[Project Management] Because a housing project is running late, the developer will need to complete and deliver the houses as quickly as possible. You and your management team are responsible for mitigating the situation by including a time-cost trade-off analysis into the project. You will need to include the following: Normal Crash Activity Prior Days cost, RM Days cost, RM 7,000 7,000 8,000 8,000 B 14 6,000 12 11,000 B. 18 5,000 11 8,500 C,D 12 8,000 12 8,000 F 20 6,000 16 12,000 7,000 7,000 11 11,000 7 15,000 G, H 10 15,000 7 21,000 I,F 9,000 9,000

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
[Project Management] Because a housing project is running late, the developer will need to
complete and deliver the houses as quickly as possible. You and your management team are
responsible for mitigating the situation by including a time-cost trade-off analysis into the
project. You will need to include the following:
Normal
crash
Activity
Prior
Days
cost, RM
Days
cost, RM
A
7,000
7,000
B
A
8,000
9
8,000
B
14
6,000
12
11,000
D
B
18
5,000
11
8,500
E
C,D
12
8,000
12
8,000
E
20
6,000
16
12,000
E
7,000
7,000
E
11
11,000
7
15,000
G, H
10
15,000
21,000
7
I, F
6
9,000
6
9,000
Construct a network diagram (PDM), including activity early start, late start, early finish,
late finish and float.
Transcribed Image Text:[Project Management] Because a housing project is running late, the developer will need to complete and deliver the houses as quickly as possible. You and your management team are responsible for mitigating the situation by including a time-cost trade-off analysis into the project. You will need to include the following: Normal crash Activity Prior Days cost, RM Days cost, RM A 7,000 7,000 B A 8,000 9 8,000 B 14 6,000 12 11,000 D B 18 5,000 11 8,500 E C,D 12 8,000 12 8,000 E 20 6,000 16 12,000 E 7,000 7,000 E 11 11,000 7 15,000 G, H 10 15,000 21,000 7 I, F 6 9,000 6 9,000 Construct a network diagram (PDM), including activity early start, late start, early finish, late finish and float.
Expert Solution
steps

Step by step

Solved in 4 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.