Markland Manufacturing intends to increase capacity by overcoming a bottleneck operation by adding new equipment. Two vendors have presented proposals. The fixed costs for proposal A are $50,000, and for proposal B, $70,000. The variable cost for A is $12.00, and for B, $10.00. The revenue generated by each unit is $20.00. Using the data in Problem a) What is the break-even point in dollars for proposal A if you add $10,000 installation to the fixed cost? b) What is the break-even point in dollars for proposal B if you add $10,000 installation to the fixed cost?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
S7.18
Markland Manufacturing intends to increase capacity by overcoming a bottleneck operation by adding
new equipment. Two vendors have presented proposals. The fixed costs for proposal A are $50,000, and
for proposal B, $70,000. The variable cost for A is $12.00, and for B, $10.00. The revenue generated by
each unit is $20.00.
Using the data in Problem
a) What is the break-even point in dollars for proposal A if you add $10,000 installation to the fixed cost?
b) What is the break-even point in dollars for proposal B if you add $10,000 installation to the fixed
cost?
Transcribed Image Text:S7.18 Markland Manufacturing intends to increase capacity by overcoming a bottleneck operation by adding new equipment. Two vendors have presented proposals. The fixed costs for proposal A are $50,000, and for proposal B, $70,000. The variable cost for A is $12.00, and for B, $10.00. The revenue generated by each unit is $20.00. Using the data in Problem a) What is the break-even point in dollars for proposal A if you add $10,000 installation to the fixed cost? b) What is the break-even point in dollars for proposal B if you add $10,000 installation to the fixed cost?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.