duration (day) 4 Most likely duration (day) Pessimistic duration (day) 5 12 L 5 11 17 M K 5 8 11 N K 3 4 11 0 L 2 3 10 P M,N 4 7 10 Q N 3 7 17 R N,O 6 9 18 S P,Q,R 1 3 5 10

Engineering Fundamentals: An Introduction to Engineering (MindTap Course List)
5th Edition
ISBN:9781305084766
Author:Saeed Moaveni
Publisher:Saeed Moaveni
Chapter20: Engineering Economics
Section: Chapter Questions
Problem 19P
icon
Related questions
Question
Q2: For the activities shown in the table below, it is required to reduce the total duration of the
project four days by using crash program and network diagram, If you knew that indirect costs is
150 S/day and the delay fine is 100 $/day after the 14th day. Find new cost after crashing the
project four days?
Activity
Preceding
Normal Program
Crash Program
activity
Duration (days) Direct Cost (S) Duration (days) Direct Cost (S)
A
5
600
3
950
B
-
4
200
3
500
C
A
5
300
4
500
D
A
2
600
1
615
E
B
6
900
5
1025
800
3
F
C
4
700
450
G
D
4
400
3
700
3
700
1400
3
H
E
2
600
I
F,G,H
4
5000
Σ
(40 px)
good luck)
Transcribed Image Text:Q2: For the activities shown in the table below, it is required to reduce the total duration of the project four days by using crash program and network diagram, If you knew that indirect costs is 150 S/day and the delay fine is 100 $/day after the 14th day. Find new cost after crashing the project four days? Activity Preceding Normal Program Crash Program activity Duration (days) Direct Cost (S) Duration (days) Direct Cost (S) A 5 600 3 950 B - 4 200 3 500 C A 5 300 4 500 D A 2 600 1 615 E B 6 900 5 1025 800 3 F C 4 700 450 G D 4 400 3 700 3 700 1400 3 H E 2 600 I F,G,H 4 5000 Σ (40 px) good luck)
Q1: By using the PERT technique, the durations of the activities were calculated as shown in the
table below, Draw an activity network for project by using Activity On Node (AON) method and
find:
1. The project's total duration and date of completion and CP (assume the project start
date is the 1st of June 2025)?
2.
The overall variance of the project?
3.
The probability of completing the project in 30 days?
4.
The probability of completing the project in 22th of June 2025?
5.
With a probability of 75%, what is the expected duration and date for completing the
project?
Activity
Preceding
activity
K
Optimistic
duration (day)
4
Most likely
duration (day)
Pessimistic
duration (day)
5
12
L
5
11
17
M
K
5
8
11
N
K
3
4
11
0
L
2
3
10
P
M,N
4
7
10
Q
N
3
7
17
R
N,O
6
9
18
S
P,Q,R
1
3
5
10
Transcribed Image Text:Q1: By using the PERT technique, the durations of the activities were calculated as shown in the table below, Draw an activity network for project by using Activity On Node (AON) method and find: 1. The project's total duration and date of completion and CP (assume the project start date is the 1st of June 2025)? 2. The overall variance of the project? 3. The probability of completing the project in 30 days? 4. The probability of completing the project in 22th of June 2025? 5. With a probability of 75%, what is the expected duration and date for completing the project? Activity Preceding activity K Optimistic duration (day) 4 Most likely duration (day) Pessimistic duration (day) 5 12 L 5 11 17 M K 5 8 11 N K 3 4 11 0 L 2 3 10 P M,N 4 7 10 Q N 3 7 17 R N,O 6 9 18 S P,Q,R 1 3 5 10
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Recommended textbooks for you
Engineering Fundamentals: An Introduction to Engi…
Engineering Fundamentals: An Introduction to Engi…
Civil Engineering
ISBN:
9781305084766
Author:
Saeed Moaveni
Publisher:
Cengage Learning
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Residential Construction Academy: House Wiring (M…
Residential Construction Academy: House Wiring (M…
Civil Engineering
ISBN:
9781285852225
Author:
Gregory W Fletcher
Publisher:
Cengage Learning
Solid Waste Engineering
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,