The senior management team at ABC Corp. are assessing where a recent project went wrong. There were issues at all areas of management but the item that most strongly suggests that there may have been planning failures is ________. Question 14 options: A) the controlling issues the project experienced were commonly experienced by other project leaders in this industry B) suppliers of components for the project had to produce at maximum capacity which turned out to be impossible C) even if planning had been effective, the project would have failed due to management style D) there was a failure to monitor production output E) two employees who were assigned to the project couldn't stand each other
The senior management team at ABC Corp. are assessing where a recent project went wrong. There were issues at all areas of management but the item that most strongly suggests that there may have been planning failures is ________.
Question 14 options:
|
|
||
|
|
||
|
|
||
|
|
||
|
|