Network Diagrams Exercise 1. For each task build the relevant network diagram 2. Add the task durations for each activity 3. Conduct a forward and backward pass (calculate ES EF, LS, LF) 4. Calculate the available float for each task 5. Identify the critical path for each network

Foundations of Business (MindTap Course List)
6th Edition
ISBN:9781337386920
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Chapter11: Building Customer Relationships Through Effective Marketing
Section11.10A: Consumer Buying Behavior
Problem 2CC
icon
Related questions
Question

Network Diagrams Exercise
1. For each task build the relevant network diagram
2. Add the task durations for each activity
3. Conduct a forward and backward pass (calculate ES EF, LS, LF)
4. Calculate the available float for each task
5. Identify the critical path for each network

Task 1
Activity
Precedence
Time (days)
A
Start
3
A
A
D
B
4
B
B
G
C,D
3
H.
E
E
J
F,E
6.
K
4
L
G,H
4
M
1,J
4
N
J
3
K,L,M,N
1
Transcribed Image Text:Task 1 Activity Precedence Time (days) A Start 3 A A D B 4 B B G C,D 3 H. E E J F,E 6. K 4 L G,H 4 M 1,J 4 N J 3 K,L,M,N 1
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Foundations of Business (MindTap Course List)
Foundations of Business (MindTap Course List)
Marketing
ISBN:
9781337386920
Author:
William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:
Cengage Learning
Foundations of Business - Standalone book (MindTa…
Foundations of Business - Standalone book (MindTa…
Marketing
ISBN:
9781285193946
Author:
William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:
Cengage Learning
Management, Loose-Leaf Version
Management, Loose-Leaf Version
Management
ISBN:
9781305969308
Author:
Richard L. Daft
Publisher:
South-Western College Pub