Make Sure That this is correct, because the answer in mannings equation is wrong. Detailed Solution for Open Channel Design (Rectangular Section) We will design a rectangular open channel with the given specifications and provide detailed calculations for discharge, cost estimate, and structural analysis. Given Data: ⚫Discharge (Q: 18 m³/s • Bed Slope (5): S- (bed slope) Manning's Roughness Coefficient (n): -0.015 Channel Shape: Rectangular section ⚫Efficiency Goal: Minimize friction loss by designing a hydraulically efficient section Now, substitute this into Manning's equation: 9-() Substitute values: 2/3 8/2 18 (2d) *-*)()()" 0.015 Now, let's simplify this expression step by step. Step 2: Simplifying and Solving for d 1500 Step 1: Hydraulic Design of the Rectangular Channel Manning's Equation for Open Channel Flow: Manning's equation describes the flow in an open channel 1 0.015 First, simplify the term () Now, substitute this into the equation: -(0)-()" (金) 1500 2/3 18 0.015 x 2 x 22/3 x 1500 1500, V1500 1 38.72983 -0.0258 Where: ⚫ Q = Discharge (m³/s) ⚫n Manning's roughness coefficient ⚫ A = Cross-sectional area of flow (m²) ⚫R Hydraulic radius (m) ⚫ S = Slope of the bed ⚫ A is calculated as A =Bxd, where B is the bottom width and d is the depth of the channel. Since we are designing the most efficient rectangular section, we can assume the bottom width B - 2d, where d is the depth. Hydraulic Radius R: The hydraulic radius R is defined as: Calculate the constant ()/2 Now the equation becomes: Simplify further: where: R- ⚫P is the wetted perimeter (m). For a rectangular channel, the wetted perimeter is: Thus: 18- x2dx 0.015 f/3 x 0.0258 22/3 18-> 2d²x²/3 0.015 x 22/3 x 0.0258 To simplify this equation, we'll use the value 22/3 1.587, so: Now, compute the constants: 20/3 0.015 x 1.587 x 0.0258 0.015 x 1.587 0.023805 P B+2d 2d +2d-4d 0.023805 x 0.0258 0.0006137 Thus, the equation becomes: 2d² d P 4d 18- 2/3 0.0006137 Solve for d Now, solve for d 18 x 0.0006137 2 -0.0055344 d=(0.0055344) 0.4775m So, the flow depth d is approximately 0.48 meters. Width of the Channel B: Since B-2d, the bottom width is B-2x 0.48 0.96 m Step 3: Cross-sectional Area and Hydraulic Radius Now we can calculate the cross-sectional area (A) and hydraulic radius (R): A-Bxd-0.96 x 0.48 -0.4608 m² d 0.48 R- 2 -0.24 m Step 4: Cost Estimate To estimate the cost of the channel, we need to consider the following: 1. Excavation Cost: The volume of soil removed to create the channel is approximately A x Length of the Channel. For simplicity, we'll assume a unit length of 1 meter. Volume to excavate: 0.4608 m2 x 1m 0.4608 m³ Cost per cubic meter of excavation (assuming 50 USD/m³ Excavation cost -0.4608 x 50 - 23.04 USD 2. Concrete Lining Cost (if needed): Assuming the channel is lined with concrete and the cost is 150 USD/m². Surface area of the channel: P x Length - 4 x 0.48 - 1.92 m² • Concrete lining cost Lining cost 1.92 x 150-288 USD Step 5: Structural Analysis 1. Shear Stress at the Bed: The shear stress at the bed r can be calculated using: T-pgSR where: • p = density of water 1000 kg/m³ ⚫ g = acceleration due to gravity 9.81 m/s² ⚫ S = slope 1500 ⚫ R = hydraulic radius 0.24 m 1 T1000 × 9.81 × x 0.24 1.57 Pa 1500 This shear stress is within acceptable limits for a concrete-lined channel.

Fundamentals of Geotechnical Engineering (MindTap Course List)
5th Edition
ISBN:9781305635180
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Braja M. Das, Nagaratnam Sivakugan
Chapter7: Seepage
Section: Chapter Questions
Problem 7.7CTP
icon
Related questions
Question

Make Sure the attached pic is correct, because the answer in mannings equation is wrong. 

Can you design a (Open Channel):

-Most Efficient Section (Rectangular Shape)

-Cost Estimate

-Structural Analysis

Design Requirements:

Bed Slope= 1:1500

Manning's (n)= 0.015

 

Discharge:

Q= 18 m^3/s

Make Sure That this is correct, because the answer in mannings equation is wrong.
Detailed Solution for Open Channel Design (Rectangular Section)
We will design a rectangular open channel with the given specifications and provide detailed calculations
for discharge, cost estimate, and structural analysis.
Given Data:
⚫Discharge (Q: 18 m³/s
• Bed Slope (5): S- (bed slope)
Manning's Roughness Coefficient (n): -0.015
Channel Shape: Rectangular section
⚫Efficiency Goal: Minimize friction loss by designing a hydraulically efficient section
Now, substitute this into Manning's equation:
9-()
Substitute values:
2/3
8/2
18
(2d)
*-*)()()"
0.015
Now, let's simplify this expression step by step.
Step 2: Simplifying and Solving for d
1500
Step 1: Hydraulic Design of the Rectangular Channel
Manning's Equation for Open Channel Flow:
Manning's equation describes the flow in an open channel
1
0.015
First, simplify the term ()
Now, substitute this into the equation:
-(0)-()"
(金)
1500
2/3
18
0.015
x 2 x
22/3
x
1500
1500,
V1500
1
38.72983
-0.0258
Where:
⚫ Q = Discharge (m³/s)
⚫n Manning's roughness coefficient
⚫ A = Cross-sectional area of flow (m²)
⚫R Hydraulic radius (m)
⚫ S = Slope of the bed
⚫ A is calculated as A =Bxd, where B is the bottom width and d is the depth of the channel.
Since we are designing the most efficient rectangular section, we can assume the bottom width B -
2d, where d is the depth.
Hydraulic Radius R:
The hydraulic radius R is defined as:
Calculate the constant ()/2
Now the equation becomes:
Simplify further:
where:
R-
⚫P is the wetted perimeter (m).
For a rectangular channel, the wetted perimeter is:
Thus:
18-
x2dx
0.015
f/3
x 0.0258
22/3
18->
2d²x²/3
0.015 x 22/3
x 0.0258
To simplify this equation, we'll use the value 22/3 1.587, so:
Now, compute the constants:
20/3
0.015 x 1.587
x 0.0258
0.015 x 1.587 0.023805
P B+2d 2d +2d-4d
0.023805 x 0.0258 0.0006137
Thus, the equation becomes:
2d²
d
P 4d
18-
2/3
0.0006137
Solve for d
Now, solve for d
18 x 0.0006137
2
-0.0055344
d=(0.0055344) 0.4775m
So, the flow depth d is approximately 0.48 meters.
Width of the Channel B:
Since B-2d, the bottom width is
B-2x 0.48 0.96 m
Step 3: Cross-sectional Area and Hydraulic Radius
Now we can calculate the cross-sectional area (A) and hydraulic radius (R):
A-Bxd-0.96 x 0.48 -0.4608 m²
d 0.48
R-
2
-0.24 m
Step 4: Cost Estimate
To estimate the cost of the channel, we need to consider the following:
1. Excavation Cost: The volume of soil removed to create the channel is approximately A x
Length of the Channel. For simplicity, we'll assume a unit length of 1 meter.
Volume to excavate: 0.4608 m2 x 1m 0.4608 m³
Cost per cubic meter of excavation (assuming 50 USD/m³
Excavation cost -0.4608 x 50 - 23.04 USD
2. Concrete Lining Cost (if needed): Assuming the channel is lined with concrete and the cost is
150 USD/m².
Surface area of the channel: P x Length - 4 x 0.48 - 1.92 m²
• Concrete lining cost
Lining cost 1.92 x 150-288 USD
Step 5: Structural Analysis
1. Shear Stress at the Bed: The shear stress at the bed r can be calculated using:
T-pgSR
Transcribed Image Text:Make Sure That this is correct, because the answer in mannings equation is wrong. Detailed Solution for Open Channel Design (Rectangular Section) We will design a rectangular open channel with the given specifications and provide detailed calculations for discharge, cost estimate, and structural analysis. Given Data: ⚫Discharge (Q: 18 m³/s • Bed Slope (5): S- (bed slope) Manning's Roughness Coefficient (n): -0.015 Channel Shape: Rectangular section ⚫Efficiency Goal: Minimize friction loss by designing a hydraulically efficient section Now, substitute this into Manning's equation: 9-() Substitute values: 2/3 8/2 18 (2d) *-*)()()" 0.015 Now, let's simplify this expression step by step. Step 2: Simplifying and Solving for d 1500 Step 1: Hydraulic Design of the Rectangular Channel Manning's Equation for Open Channel Flow: Manning's equation describes the flow in an open channel 1 0.015 First, simplify the term () Now, substitute this into the equation: -(0)-()" (金) 1500 2/3 18 0.015 x 2 x 22/3 x 1500 1500, V1500 1 38.72983 -0.0258 Where: ⚫ Q = Discharge (m³/s) ⚫n Manning's roughness coefficient ⚫ A = Cross-sectional area of flow (m²) ⚫R Hydraulic radius (m) ⚫ S = Slope of the bed ⚫ A is calculated as A =Bxd, where B is the bottom width and d is the depth of the channel. Since we are designing the most efficient rectangular section, we can assume the bottom width B - 2d, where d is the depth. Hydraulic Radius R: The hydraulic radius R is defined as: Calculate the constant ()/2 Now the equation becomes: Simplify further: where: R- ⚫P is the wetted perimeter (m). For a rectangular channel, the wetted perimeter is: Thus: 18- x2dx 0.015 f/3 x 0.0258 22/3 18-> 2d²x²/3 0.015 x 22/3 x 0.0258 To simplify this equation, we'll use the value 22/3 1.587, so: Now, compute the constants: 20/3 0.015 x 1.587 x 0.0258 0.015 x 1.587 0.023805 P B+2d 2d +2d-4d 0.023805 x 0.0258 0.0006137 Thus, the equation becomes: 2d² d P 4d 18- 2/3 0.0006137 Solve for d Now, solve for d 18 x 0.0006137 2 -0.0055344 d=(0.0055344) 0.4775m So, the flow depth d is approximately 0.48 meters. Width of the Channel B: Since B-2d, the bottom width is B-2x 0.48 0.96 m Step 3: Cross-sectional Area and Hydraulic Radius Now we can calculate the cross-sectional area (A) and hydraulic radius (R): A-Bxd-0.96 x 0.48 -0.4608 m² d 0.48 R- 2 -0.24 m Step 4: Cost Estimate To estimate the cost of the channel, we need to consider the following: 1. Excavation Cost: The volume of soil removed to create the channel is approximately A x Length of the Channel. For simplicity, we'll assume a unit length of 1 meter. Volume to excavate: 0.4608 m2 x 1m 0.4608 m³ Cost per cubic meter of excavation (assuming 50 USD/m³ Excavation cost -0.4608 x 50 - 23.04 USD 2. Concrete Lining Cost (if needed): Assuming the channel is lined with concrete and the cost is 150 USD/m². Surface area of the channel: P x Length - 4 x 0.48 - 1.92 m² • Concrete lining cost Lining cost 1.92 x 150-288 USD Step 5: Structural Analysis 1. Shear Stress at the Bed: The shear stress at the bed r can be calculated using: T-pgSR
where:
• p = density of water 1000 kg/m³
⚫ g = acceleration due to gravity 9.81 m/s²
⚫ S = slope 1500
⚫ R = hydraulic radius 0.24 m
1
T1000 × 9.81 ×
x 0.24 1.57 Pa
1500
This shear stress is within acceptable limits for a concrete-lined channel.
Transcribed Image Text:where: • p = density of water 1000 kg/m³ ⚫ g = acceleration due to gravity 9.81 m/s² ⚫ S = slope 1500 ⚫ R = hydraulic radius 0.24 m 1 T1000 × 9.81 × x 0.24 1.57 Pa 1500 This shear stress is within acceptable limits for a concrete-lined channel.
Expert Solution
steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Recommended textbooks for you
Fundamentals of Geotechnical Engineering (MindTap…
Fundamentals of Geotechnical Engineering (MindTap…
Civil Engineering
ISBN:
9781305635180
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Principles of Geotechnical Engineering (MindTap C…
Principles of Geotechnical Engineering (MindTap C…
Civil Engineering
ISBN:
9781305970939
Author:
Braja M. Das, Khaled Sobhan
Publisher:
Cengage Learning
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781305081550
Author:
Braja M. Das
Publisher:
Cengage Learning
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning