Hart Manufacturing makes three products. Each product requires manufacturing operations in three departments: A, B, and C. The labor-hour requirements, by department, are as follows. Department Product 1 Product 2 Product 3 A 1.50 3.00 2.00 B 2.00 1.00 2.50 C 0.25 0.25 0.25 During the next production period, the labor-hours available are 450 in department A, 350 in department B, and 50 in department C. The profit contributions per unit are $28 for product 1, $30 for product 2, and $32 for product 3. (a) Formulate a linear programming model for maximizing total profit contribution (in $). (Let Pi = units of product i produced, for i = 1, 2, 3.) Max s.t.Department A Department B Department C P1, P2, P3 ≥ 0 (b) Solve the linear program formulated in part (a). How much of each product should be produced, and what is the projected total profit contribution (in dollars)? (P1, P2, P3) = with profit $ . (c) After evaluating the solution obtained in part (b), one of the production supervisors noted that production setup costs had not been taken into account. The supervisor noted that setup costs are $360 for product 1, $600 for product 2, and $570 for product 3. If the solution developed in part (b) is to be used, what is the total profit contribution (in dollars) after taking into account the setup costs? $ (d) Management realized that the optimal product mix, taking setup costs into account, might be different from the one recommended in part (b). Formulate a mixed-integer linear program that takes setup costs in part (c) into account. Management also stated that we should not consider making more than 145 units of product 1, 150 units of product 2, or 160 units of product 3. (Let Pi = units of product i produced and yi be the 0-1 variable that is one if any quantity of product i is produced and zero otherwise, for i = 1, 2, 3.) What is the objective function of the mixed-integer linear program? Max In addition to the constraints from part (a), what other constraints should be added to the mixed-integer linear program? s.t.units of Product 1 produced units of Product 2 produced units of Product 3 produced P1, P2, P3 ≥ 0; y1, y2, y3 = 0, 1 (e) Solve the mixed-integer linear program formulated in part (d). How much of each product should be produced, and what is the projected total profit contribution (in dollars)? (P1, P2, P3, y1, y2, y3) = with profit $ .
Hart Manufacturing makes three products. Each product requires manufacturing operations in three departments: A, B, and C. The labor-hour requirements, by department, are as follows. Department Product 1 Product 2 Product 3 A 1.50 3.00 2.00 B 2.00 1.00 2.50 C 0.25 0.25 0.25 During the next production period, the labor-hours available are 450 in department A, 350 in department B, and 50 in department C. The profit contributions per unit are $28 for product 1, $30 for product 2, and $32 for product 3. (a) Formulate a linear programming model for maximizing total profit contribution (in $). (Let Pi = units of product i produced, for i = 1, 2, 3.) Max s.t.Department A Department B Department C P1, P2, P3 ≥ 0 (b) Solve the linear program formulated in part (a). How much of each product should be produced, and what is the projected total profit contribution (in dollars)? (P1, P2, P3) = with profit $ . (c) After evaluating the solution obtained in part (b), one of the production supervisors noted that production setup costs had not been taken into account. The supervisor noted that setup costs are $360 for product 1, $600 for product 2, and $570 for product 3. If the solution developed in part (b) is to be used, what is the total profit contribution (in dollars) after taking into account the setup costs? $ (d) Management realized that the optimal product mix, taking setup costs into account, might be different from the one recommended in part (b). Formulate a mixed-integer linear program that takes setup costs in part (c) into account. Management also stated that we should not consider making more than 145 units of product 1, 150 units of product 2, or 160 units of product 3. (Let Pi = units of product i produced and yi be the 0-1 variable that is one if any quantity of product i is produced and zero otherwise, for i = 1, 2, 3.) What is the objective function of the mixed-integer linear program? Max In addition to the constraints from part (a), what other constraints should be added to the mixed-integer linear program? s.t.units of Product 1 produced units of Product 2 produced units of Product 3 produced P1, P2, P3 ≥ 0; y1, y2, y3 = 0, 1 (e) Solve the mixed-integer linear program formulated in part (d). How much of each product should be produced, and what is the projected total profit contribution (in dollars)? (P1, P2, P3, y1, y2, y3) = with profit $ .
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Hart Manufacturing makes three products. Each product requires manufacturing operations in three departments: A, B, and C. The labor-hour requirements, by department, are as follows.
Department | Product 1 | Product 2 | Product 3 |
---|---|---|---|
A | 1.50 | 3.00 | 2.00 |
B | 2.00 | 1.00 | 2.50 |
C | 0.25 | 0.25 | 0.25 |
During the next production period, the labor-hours available are 450 in department A, 350 in department B, and 50 in department C. The profit contributions per unit are $28 for product 1, $30 for product 2, and $32 for product 3.
(a)
Formulate a linear programming model for maximizing total profit contribution (in $). (Let
Pi =
units of product i produced, for
i = 1, 2, 3.)
Max
s.t.Department A
Department B
Department C
P1, P2, P3 ≥ 0
(b)
Solve the linear program formulated in part (a). How much of each product should be produced, and what is the projected total profit contribution (in dollars)?
(P1, P2, P3) =
with profit $ .(c)
After evaluating the solution obtained in part (b), one of the production supervisors noted that production setup costs had not been taken into account. The supervisor noted that setup costs are $360 for product 1, $600 for product 2, and $570 for product 3. If the solution developed in part (b) is to be used, what is the total profit contribution (in dollars) after taking into account the setup costs?
$
(d)
Management realized that the optimal product mix, taking setup costs into account, might be different from the one recommended in part (b). Formulate a mixed-integer linear program that takes setup costs in part (c) into account. Management also stated that we should not consider making more than 145 units of product 1, 150 units of product 2, or 160 units of product 3. (Let
Pi =
units of product i produced and
yi
be the 0-1 variable that is one if any quantity of product i is produced and zero otherwise, for
i = 1, 2, 3.)
What is the objective function of the mixed-integer linear program?
Max
In addition to the constraints from part (a), what other constraints should be added to the mixed-integer linear program?
s.t.units of Product 1 produced
units of Product 2 produced
units of Product 3 produced
P1, P2, P3 ≥ 0; y1, y2, y3 = 0, 1
(e)
Solve the mixed-integer linear program formulated in part (d). How much of each product should be produced, and what is the projected total profit contribution (in dollars)?
(P1, P2, P3, y1, y2, y3) =
with profit $ .Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Step 1: Examine - Given details:
VIEWStep 2: a) Examine - Objective Functions and Constraints:
VIEWStep 3: b) Calculate - Total profit:
VIEWStep 4: b) Calculate - Total profit:
VIEWStep 5: c) Calculate - Net profit:
VIEWStep 6: d) Examine - Objective Functions and Constraints:
VIEWStep 7: e) Calculate - Total profit:
VIEWStep 8: e) Calculate - Total profit:
VIEWSolution
VIEWTrending now
This is a popular solution!
Step by step
Solved in 9 steps with 18 images
Follow-up Questions
Read through expert solutions to related follow-up questions below.
Follow-up Question
For step 8, I'm trying to understand why the Constraints for P1, P2, and P3 are all 1 in the table in cells B9, C10, D11
Solution
by Bartleby Expert
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.