I. Gannt Chart. Contractors for a building restoration project will have to do the following: For the precedence relationships of the activities, assume the following: 1. The wall/ceiling activities, the flooring activities, and the exterior activities are listed in the order in which they are to be performed. 2. Cleaning removing the old carpeting, and sanding and repairing the exterior must precede any painting activity (interior and exterior). 3. The walls/ceilings must be painted before the hardwood flooring is installed, stained, and sealed. 4. All painting (interior and exterior) must be completed before new rugs and carpet runners are installed. 5. Stripping the wallpaper, removing the old carpeting, and sanding and repairing the exterior may all start at the same time. Wall/Ceiling Activities A Strip the existing wall paper B Clean and repair the walls/ceilings C Paint the walls/ceilings and repairing the walls/ceilings, Flooring Activities D Remove old carpeting E Lay a floor foundation F Install, stain, and seal hardwood flooring G Install rugs and carpet runners Exterior Activities H Sand and repair outside wood surfaces I Paint the exterior a. If the estimated time of each wall/ceiling activity is two weeks, the estimated time of each flooring activity is one week, and the estimated time of each exterior activity is three weeks, fill out the Immediate Predecessor/s column in the table below and draw the Gannt Chart corresponding to this project. Weeks after start Immediate Predecessor/s 0 2 3 4 5 6 7 8 9 10 Activity 1 A В C D E F H I p. What is the expected project completion time? c. Which are the critical activities?
I. Gannt Chart. Contractors for a building restoration project will have to do the following: For the precedence relationships of the activities, assume the following: 1. The wall/ceiling activities, the flooring activities, and the exterior activities are listed in the order in which they are to be performed. 2. Cleaning removing the old carpeting, and sanding and repairing the exterior must precede any painting activity (interior and exterior). 3. The walls/ceilings must be painted before the hardwood flooring is installed, stained, and sealed. 4. All painting (interior and exterior) must be completed before new rugs and carpet runners are installed. 5. Stripping the wallpaper, removing the old carpeting, and sanding and repairing the exterior may all start at the same time. Wall/Ceiling Activities A Strip the existing wall paper B Clean and repair the walls/ceilings C Paint the walls/ceilings and repairing the walls/ceilings, Flooring Activities D Remove old carpeting E Lay a floor foundation F Install, stain, and seal hardwood flooring G Install rugs and carpet runners Exterior Activities H Sand and repair outside wood surfaces I Paint the exterior a. If the estimated time of each wall/ceiling activity is two weeks, the estimated time of each flooring activity is one week, and the estimated time of each exterior activity is three weeks, fill out the Immediate Predecessor/s column in the table below and draw the Gannt Chart corresponding to this project. Weeks after start Immediate Predecessor/s 0 2 3 4 5 6 7 8 9 10 Activity 1 A В C D E F H I p. What is the expected project completion time? c. Which are the critical activities?
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 2 images
Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.